CBRE v. Super. Ct.

CourtCalifornia Court of Appeal
DecidedJune 4, 2024
DocketD083130
StatusPublished

This text of CBRE v. Super. Ct. (CBRE v. Super. Ct.) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
CBRE v. Super. Ct., (Cal. Ct. App. 2024).

Opinion

Filed 6/4/24

CERTIFIED FOR PUBLICATION

COURT OF APPEAL, FOURTH APPELLATE DISTRICT

DIVISION ONE

STATE OF CALIFORNIA

CBRE et al., D083130 Petitioners, v. (Super. Ct. No. 37-2021- THE SUPERIOR COURT OF SAN 00033025-CU-PO-CTL) DIEGO COUNTY, Respondent; JAKE JOHNSON, Real Party in Interest.

ORIGINAL PROCEEDING on a petition for writ of mandate after the superior court denied summary judgment. Marcella O. McLaughlin, Judge. Petition granted. Niddrie Addams Fuller Singh, John S. Addams; Wingert Grebing Brubaker & Juskie, Alan K. Brubaker, Ian R. Friedman and Steven J. Scordakis for Petitioners. Hoffman & Forde, Michael Dicks; Berding & Weil, Anne L. Rauch and Trinette S. Sachrison for Real Party in Interest. No appearance for Respondent. Jake Johnson was injured while working as an electrician on a construction project in a building owned by Property Reserve, Inc. (PRI) and managed by CBRE (collectively, Petitioners). When injured, Johnson was employed by PCF Electric (PCF), a subcontractor hired by Crew Builders (Crew), the general contractor for the project. Johnson filed a complaint against Petitioners, Crew, and PCF for damages. Petitioners moved for summary judgment based on the Privette doctrine, which generally protects entities that hire independent contractors from liability for injuries sustained by employees of the independent contractor while working on a project. (See Privette v. Superior Court (1993) 5 Cal.4th 689 (Privette).) The trial court denied Petitioners’ motion, finding a triable issue of fact as to when they hired Crew for the project. In the instant petition for writ of mandate, Petitioners assert the trial court erred by focusing on the execution date of the written contract, and they ask this court to issue a writ compelling the trial court to grant their motion for summary judgment. We agree the trial court erred in denying Petitioners’ motion for summary judgment. A written contract is not required to invoke the Privette doctrine, and the undisputed facts establish that Petitioners delegated control over the tenant improvements to Crew prior to Johnson’s injury. The undisputed facts also establish that no exception to the Privette doctrine applies. Prior to Johnson’s injury, Petitioners and Crew mutually agreed to proceed with the project without obtaining permits such that the permitting process was never within the scope of the contracted work. Because the evidence conclusively shows PCF was able to discover any non- code-compliant wiring itself, even in the absence of permits, the “concealed hazardous condition” exception to the Privette doctrine is inapplicable as a matter of law. Further, because the decision to forego the permitting process did not affect the means by which PCF and its employees performed the

2 electrical work for which they were hired or the manner in which they ensured their own safety, the “retained control” exception to the Privette doctrine is equally inapplicable. Because no triable issues of material fact preclude summary judgment, we grant Petitioners’ requested relief. I. PRI owns an office building in San Diego managed by CBRE. On April 9, 2019, PRI entered into a lease agreement with a new tenant for a suite in the building. The lease was to commence on June 1 and required PRI to make certain tenant improvements. During the lease negotiations, Petitioners solicited a bid from Crew to act as the general contractor for the tenant improvement project, and on March 4, Crew submitted its bid. Crew believed a permit was required for the work, as reflected in the bid. The parties began negotiating a formal service contract; however, they had a standing relationship, and it was common for Crew to begin work for Petitioners before finalizing a contract. On March 18, Crew sent CBRE a timeline for the project that still included the permitting process, noting the project would need to begin the following week to meet the tenant’s move-in date. On March 22, CBRE’s senior real estate manager asked for an updated timeline “without a permit,” indicating, “[w]e’ll probably get started on this one right away.” On April 5, PRI requested that CBRE ask Crew to make changes to the bid, including omitting permits because PRI did not think they were needed. Crew’s April 5 bid excluded permits but still included other line items to bring the project “up to code.” On April 8, Crew submitted a revised and final bid excluding additional permit-related line items at Petitioners’ request.

3 PRI’s asset manager “gave the ok to begin” on April 9, and work on the project commenced. In soliciting bids from subcontractors, Crew indicated the project “won’t be permitted.” Crew subcontracted the electrical work on the project to PCF. PCF began work on the project on April 10 but did not execute a formal written subcontract with Crew until April 15. PCF’s April 15 bid included researching the existing electrical system and putting it in “safeoff,” a safe working condition also called “lockout/tagout,” prior to commencing work. PCF’s site superintendent inspected the site, traced the circuits, and performed lockout/tagout prior to demolition at the outset of the project. Johnson was not involved in this process. On April 26, Johnson was working as foreman on the electrical wiring in the suite. Johnson knew no permits had been pulled for the project. He also knew the 277-volt power circuit was turned on to power the building’s lights, as the mandatory temporary lighting had been removed the prior day. However, he believed the 277-volt system was “separate and apart” from the 120-volt system he was working on, as currently required by code. Further, he did not know there were no engineering plans, as-built drawings, as-built plans, building inspections, or plans to bring the building up to code. Prior to April 26, someone had removed the PCF superintendent’s lockout/tagout. While attempting to replace a cover on a junction box labeled as 120-volt and containing wires color-coded as 120-volt under the current code, Johnson touched a live 277-volt wire, fell off a ladder, and sustained serious injuries. According to the deposition testimony of PCF’s site superintendent and person most knowledgeable, “a foreman on a job site like that should not have trusted color codes or voltages,” and he personally uses both his meter and

4 his “hot stick” to test every “[o]utlet, switch, box, anything. Any wire, any electrical.” PCF’s preconstruction manager said PCF protocol was to hot- stick every box, even after inspection and lockout/tagout. Petitioners’ expert similarly opined that best practice is for an electrician to “assume all circuits ‘hot’ until you’ve proved they’re not.” He also opined “[t]here was no possible role for CBRE or PRI in the required lockout/tagout process.” Petitioners and Crew executed their formal service contract on May 13. The contract included a paragraph specifying Crew was to obtain all permits, licenses, and approvals necessary to perform and complete the work, at its sole cost and expense. Johnson filed a complaint against Petitioners, Crew, and PCF for damages arising out of the April 26 incident. After discovery, Petitioners filed a motion for summary judgment, asserting all Johnson’s claims as to them were barred by the Privette doctrine. Johnson opposed, asserting: (1) there was no contract delegating responsibility for workplace safety between Petitioners and Crew or PCF at the time of the incident, and (2) material issues of fact remained as to whether an exception to the Privette doctrine applied. The trial court denied Petitioners’ motion, concluding there was a triable issue of material fact as to when Petitioners hired Crew for the project such that Petitioners were not entitled to judgment as a matter of law.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

SeaBright Insurance v. US Airways, Inc.
258 P.3d 737 (California Supreme Court, 2011)
Privette v. Superior Court
854 P.2d 721 (California Supreme Court, 1993)
Lachapelle v. Toyota Motor Credit Corporation
126 Cal. Rptr. 2d 32 (California Court of Appeal, 2002)
Browne v. Turner Construction Co.
26 Cal. Rptr. 3d 433 (California Court of Appeal, 2005)
Ray v. Silverado Constructors
120 Cal. Rptr. 2d 251 (California Court of Appeal, 2002)
Aguilar v. Atlantic Richfield Co.
24 P.3d 493 (California Supreme Court, 2001)
Miller v. Department of Corrections
115 P.3d 77 (California Supreme Court, 2005)
Hooker v. Department of Transportation
38 P.3d 1081 (California Supreme Court, 2002)
McKown v. Wal-Mart Stores, Inc.
38 P.3d 1094 (California Supreme Court, 2002)
Kinsman v. Unocal Corp.
123 P.3d 931 (California Supreme Court, 2005)
Moore v. Regents of the University of California
248 Cal. App. 4th 216 (California Court of Appeal, 2016)
Regalado v. Callaghan CA
3 Cal. App. 5th 582 (California Court of Appeal, 2016)
CRST, Inc. v. Superior Court of Los Angeles County
11 Cal. App. 5th 1255 (California Court of Appeal, 2017)
Gonzalez v. Mathis
493 P.3d 212 (California Supreme Court, 2021)
H.N. & Frances C. Berger Foundation v. City of Escondido
127 Cal. App. 4th 1 (California Court of Appeal, 2005)
Tverberg v. Fillner Construction, Inc.
202 Cal. App. 4th 1439 (California Court of Appeal, 2012)
Alvarez v. Seaside Transp. Servs. LLC
221 Cal. Rptr. 3d 119 (California Court of Appeals, 5th District, 2017)
Delgadillo v. Television Ctr., Inc.
229 Cal. Rptr. 3d 594 (California Court of Appeals, 5th District, 2018)

Cite This Page — Counsel Stack

Bluebook (online)
CBRE v. Super. Ct., Counsel Stack Legal Research, https://law.counselstack.com/opinion/cbre-v-super-ct-calctapp-2024.