CC-Aventura, Inc. v. Weitz Company, LLC

Procedural entryThis page is a short order in CC-Aventura, Inc. v. Weitz Company, LLC. Read the opinion of the Court — 492 F. App'x 54
Court of Appeals for the Eleventh Circuit·Decided October 11, 2012·No. 11-11191·Unpublished

Opinion

Case: 11-11191 Date Filed: 10/11/2012 Page: 1 of 7

[DO NOT PUBLISH]

IN THE UNITED STATES COURT OF APPEALS

FOR THE ELEVENTH CIRCUIT ________________________

No. 11-11191 ________________________

D. C. Docket No. 1:06-cv-21598-PCH

CC-AVENTURA, INC.,

Plaintiff - Counter Defendant - Appellee,

CLASSIC RESIDENCE MANAGEMENT LIMITED PARTNERSHIP,

Plaintiff - Appellee,

versus

WEITZ COMPANY, LLC,

Defendant - Cross Defendant - Cross Claimant - Counter Claimant - Third Party Plaintiff - Counter Defendant - Appellant.

________________________

Appeal from the United States District Court for the Southern District of Florida _________________________

(October 11, 2012)

Before DUBINA, Chief Judge, and PRYOR and ANDERSON, Circuit Judges. Case: 11-11191 Date Filed: 10/11/2012 Page: 2 of 7

PER CURIAM:

In this surety case, obligee/contractor Weitz contends that the district court

erred by failing to properly follow the majority opinion in Dooley & Mack

Constructors, Inc. v. Developers Surety & Indemnity Co., 972 So. 2d 893 (Fla.

Dist. Ct. App. 2007). The district court concluded that the surety Fidelity was not

liable on a surety bond because Weitz had failed to give notice to Fidelity of the

subcontractor Aero’s default before Weitz undertook to remedy the default itself.

In Dooley, the subcontractor defaulted on its obligations. Id. at 894. Rather

than notify the surety, the obligee/contractor remedied the default itself and then

brought suit against the surety. Id. The majority in Dooley interpreted the surety

bond (which included by incorporation the subcontract between the

obligee/contractor and the subcontractor) to have two alternative routes by which

the surety could face liability if the subcontractor defaulted on its obligations: (1)

the bond itself stated that the obligee/contractor could notify the surety of the

default and require that the surety remedy the default; or (2) the subcontract

(incorporated into the bond) stated that the obligee/contractor could remedy the

default itself and then later sue the surety to cover the shortfall.

The Dooley majority conceded that if the obligee/contractor had proceeded

under the first route, then it would have been required to first give notice to the

2 Case: 11-11191 Date Filed: 10/11/2012 Page: 3 of 7

surety, because that provision was included with “standard” surety bond language

that requires the obligee/contractor to first give notice. Id.1 But the court

concluded that the second route (where the obligee/contractor could remedy the

default itself) did not include any of the “standard” surety language that requires

notification, id. at 895, and it also did not include any other language explicitly

requiring notice to be given, id. (citing RLI Ins. Co. v. St. Patrick’s Home for the

Infirm & Aged, 452 F. Supp. 2d 484 (S.D.N.Y. 2006), for the proposition that the

“absence of [an] explicit notice requirement of principal’s default to surety

distinguishes cases finding that notice is condition precedent to surety’s payment

under bond.”). Since the obligee/contractor proceeded under this second route, it

did not have to give prior notice to the surety.

In the case sub judice, the bond (and, by incorporation, the subcontract)

similarly has two routes by which the surety could be exposed to liability if the

subcontractor defaulted: the surety could undertake to remedy the default, or the

obligee/contractor could undertake to remedy the default. But unlike the scenario

in Dooley, the record in this case shows that both routes did include an explicit

1 The Dooley majority noted that “[u]nder a familiar term of a ‘standard’ surety bond, which is included in this one, such a failure [to first provide notice to the surety] would indeed result in a termination of the surety’s obligations.” Dooley, 972 So. 2d at 894. The “familiar term” of a “standard” surety bond in Dooley was quoted as: “Whenever subcontractor shall be, and declared by Obligee to be in default under the Subcontract, . . . the Surety may promptly remedy the default . . . .” Id. at 894 n.1 (emphasis in original).

3 Case: 11-11191 Date Filed: 10/11/2012 Page: 4 of 7

requirement that notice first be given to the surety,2 and it also was included along

with the same provision as the “standard” language that would require notice to

first be given (as Dooley itself acknowledged).

In other words, the language of the relevant documents in Dooley was

different from the relevant language here. In Dooley, the subcontract gave the

general contractor “the option, but not the obligation, to notify.” In contrast, the

subcontract in this case made reference to Weitz’s ability to remedy the default, but

only after Weitz terminated the subcontractor’s performance for cause, and thus

only after reasonable notice.3 Reading all the language in the relevant documents

2 The pertinent part of the bond stated:

Whenever Principal shall be, and be declared by Obligee to be in default under the subcontract, the Obligee having performed Obligee’s obligations thereunder:

(1) Surety may promptly remedy the default subject to the provisions of paragraph 3 herein, or;

(2) Obligee after reasonable notice to Surety may, or Surety upon demand of Obligee may arrange for the performance of Principal’s obligation under the subcontract subject to the provisions of paragraph 3 herein; . . . .

Doc. 1173-3 (emphasis added). 3 Section 10.1 of the subcontract provided:

If [Aero] fails or neglects to carry out [its] Work in strict compliance with the Subcontract Documents or is otherwise in default of any of its obligations under the Subcontract Documents, and fails to commence and continue correction of such default or neglect with diligence and promptness, [Weitz] may, after 48 hours following delivery to [Aero] of written notice thereof and without prejudice to any other remedy [Weitz] may have, (i) supplement [Aero’s] performance with

4 Case: 11-11191 Date Filed: 10/11/2012 Page: 5 of 7

here harmoniously in order to give effect to all provisions, as Florida law requires,

it is clear in this case that the surety, Fidelity, had a right to reasonable notice

before Weitz undertook to arrange for the performance of the work to cure the

default.4 In Dooley, the obligee/contractor proceeded under a route that did not

additional material, supplies, equipment or labor, pay for same and deduct the amount so paid from any money then or thereafter due [Aero] (if such offset is not sufficient, [Aero] shall pay any deficiency promptly upon demand), or (ii) terminate [Aero’s] continuing performance under the Agreement. Termination of performance may be immediate (without prior notice) in the event of conditions hazardous to persons or property. Such termination of performance shall be deemed for cause, and Section 10.4 [Consequences of Termination for Cause] shall apply thereto.

Section 10.4 provided:

Upon a termination of [Aero’s] continuing performance under the Agreement for cause, [Weitz] may, without limitation to any other available remedies, proceed as follows: (i) direct [Aero] to immediately leave the site, but to give possession of all completed materials and supplies at the site or stored off-site, to [Weitz] for use in completing [Aero’s] Work; .

Free access — add to your briefcase to read the full text and ask questions with AI

CC-Aventura, Inc. v. Weitz Company, LLC, (11th Cir. 2012).

CC-Aventura, Inc. v. Weitz Company, LLC (CC-Aventura, Inc. v. Weitz Company, LLC) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Dooley Constructors v. Developers Sur.
972 So. 2d 893 (District Court of Appeal of Florida, 2007)
RLI Insurance v. St. Patrick's Home for the Infirm & Aged
452 F. Supp. 2d 484 (S.D. New York, 2006)