CCE, Inc. v. PBS&J Construction Services, Inc. Post, Buckley, Schuh & Jernigan, Inc. And Yu-Chun Su, P.E.

CourtCourt of Appeals of Texas
DecidedJanuary 28, 2011
Docket01-09-00040-CV
StatusPublished

This text of CCE, Inc. v. PBS&J Construction Services, Inc. Post, Buckley, Schuh & Jernigan, Inc. And Yu-Chun Su, P.E. (CCE, Inc. v. PBS&J Construction Services, Inc. Post, Buckley, Schuh & Jernigan, Inc. And Yu-Chun Su, P.E.) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
CCE, Inc. v. PBS&J Construction Services, Inc. Post, Buckley, Schuh & Jernigan, Inc. And Yu-Chun Su, P.E., (Tex. Ct. App. 2011).

Opinion

Opinion issued January 28, 2011

In The

Court of Appeals

For The

First District of Texas

————————————

NO. 01-09-00040-CV

———————————

CCE, Inc., Appellant

V.

PBS&J Construction Services, Inc.; Post, Buckley, Schuh & Jernigan, Inc.; and Yu-Chun Su, P.E., Appellees

On Appeal from the 215th District Court

Harris County, Texas

Trial Court Case No. 2006-46041

MEMORANDUM OPINION

Appellant, CCE, Inc., challenges the trial court’s rendition of summary judgment in favor of appellees, PBS&J Construction Services, Inc.; Post, Buckley, Schuh & Jernigan, Inc.; and Yu-Chen Su, P.E. (collectively “PBS&J”), on CCE’s claims against PBS&J for negligent misrepresentation and breach of warranty.  In two of its three issues, CCE contends that the trial court erred in rendering summary judgment against CCE (1) on its negligent-misrepresentation claim on the grounds that PBS&J made no affirmative misrepresentation of material fact and the economic-loss rule bars recovery of CCE’s “benefit-of-the-bargain damages” and (2) on its breach-of-warranty claim on the grounds that PBS&J was “not in privity [of contract] with CCE” and PBS&J made no express representation to CCE about the quality or character of its services.  Alternatively, in its third issue, CCE contends that it should now be allowed to raise a claim against PBS&J for equitable subrogation.  In a styled “cross-appeal,”[1] PBS&J contends that the trial court erred in denying it summary judgment on CCE’s negligent-misrepresentation claim on the ground that PBS&J did not proximately cause CCE’s alleged damages.

          We affirm the trial court’s judgment in part, reverse the trial court’s judgment in part, and remand for further proceedings.

Background

          The critical facts are largely undisputed.  The Texas Department of Transportation (“TxDOT”) hired PBS&J to draft engineering plans and specifications for a new road, FM 2435, in Nacogdoches County (the “road project”).  PBS&J devised the plans, including a “Storm Water Pollution Prevention Plan” (the “SW3P”), which was required by a general surface‑water discharge permit (the “permit”), issued by the Texas Commission on Environmental Quality (“TCEQ”), for the road project to prevent pollution from wastewater discharges entering into nearby waterways in violation of the Clean Water Act.[2]

          TxDOT awarded the construction contract for the road project to CCE, a general contractor.  TxDOT’s “Standard Specifications for Construction of Highways, Streets and Bridges” generally requires that all work performed by a contractor on a TxDOT project must be in conformity with TxDOT plans, unless a deviation is approved by the TxDOT engineer responsible for the project.  CCE alleged that it was contractually bound to configure erosion control measures for the road project in compliance with the SW3P designed by PBS&J and that it, in fact, complied with the SW3P.

          TxDOT, on December 22, 2004, notified CCE that silt had discharged from the road project and accumulated on nearby private property, and TxDOT instructed CCE to suspend work on the road project until “all erosion control measures [were] in place.”  On January 7, 2005, TxDOT expressed to CCE that it believed that the erosion and “siltation” problems arose from CCE’s “failure to provide the control measures required by the plans.”  And TxDOT notified CCE that it had ten days to correct the alleged contract violations, or CCE would be considered in default under the construction contract.  On January 18, 2005, TxDOT declared CCE in default, ordered CCE to cease work, and notified CCE’s surety that it was obligated to arrange for completion of the road project.

CCE then hired Longview Road and Bridge, Ltd. (“LR&B”) to complete the road project.  In its summary‑judgment evidence, CCE included the affidavit of its Financial Control Officer, Phil Mahar, who testified that hiring LR&B to complete the road project caused CCE to spend $2,423,752.20 more than it would have had it been able to complete the project on its own.

In its Fifth Amended Original Petition, CCE, in regard to its negligent misrepresentation claim, alleged that PBS&J “recklessly” or “without reasonable care” submitted the SW3P to TxDOT knowing that construction contractors like CCE would bid on and attempt to build the road project in reliance on the SW3P.  CCE further alleged that the SW3P “contained numerous false statements of material existing fact including, but not limited to, the representation[s] that it was an instrument of service resulting from an engineering process when it was not, that it complied with the [p]ermit and [TxDOT] [g]uidelines, and that if CCE followed it, the [engineering] [p]lans and SW3P would work.”  In regard to its breach­‑of‑warranty claim, CCE alleged that PBS&J “provided express and written warranties and represented that its [p]lans and SW3P conformed to the [p]ermit and [g]uidelines, when they did not.”  CCE further alleged that PBS&J represented that the engineering plans and the SW3P “were instruments of services resulting from an engineering process, when they were not”; PBS&J “admitted that it expressly warranted and represented that if CCE followed the [p]lans and SW3P, they would work; and the plans and SW3P did not “conform with the [p]ermit and [g]uidelines and the SW3P did not work.”  CCE did not assert a claim for equitable subrogation against PBS&J.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Ford Motor Co. v. Ridgway
135 S.W.3d 598 (Texas Supreme Court, 2004)
Fort Worth Osteopathic Hospital, Inc. v. Reese
148 S.W.3d 94 (Texas Supreme Court, 2004)
Indust-Ri-Chem Laboratory, Inc. v. Par-Pak Co.
602 S.W.2d 282 (Court of Appeals of Texas, 1980)
Spradlin v. State
100 S.W.3d 372 (Court of Appeals of Texas, 2003)
Merrell Dow Pharmaceuticals, Inc. v. Havner
953 S.W.2d 706 (Texas Supreme Court, 1997)
Baker Hughes, Inc. v. KECO R. & D., INC.
12 S.W.3d 1 (Texas Supreme Court, 2000)
General Mills Restaurants, Inc. v. Texas Wings, Inc.
12 S.W.3d 827 (Court of Appeals of Texas, 2000)
Cincinnati Life Insurance Co. v. Cates
927 S.W.2d 623 (Texas Supreme Court, 1996)
Blair v. Fletcher
849 S.W.2d 344 (Texas Supreme Court, 1993)
Cathey v. Booth
900 S.W.2d 339 (Texas Supreme Court, 1995)
Paragon General Contractors, Inc. v. Larco Construction Inc.
227 S.W.3d 876 (Court of Appeals of Texas, 2007)
U.S. Tire-Tech, Inc. v. Boeran, B.V.
110 S.W.3d 194 (Court of Appeals of Texas, 2003)
Nixon v. Mr. Property Management Co.
690 S.W.2d 546 (Texas Supreme Court, 1985)
Yazdchi v. Bank One, Texas, N.A.
177 S.W.3d 399 (Court of Appeals of Texas, 2005)
Edwards v. Schuh
5 S.W.3d 829 (Court of Appeals of Texas, 1999)
Sterling Chemicals, Inc. v. Texaco Inc.
259 S.W.3d 793 (Court of Appeals of Texas, 2007)
Westgate, Ltd. v. State
843 S.W.2d 448 (Texas Supreme Court, 1992)
Murphy v. Campbell
964 S.W.2d 265 (Texas Supreme Court, 1998)
Federal Land Bank Ass'n of Tyler v. Sloane
825 S.W.2d 439 (Texas Supreme Court, 1992)

Cite This Page — Counsel Stack

Bluebook (online)
CCE, Inc. v. PBS&J Construction Services, Inc. Post, Buckley, Schuh & Jernigan, Inc. And Yu-Chun Su, P.E., Counsel Stack Legal Research, https://law.counselstack.com/opinion/cce-inc-v-pbsj-construction-services-inc-post-buck-texapp-2011.