CB&I Constructors, Inc. v. Town of Wake Forest

579 S.E.2d 502, 157 N.C. App. 545, 2003 N.C. App. LEXIS 736
CourtCourt of Appeals of North Carolina
DecidedMay 6, 2003
DocketCOA02-1100
StatusPublished
Cited by7 cases

This text of 579 S.E.2d 502 (CB&I Constructors, Inc. v. Town of Wake Forest) is published on Counsel Stack Legal Research, covering Court of Appeals of North Carolina primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
CB&I Constructors, Inc. v. Town of Wake Forest, 579 S.E.2d 502, 157 N.C. App. 545, 2003 N.C. App. LEXIS 736 (N.C. Ct. App. 2003).

Opinion

CALABRIA, Judge.

This appeal arises from a Wake County Superior Court order issuing preliminary and permanent injunctive relief concerning the award of the construction of an elevated water tank needed to alleviate concerns associated with the sufficiency of the current water supply in the Town of Wake Forest (“Wake Forest”). After Wake Forest selected a site for the future water tank, a subsurface investigation evaluated site grading and foundation support considerations. The resulting report (“Geotech report”) analyzed two commonly utilized foundations, shallow spread footing foundations and pile foundations, as well as the amount of settlement that could be expected from each foundation. The pile foundation, although more costly than the shal *547 low spread footing foundation, benefits from lower differential settlement. Thereafter, Wake Forest employed the engineering consulting firm of Hazen and Sawyer to prepare an invitation for bids (“IFB”) for the construction of the future water tower.

Wake Forest issued the IFB in January of 2002. The IFB set forth mandatory specifications for the design of the water tank, its components, and its foundation. It also included illustrative drawings and the Geotech report as an attachment. Any party submitting a bid was required to design and submit a foundation as shown in the drawings and compliant with the mandatory specifications contained in the IFB.

CB&I Constructors, Inc. (“CB&I”) and Landmark Structures I, L.P. (“Landmark”) are businesses engaged in the commercial construction of water tanks who both submitted bids in response to the IFB. Landmark interpreted the IFB to allow a manufacturer to design and submit a shallow spread footing foundation, while CB&I interpreted the IFB to require a pile foundation. When the bids were opened, Landmark had submitted the lowest bid.

Instead of awarding the contract to Landmark as the lowest responsive bidder, Wake Forest contacted Landmark with several concerns. These concerns included the differential settlement that could be expected if a shallow spread footing foundation, as proposed in their bid, was utilized as well as whether the bid complied with the foundation required by the specifications in the IFB. Thereafter, Landmark agreed to provide a pile foundation for the same price as the price stated in their bid, and Wake Forest voted to award the contract to Landmark.

CB&I initiated this action against Wake Forest on 31 May 2002 alleging Wake Forest improperly awarded the construction contract of the proposed water tank to Landmark. CB&I contended the bid submitted by Landmark to Wake Forest was not responsive to the mandatory foundation specifications in the IFB, that Wake Forest engaged in inappropriate post-bid negotiations with Landmark, and that CB&I should be awarded the construction contract as the lowest responsible, responsive bidder on the project pursuant to N.C. Gen. Stat. §§ 143-128, -129. CB&I sought a declaratory judgment and injunctive relief, or, in the alternative, monetary damages.

On 6 June 2002, Judge Ripley Rand entered a temporary restraining order prohibiting Wake Forest from executing a contract with *548 Landmark or any other contractor other than CB&I for the water tank construction project. The trial court also set a hearing on a preliminary injunction for 14 June 2002, the same day as the expiration of the temporary restraining order. On 14 June 2002, with the consent of all parties, the trial court joined Landmark as a necessary party. After the hearing, the trial court granted both preliminary and permanent injunctive relief “prohibiting the award of the Project to any entity other than CB&I.. . [and] directing [Wake Forest] to issue a notice of award for the Project to CB&I....” It was the express intention of the trial court to “dispose of all claims including [CB&I’s] claim for a declaratory judgment” which was made moot by the order. Landmark appeals.

Before we address Landmark’s assignments of error, we must determine whether the order of the trial court is properly presented to this Court. Because we find the trial court exceeded its jurisdiction with respect to the permanent injunction and the order was interlocutory with respect to the preliminary injunction, we vacate in part and remand in part for further proceedings.

I. Permanent Injunction

“A permanent injunction is an extraordinary equitable remedy and may only properly issue after a full consideration of the merits of a case.” Shishko v. Whitley, 64 N.C. App. 668, 671, 308 S.E.2d 448, 450 (1983). “A judge conducting a hearing to determine whether a temporary restraining order should be continued as a preliminary injunction . . . has no jurisdiction to determine a controversy on its merits.” Everette v. Taylor, 77 N.C. App. 442, 444, 335 S.E.2d 212, 214 (1985) (holding “it was error for the court to issue a permanent injunction at a hearing to show cause why a temporary restraining order should not be continued [via a preliminary injunction]”). “[Where] the judgment entered [is] beyond the jurisdiction of the judge . . ., such jurisdiction [cannot] be conferred by agreement, and objection to the jurisdiction may be made at any stage of a proceeding, even in the Supreme Court[.]” MacRae & Co. v. Shew, 220 N.C. 516, 518, 17 S.E.2d 664, 665 (1941).

On 14 June 2002, Judge Evelyn Hill conducted a hearing to determine whether the temporary restraining order, granted previously and set to expire on the day of the hearing, should be continued as a preliminary injunction. However, at the conclusion of the hearing, the trial court granted both a preliminary and a permanent injunction, which, by intent and effect, determined the controversy on its merits. *549 The granting of the permanent injunction exceeded the jurisdiction of the court. Accordingly, that portion of the order granting the permanent injunction and awarding affirmative injunctive relief is vacated.

II. Preliminary Injunction

Because the portion of the order granting a permanent injunction has been vacated, the dispositive remaining question is whether the remainder of the order granting a preliminary injunction is interlocutory. “The purpose of a preliminary injunction is ordinarily to preserve the status quo pending trial on the merits.” State v. School, 299 N.C. 351, 357, 261 S.E.2d 908, 913 (1980). “Its impact is temporary and lasts no longer than the pendency of the action. Its decree bears no precedent to guide the final determination of the rights of the parties. In form, purpose, and effect, it is purely interlocutory.” Id., 299 N.C. at 357-58, 261 S.E.2d at 913.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Epes Logistics Servs., Inc. v. De Piante
2025 NCBC 10 (North Carolina Business Court, 2025)
Wining Taylors, LLC v. Ce Precision, Inc.
2019 NCBC 25 (North Carolina Business Court, 2019)
Levin v. Jacobson
2015 NCBC 108 (North Carolina Business Court, 2015)
Sandhill Amusements, Inc. v. Sheriff of Onslow County
762 S.E.2d 666 (Court of Appeals of North Carolina, 2014)
Scottish Re Life Corp. v. Transamerica Occidental Life Insurance
647 S.E.2d 102 (Court of Appeals of North Carolina, 2007)

Cite This Page — Counsel Stack

Bluebook (online)
579 S.E.2d 502, 157 N.C. App. 545, 2003 N.C. App. LEXIS 736, Counsel Stack Legal Research, https://law.counselstack.com/opinion/cbi-constructors-inc-v-town-of-wake-forest-ncctapp-2003.