CCW Ranch, LLC v. Nielsen

2012 UT App 205, 283 P.3d 1072, 2012 WL 3054117, 2012 Utah App. LEXIS 211
CourtCourt of Appeals of Utah
DecidedJuly 27, 2012
Docket20090776-CA
StatusPublished
Cited by1 cases

This text of 2012 UT App 205 (CCW Ranch, LLC v. Nielsen) is published on Counsel Stack Legal Research, covering Court of Appeals of Utah primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
CCW Ranch, LLC v. Nielsen, 2012 UT App 205, 283 P.3d 1072, 2012 WL 3054117, 2012 Utah App. LEXIS 211 (Utah Ct. App. 2012).

Opinion

MEMORANDUM DECISION

ORME, Judge:

1 1 This case arises as a result of a dispute regarding fencing along boundaries shared by Plaintiff CCW Ranch and Defendants Chris and Sunny Nielsen. The parties at various times have insisted or denied that they had an agreement that each would take responsibility for rebuilding or repairing one of the sections of fence along their two common borders. Plaintiff was once the main proponent of the idea that such an agreement had been reached but now resists that proposition. Defendants were earlier lukewarm on the notion that there was an agreement, but, at least given the totality of the trial court's disposition, now endorse the idea. Plaintiff is adamant that Defendants breached any such agreement that there might have been, either by their significant delay in beginning their part of the fence construction or by doing the work in an incomplete or shoddy fashion. On alternative theories that there was no contract or, if there was, it was breached, Plaintiff also sought to recover half the cost of construction of proper fencing along its boundaries with Defendants, per Plaintiffs interpretation of Utah Code section 4-26-5.1. See Utah Code Ann. § 4-26-5.1(8) (2006).

T2 Following a bench trial, during which the court heard conflicting evidence and made its credibility assessments, the court entered detailed findings of fact. It concluded that the parties had an agreement for refurbishing the fences in question and that each party had fulfilled its obligations pursuant to the agreement. While the south fence work did not satisfy government standards and both the north and south fences had problems with moisture and "sway," the fences were, according to the trial court, on par with many others in the area and "appeared] to be doing the job [they were] intended to do," namely, keeping cattle where they belonged.

3 While Plaintiff has pointed to evidence in the record that could have supported findings more favorable to Plaintiff, it has not demonstrated that the findings entered by the trial court are clearly erroneous, i.e., that they lack adequate evidentiary support. See Chen v. Stewart, 2004 UT 82, 119, 100 P.8d 1177 ("A trial court's findings of fact will not be set aside unless clearly erroneous.... [TJo establish that a particular finding of fact is clearly erroneous, [a)n appellant must marshal the evidence in support of the findings and then demonstrate that despite this evidence, the trial court's findings are so lacking in support as to be against the clear weight of the evidence.") (second alteration in original) (citation and internal quotation marks omitted). Accordingly, we decline to disturb the findings made by the trial court and take them as our starting point in considering Plaintiff's legal arguments. 1 See id. See *1074 also Kimball v. Kimball, 2009 UT App 233, ¶ 20 n. 5, 217 P.3d 733 ("No matter what contrary facts might have been found from all the evidence, our deference to the trial court's pre-eminent role as fact-finder requires us to take the findings of fact as our starting point, unless particular findings have been shown, in the course of an appellant's meeting the marshaling requirement, to lack legally adequate evidentiary support.").

14 Given those findings, we do not agree with Plaintiff's primary argument that the agreement was too vague or indefinite to be enforceable. The section of fence for which each party was responsible was always clearly understood. And each party understood that they would bear the costs attributable to the fence for which that party had responsibility. The parties did not have an express understanding about the materials to be used but each assumed, as evidenced by their subsequent course of conduct, that the reconstructed fence would have to "hold up," that it would be "a good fence ... common with the other fences found around the County," and that the repaired or rebuilt fence "would be adequate to keep the cattle enclosed in the respective owners' property."

15 Second, we cannot agree that Defendants' delay in performing constituted a breach as a matter of law. There was no explicit agreement about when each party had to perform, so the law implies a reasonable time for performance. See Cooper v. Deseret Fed. Sav. & Loan Ass'n, 757 P.2d 483, 485 (Utah Ct.App.1988). That the time of Defendants' performance was not unreasonably late is implicit in the trial court's finding number ten 2 and is buttressed by the fact, as acknowledged in the testimony of Plaintiff's principal, that although Plaintiff started its work long before Defendants, Defendants finished their work first.

T 6 Third, Plaintiff's argument that Defendant breached the covenant of good faith and fair dealing, which is implied in all Utah contracts, see Eiggeit v. Wasatch Energy Corp., 2004 UT 28, 1 14, 94 P.3d 193, has no basis in the facts as found by the trial court, see generally Young Living Essential Oils, LC v. Marin, 2011 UT 64, ¶¶ 9-10, 266 P.3d 814 (describing the limits of a covenant of good faith and fair dealing and the "high bar" required to demonstrate the existence of such a covenant).

17 Plaintiffs final argument is that the trial court's allocation of responsibility for future maintenance expenses is at odds with the governing statute. Both sides agree that the cost of future maintenance of the fences is governed by section 4-26-5.1(4) of the Utah Code, which provides that "[the cost of the maintenance of the fence shall also be apportioned between each party based upon the amount of land enclosed." *1075 Utah Code Ann. § 4-26-5.1(4) (2006). However, Plaintiff contends that the trial court should determine the "amount of land enclosed" by looking at the "lineal feet of boundary" of each parcel. Defendants, on the other hand, agree with the trial court's calculations, which were based on the acreage of land enclosed by each landowner's fencing of which the boundary fences were a part.

18 "[A] trial court's interpretation of a statute is a question of law that we review for correctness." Blackner v. Department of Transp., 2002 UT 44, ¶ 8, 48 P.3d 949. We interpret statutes according to their plain meaning and "need not look beyond the plain language unless we find some ambiguity." State v. MacGuwire, 2004 UT 4, ¶ 15, 84 P.3d 1171 (citation and internal quotation marks omitted).

19 The statute in issue is by no means a model of precise drafting. We note that it is limited, as a practical matter, to rural areas. See Utah Code Ann. § 4-26-5.1(1)(b) (defining a qualified landowner as a private landowner whose land is used for grazing livestock and is land that qualifies as a "conservation easement" or is "in agricultural use").

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Nielsen v. Cronquist
Court of Appeals of Utah, 2026
State v. Cater
2014 UT App 207 (Court of Appeals of Utah, 2014)

Cite This Page — Counsel Stack

Bluebook (online)
2012 UT App 205, 283 P.3d 1072, 2012 WL 3054117, 2012 Utah App. LEXIS 211, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ccw-ranch-llc-v-nielsen-utahctapp-2012.