This is a motion for a new trial, on behalf of the defendant, on exceptions taken at the Cayuga Circuit and ordered to be heard at the General Term in the first instance.
The action was in replevin for the wrongful detention of certain raih’oad iron and a quantity of ties laid down, and constituting a railroad track leading from the main track of what was lately the Cayuga Lake Railroad Company, now belonging to the plaintiff. The said side track is about eighty rods long and was laid upon and across land belonging to Mrs. Winegar and led to a stone quarry situated on Mrs. Winegar’s land.
One Hawley was the lessee from Mrs. Winegar of the premises on which the side track was laid, and the side track was laid by the Cayuga Lake Railroad Company, the predecessors in title of the plaintiff, by and under an agreement between that company and Hawley, the lessee of Mrs. Winegar. The railroad company wished to procure loose stones and dirt for the purposes of the railroad from the said quarry. Hawley had taken a lease of the premises for the term of five years from September 3, 1873, at the annual rent of $500, and it was then agreed between Hawley and the railroad company, by parol, to the effect that the company was to lay this track to the quarry and to have the earth and loose stones down [172]*172to the building stone, and were to send their ears into the quarry by means of the side track and take out what they wanted, and in consideration thereof the company agreed to pay $100 per year of the annual rent due by Hawley’s lease, and if Hawley loaded the cars for the company it was to pay him certain rates for so doing.
The Cayuga Lake Railroad Company, under the said parol agreement, laid down the side track .which, by the parol agreement, Hawley was to use in shipping building stone from the quarry. The agreement was to continue during the term of Hawley’s lease. Whether the Cayuga Lake Railroad Company had ever availed itself of the privilege of taking out the loose earth and stone, or whether that company ever paid any thing on the rent of $100 per year, did not appear. The Cayuga Lake Railroad Company and all its lands and premises, rights of way, side track, branches, turnouts; etc., owned by the company on December 6,1872, or to be thereafter constructed, erected or acquired, in any way connected with, or appurtenant to, the said railroad track, was sold on the foreclosure of a second mortgage and purchased by one James Stillman, to whom the referee, who made the sale, conveyed on the 29th of August, 1874, and Stillman conveyed to the plaintiffs. In the meantime Hawley, by parol, transferred his lease by parol to the defendant Niles, who had been a pai’tner with Hawley in working the quarry.
The new coxnpany (the plaintiff) by its president, agx*eed by parol with Niles, that the arrangement should contixxue at the same price of $100 per year, and went in and took out the dix’t and loose stones, and paid Niles for what cars he loaded at the rates which had been agreed on —■ and paid also fifty dollars on account of the rent. In 1875, the sxxperintendent of the plaintiff’s road was desirous of removing the said rails and ties composing the said side track, but was forbidden and prevented by Niles, the defendant.
On this appeal, the defendant’s counsel presents two points, which ax’ose on his motion for a nonsuit, and to the railing of the justice at the Circuit:
First. That the contract was not void by the statute of frauds.
Second. That if void then the placing of the side tracks on the premises was a trespass, and the said rails and ties became fixtures, for which, thex’efore, this action would not lie.
[173]*173We think the contract was void at law under the statute of frauds, as being an agreement for an easement, wherfeby, if valid, the premises, so far as the leasehold interest for five years was concerned, became the servient tenement.
The statute is, that no estate or interest in lands, or any trust or power, over or concerning lands, or in any manner relating thereto, shall be created, granted or assigned, etc., unless by act or operation of law or by a deed of conveyance.
We think, also, the contract was void as not to be performed within a year. (Pitkin v. The Long Island Railroad Company, 2 Barb. Ch., 221; Day v. The New York Central Railroad Co., 31 Barb., 548.)
We think, also, that the rails and ties so laid down, did not become fixtures, for the intent was that they were to be placed there for a temporary purpose and the consent of the lessee, though void as a contract, inured as a license and prevented the act from being a trespass. The receipt of the fifty dollars on account of rent, was conclusive evidence of the consent of the lessee to the occupation of the premises by the side track, and judgment should be ordered for the plaintiff on the verdict.
New trial denied and judgment ordered for the plaintiff on the verdict.
Free access — add to your briefcase to read the full text and ask questions with AI
Related
Cite This Page — Counsel Stack
20 N.Y. Sup. Ct. 170, Counsel Stack Legal Research, https://law.counselstack.com/opinion/cayuga-railway-co-v-niles-nysupct-1878.