CCE, Ltd. F/K/A CCE, Inc. v. Texas Department of Transportation

CourtCourt of Appeals of Texas
DecidedMarch 2, 2011
Docket03-10-00072-CV
StatusPublished

This text of CCE, Ltd. F/K/A CCE, Inc. v. Texas Department of Transportation (CCE, Ltd. F/K/A CCE, Inc. v. Texas Department of Transportation) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
CCE, Ltd. F/K/A CCE, Inc. v. Texas Department of Transportation, (Tex. Ct. App. 2011).

Opinion

TEXAS COURT OF APPEALS, THIRD DISTRICT, AT AUSTIN

NO. 03-10-00072-CV

CCE, Ltd. f/k/a CCE, Inc., Appellant

v.

Texas Department of Transportation, Appellee

FROM THE DISTRICT COURT OF TRAVIS COUNTY, 200TH JUDICIAL DISTRICT NO. D-1-GN-08-002868, HONORABLE SUZANNE COVINGTON, JUDGE PRESIDING

MEMORANDUM OPINION

CCE, Ltd., formerly known as CCE, Inc., appeals a district court judgment affirming

an order by the Texas Department of Transportation (TxDOT) denying CCE’s claims for additional

compensation under a road construction contract. In five issues, CCE complains that the order must

be reversed under the substantial evidence standard of review because TxDOT committed errors of

law and acted arbitrarily and capriciously in failing to follow contract provisions that, CCE asserts,

shifted the costs in dispute to TxDOT rather than CCE. Concluding that the contract as a matter of

law made CCE responsible for the costs in question, we will affirm the district court’s judgment.

The underlying dispute relates to a 1999 contract TxDOT awarded to CCE to

perform work on three existing farm-to-market roads in TxDOT’s Lufkin District, including

FM 3315, a two-lane road. The contract includes standard specifications contained in a 1,233-page

book as well as special provisions, plans, change orders, and other items. The work required of CCE, simply described, consisted of removing portions of the existing roadway surface, reworking

its cementious base, and then building a new asphalt and aggregate surface. The contract provided

that CCE could perform its work by closing one of FM 3315’s two lanes at a time, except

that—under a provision designated as item 502—“[a]t the close of work each day, all traffic lanes

shall be open to traffic,” and provided detailed plans and directives regarding the routing of traffic

and appropriate signage. The contract further provides that “[t]he Engineer will act as referee in all

questions arising under the terms of the contract between the parties thereto and his decisions shall

be final and binding.”

Although the record reflects that the “season” for applying asphalt is typically

between March 1 and October 31, TxDOT’s Lufkin District engineer consented to CCE doing this

work in December 1999. CCE applied the first of what was to be two layers of asphalt to a lane of

FM 3315 on December 14, 1999. During the ensuing days, however, portions of this asphalt layer

stuck to cars traveling over it while the lane was open, exposing the cement base to traffic and still

more damage. TxDOT directed CCE to repair the damage at CCE’s expense. CCE did so, and

eventually completed its work under the contract.

Following completion of the project, CCE sought over $600,000 in additional

compensation for its repair of the damages to FM 3315 through TxDOT’s informal claim resolution

procedures. See Tex. Transp. Code Ann. § 201.112(a) (West Supp. 2010). Dissatisfied with the

outcome of this process, CCE requested a formal contested-case hearing. See id. § 201.112(b)

(West Supp. 2010). TxDOT referred the claim to the State Office of Administrative Hearings

(SOAH). Before the ALJ, CCE contended that TxDOT was responsible for the repair cost because

2 it had specified the wrong type of asphalt for CCE to apply, that the Department’s engineer should

have stopped CCE from applying asphalt on December 14, that special provision 7.12 had shifted

responsibility for road maintenance to TxDOT while the road was opened, and that the Department’s

engineer had departed from the plain language of the contract in a manner constituting gross error.

Following the hearing, the ALJ prepared a proposal for decision rejecting each of CCE’s theories.

The ALJ failed to find or conclude that TxDOT was responsible for the repairs under special

provision 7.12. Instead, it relied on a different provision, standard specification 316.4, which

provides, in relevant part:

The Contractor shall be responsible for the maintenance of each course until covered by the succeeding courses or until the work is accepted by the Engineer. All holes or failures in the surface shall be repaired by use of additional asphalt and aggregate.

The ALJ reasoned that CCE was “responsible for the maintenance” of the first asphalt layer

“until covered by the succeeding courses or until the work is accepted by the Engineer,” neither of

which had occurred before the road was damaged. The ALJ further found that the engineer’s failure

to assume responsibility for the first layer of asphalt was not gross error and concluded that CCE

had failed to prove its entitlement to additional compensation. The ALJ’s proposed findings and

conclusions were adopted by TxDOT’s executive director. See id. § 201.112(c) (West Supp. 2010).

CCE then sought judicial review of TxDOT’s order in the district court. See id.

§ 201.112(d) (West Supp. 2010). Concluding that the order withstood scrutiny under the

Administrative Procedure Act’s “substantial evidence” standard of review, see Tex. Gov’t Code

Ann. § 2001.174 (West 2008), the district court affirmed the order.

3 On appeal, CCE brings five issues that are each predicated on the contention that, as

a matter of law, special provision 7.12 governed the parties’ respective responsibilities during the

evening hours when FM 3315 was open and shifted the cost of repairing damage occurring at that

time to TxDOT.1 Special provision 7.12 provides, in relevant part:

Contractor’s Responsibility for Work. Until final written acceptance of the project by the Engineer, the contractor shall have the charge and care thereof and shall take every precaution against injury or damage to any part thereof by the action of the elements or from any other cause, whether arising from the execution or from the nonexecution of the work.

....

Wherever in the opinion of the Engineer, any roadway or portion thereof is in suitable condition for travel, it shall be opened to traffic, as may be directed, and such opening shall not be held to be in any way the final acceptance of the roadway or any part of the provisions of the contract. Where it is considered by the Engineers to be in the public interest and so ordered in writing by him, any substantially completed roadway or portion thereof may be opened to traffic as follows:

(1) When required by plans, job sequence or the approved traffic control plan, with the Department accepting responsibility for maintaining that portion of the roadway opened to traffic.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Valence Operating Co. v. Dorsett
164 S.W.3d 656 (Texas Supreme Court, 2005)
Frost National Bank v. L & F Distributors, Ltd.
165 S.W.3d 310 (Texas Supreme Court, 2005)
Seagull Energy E & P, Inc. v. Eland Energy, Inc.
207 S.W.3d 342 (Texas Supreme Court, 2006)
Coker v. Coker
650 S.W.2d 391 (Texas Supreme Court, 1983)
Cities of Abilene v. PUBLIC UTILITY COM'N OF TEXAS
146 S.W.3d 742 (Court of Appeals of Texas, 2004)

Cite This Page — Counsel Stack

Bluebook (online)
CCE, Ltd. F/K/A CCE, Inc. v. Texas Department of Transportation, Counsel Stack Legal Research, https://law.counselstack.com/opinion/cce-ltd-fka-cce-inc-v-texas-department-of-transpor-texapp-2011.