CBCO, Inc. v. Grani Installation, Inc.

95 Cal. App. 3d 290, 157 Cal. Rptr. 28, 1979 Cal. App. LEXIS 1929
CourtCalifornia Court of Appeal
DecidedJuly 24, 1979
DocketCiv. No. 55410
StatusPublished
Cited by1 cases

This text of 95 Cal. App. 3d 290 (CBCO, Inc. v. Grani Installation, Inc.) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
CBCO, Inc. v. Grani Installation, Inc., 95 Cal. App. 3d 290, 157 Cal. Rptr. 28, 1979 Cal. App. LEXIS 1929 (Cal. Ct. App. 1979).

Opinion

Opinion

KINGSLEY, Acting P. J.

We are presented with two appeals from two contradictory orders in an arbitration matter. We reverse the orders.

CBCO, Inc., as general contractor, entered into a contract with Grani Installations, Inc., to perform work on buildings being constructed for State Farm Mutual. The contract contained an arbitration clause;1 State [293]*293Mutual was not a party to that contract. A disagreement arose between the parties and Grani filed an action in municipal court against CBCO and State Mutual, for breach of contract. CBCO moved in municipal court for an order staying the action and directing arbitration. That motion was denied for lack of jurisdiction, but proceedings were stayed to permit CBCO to apply for such relief in superior court. Such a petition was filed resulting, after hearing, in an order denying arbitration. CBCO has appealed from that order. (Code Civ. Proc., § 1294.)

Thereafter, at the insistencies of CBCO, an arbitration was held, over the objection of Grani and without appearance by it, resulting in an award in favor of CBCO. Grani then moved for an order vacating the award on the ground that, because of the order denying arbitration, the arbitrators had no jurisdiction to act. That petition was denied and Grani has appealed.

I

We conclude that the first order was in error. Admittedly there was a contract between CBCO and Grani providing for arbitration which CBCO has properly invoked. Apparently the theory of the denial order, as the trial court explained it in the second order, was that the presence of State Farm in the municipal court action prevented enforcement of that agreement. We reject that theory. State Farm was, and is, liable only if CBCO is indebted to Grani for work on the State Farm building. CBCO and Grani were free to settle between themselves Grani’s liability under the construction contract. If such settlement, whether by negotiation, litigation or arbitration, resulted in liability on CBCO, State Farm will be liable, if at all, only because its building may be subject to a mechanic’s lien for work for which CBCO does not pay. If State Farm requires protection while the CBCO-Grani dispute is settled, the trial court’s action (as CBCO had requested) was to stay the municipal court action. The order denying arbitration must be, and is, reversed.

II

It is true, as CBCO argues, that under an arbitration provision such as the one herein involved, a party to that contract may proceed to demand and receive arbitration without the necessity of securing an order under section 1282.2 of the Code of Civil Procedure. (Brink v. Allegro Builders, Inc. (1962) 58 Cal.2d 577 [25 Cal.Rptr. 556, 375 P.2d 436].) However, a party faced with alternative remedies is bound by the one he [294]*294chooses. When CBCO elected to seek a court order under section 1282.2, it waived its right to proceed with arbitration on the theory that the arbitration clause was self-operating. Having litigated the issue of arbitrability and lost, its sole remaining remedy—which it utilized—was to appeal from the order of denial, and await this court’s disposition of that appeal.

It follows that Grani was correct that CBCO and the arbitrators were without jurisdiction to proceed with a unilateral arbitration until CBCO’s appeal was determined.

Ill

The result is that Grani has been held liable under an award given in a proceeding in which it was not required to participate and in which its position as to liability has never been heard; Grani is entitled to a new arbitration in which the rights of CBCO and Grani can be fully heard and determined.

The orders appealed from are reversed with directions to enter a new order directing arbitration and staying the municipal court action.

Jefferson (Bernard), J., and Alarcon, J., concurred.

On August 14, 1979, the judgment was modified to read as printed above.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

J&K Cement Construction, Inc. v. Montalbano Builders, Inc.
456 N.E.2d 889 (Appellate Court of Illinois, 1983)

Cite This Page — Counsel Stack

Bluebook (online)
95 Cal. App. 3d 290, 157 Cal. Rptr. 28, 1979 Cal. App. LEXIS 1929, Counsel Stack Legal Research, https://law.counselstack.com/opinion/cbco-inc-v-grani-installation-inc-calctapp-1979.