NOTICE: All slip opinions and orders are subject to formal revision and are superseded by the advance sheets and bound volumes of the Official Reports. If you find a typographical error or other formal error, please notify the Reporter of Decisions, Supreme Judicial Court, John Adams Courthouse, 1 Pemberton Square, Suite 2500, Boston, MA, 02108-1750; (617) 557- 1030; SJCReporter@sjc.state.ma.us
16-P-944 Appeals Court
CAVE CORPORATION vs. CONSERVATION COMMISSION OF ATTLEBORO.
No. 16-P-944.
Plymouth. April 6, 2017. - July 14, 2017.
Present: Green, Blake, & Lemire, JJ.
Municipal Corporations, Conservation commission, By-laws and ordinances. Wetlands Protection Act.
Civil action commenced in the Superior Court Department on January 9, 2015.
The case was heard by Richard J. Chin, J., on a motion for judgment on the pleadings, and a motion for clarification or reconsideration was considered by him.
Matthew Watsky for the plaintiff. Rebekah Lacey for the defendant.
GREEN, J. When a municipal conservation commission fails
to act timely on a notice of intent for work affecting wetlands,
the applicant is entitled to seek relief from the Department of
Environmental Protection (DEP). G. L. c. 131, § 40. If, on the
applicant's request for relief, the DEP thereafter issues a 2
superseding order of conditions authorizing the work described
in the notice of intent, the superseding order controls the work
under the Wetlands Protection Act (act), G. L. c. 131, § 40,
notwithstanding any more restrictive provisions of an otherwise
applicable municipal wetlands ordinance or by-law. See Oyster
Creek Preservation, Inc. v. Conservation Commn. of Harwich, 449
Mass. 859, 865 (2007). Cave Corporation (Cave), the plaintiff
in the present case, contends that such a superseding order
operated to divest the conservation commission of Attleboro
(commission) of all authority to regulate activity on the land
subject to the superseding order, even if the same land is also
the subject of a separate notice of intent on which the
commission acted timely.1 A judge of the Superior Court
disagreed, and we affirm.
Background. The Attleboro city council adopted the
Attleboro wetlands protection ordinance (ordinance) on October
2, 2001, and the commission, acting pursuant to authority
delegated by the ordinance, promulgated rules and regulations
1 Cave also contends that the provisions of the Attleboro wetlands protection ordinance are no more restrictive than those of the act such that the DEP's superseding order on the separate notice of intent controls in any event, see DeGrace v. Conservation Commn. of Harwich, 31 Mass. App. Ct. 132, 136 (1991), and that the record does not contain substantial evidence supporting the conditions imposed by the commission, even if it had authority to regulate the land at issue. 3
thereafter. Section 18-1.1 of the ordinance recites as its
purpose:
"to protect the wetlands, water resources, and adjoining land areas in Attleboro by controlling activities deemed by the Conservation Commission likely to have a significant or cumulative effect upon resource area values, including but not limited to the following: public or private water supply, groundwater, flood control, erosion and sedimentation control, storm damage prevention including coastal storm flowage, water quality, water pollution control, fisheries, wildlife habitat, rare species habitat including rare plant species, agriculture, aquaculture, and recreation values, deemed important to the community (collectively, the 'resource areas or values protected by this ordinance')."
Among other provisions, § 18-1.8 of the ordinance imposes a
requirement that any application for a permit to perform work in
any area potentially affecting wetlands delineate and maintain
"a 25-foot wide continuous and undisturbed Wetlands Protection
Zone measured from and parallel to the [wetlands] resource area
boundary."2
On December 18, 2013, Cave filed a notice of intent with
the commission proposing construction of a roadway, drainage,
infrastructure, and utilities associated with a subdivision
development. The proposed project included 175 linear feet of
new roadway, with connections to a water main to serve seven new
lots, but did not propose any work on the individual lots
related to the construction of houses on the lots.
2 The same requirement is repeated in § 4.9 of the ordinance rules and regulations. 4
The notice of intent acknowledged the presence of vegetated
wetlands along the westerly side of the project site and a
twenty-five-foot wetlands protection zone along the boundary of
those vegetated wetlands; it also recognized two vernal pools to
the south of the proposed roadway, a 125-foot protected area
surrounding each of the vernal pools,3 and a riverfront area4
bordering the southerly part of the project site.
After several extensions of time for the commission's
consideration of the proposal, and several modifications to the
proposed work, Cave submitted a final revised proposal to the
commission on October 16, 2014. Following a hearing on November
5, 2014, the commission voted to approve the roadway extension
project, with conditions. The commission issued its order of
conditions on November 12, 2014. Of particular note among the
conditions, for present purposes, is condition number twenty-
3 As defined in the ordinance, a "vernal pool" includes the basin depression itself and an area of vernal pool habitat extending 100 feet from the boundary of the mean annual boundary of the depression; the ordinance rules and regulations prohibit disturbance of any land within both the vernal pool basin and its surrounding 100-foot habitat area. The ordinance rules and regulations further prohibit any disturbance of land within the additional twenty-five-foot wetlands protection zone extending beyond the boundary of the defined vernal pool (including the 100-foot habitat perimeter), so that the total area of protection extends 125 feet from the boundary of the basin depression. 4 The act defines "riverfront area" as an "area of land situated between a river's mean annual high-water line and a parallel line located [200] feet away." G. L. c. 131, § 40, inserted by St. 1996, c. 258, § 18. 5
nine, which prohibited any disturbance of the area within 125
feet of the two vernal pools based on a finding that "any
disturbance to the [125-foot area] on the subject parcels of
land will result in cumulative adverse impacts upon the resource
area values." Cave appealed the order of conditions for the
roadway extension project to the DEP, seeking a superseding
order of conditions,5 and, on February 26, 2015, the DEP approved
the work proposed in Cave's notice of intent for the roadway
extension project, subject to conditions set forth in a
superseding order of conditions.
While the roadway extension notice of intent was under
consideration by the commission, but before it was approved,
Cave also submitted on October 14, 2014, notices of intent for
work (including proposed construction of homes and related
improvements) on lots 4, 5, 6, and 7 of the proposed
subdivision.6 Thereafter, the commission took no action on the
notices of intent for those lots until the evening of November
5, 2014, when it opened a hearing. However, that date was
beyond the twenty-one-day period within which a hearing must be
Free access — add to your briefcase to read the full text and ask questions with AI
NOTICE: All slip opinions and orders are subject to formal revision and are superseded by the advance sheets and bound volumes of the Official Reports. If you find a typographical error or other formal error, please notify the Reporter of Decisions, Supreme Judicial Court, John Adams Courthouse, 1 Pemberton Square, Suite 2500, Boston, MA, 02108-1750; (617) 557- 1030; SJCReporter@sjc.state.ma.us
16-P-944 Appeals Court
CAVE CORPORATION vs. CONSERVATION COMMISSION OF ATTLEBORO.
No. 16-P-944.
Plymouth. April 6, 2017. - July 14, 2017.
Present: Green, Blake, & Lemire, JJ.
Municipal Corporations, Conservation commission, By-laws and ordinances. Wetlands Protection Act.
Civil action commenced in the Superior Court Department on January 9, 2015.
The case was heard by Richard J. Chin, J., on a motion for judgment on the pleadings, and a motion for clarification or reconsideration was considered by him.
Matthew Watsky for the plaintiff. Rebekah Lacey for the defendant.
GREEN, J. When a municipal conservation commission fails
to act timely on a notice of intent for work affecting wetlands,
the applicant is entitled to seek relief from the Department of
Environmental Protection (DEP). G. L. c. 131, § 40. If, on the
applicant's request for relief, the DEP thereafter issues a 2
superseding order of conditions authorizing the work described
in the notice of intent, the superseding order controls the work
under the Wetlands Protection Act (act), G. L. c. 131, § 40,
notwithstanding any more restrictive provisions of an otherwise
applicable municipal wetlands ordinance or by-law. See Oyster
Creek Preservation, Inc. v. Conservation Commn. of Harwich, 449
Mass. 859, 865 (2007). Cave Corporation (Cave), the plaintiff
in the present case, contends that such a superseding order
operated to divest the conservation commission of Attleboro
(commission) of all authority to regulate activity on the land
subject to the superseding order, even if the same land is also
the subject of a separate notice of intent on which the
commission acted timely.1 A judge of the Superior Court
disagreed, and we affirm.
Background. The Attleboro city council adopted the
Attleboro wetlands protection ordinance (ordinance) on October
2, 2001, and the commission, acting pursuant to authority
delegated by the ordinance, promulgated rules and regulations
1 Cave also contends that the provisions of the Attleboro wetlands protection ordinance are no more restrictive than those of the act such that the DEP's superseding order on the separate notice of intent controls in any event, see DeGrace v. Conservation Commn. of Harwich, 31 Mass. App. Ct. 132, 136 (1991), and that the record does not contain substantial evidence supporting the conditions imposed by the commission, even if it had authority to regulate the land at issue. 3
thereafter. Section 18-1.1 of the ordinance recites as its
purpose:
"to protect the wetlands, water resources, and adjoining land areas in Attleboro by controlling activities deemed by the Conservation Commission likely to have a significant or cumulative effect upon resource area values, including but not limited to the following: public or private water supply, groundwater, flood control, erosion and sedimentation control, storm damage prevention including coastal storm flowage, water quality, water pollution control, fisheries, wildlife habitat, rare species habitat including rare plant species, agriculture, aquaculture, and recreation values, deemed important to the community (collectively, the 'resource areas or values protected by this ordinance')."
Among other provisions, § 18-1.8 of the ordinance imposes a
requirement that any application for a permit to perform work in
any area potentially affecting wetlands delineate and maintain
"a 25-foot wide continuous and undisturbed Wetlands Protection
Zone measured from and parallel to the [wetlands] resource area
boundary."2
On December 18, 2013, Cave filed a notice of intent with
the commission proposing construction of a roadway, drainage,
infrastructure, and utilities associated with a subdivision
development. The proposed project included 175 linear feet of
new roadway, with connections to a water main to serve seven new
lots, but did not propose any work on the individual lots
related to the construction of houses on the lots.
2 The same requirement is repeated in § 4.9 of the ordinance rules and regulations. 4
The notice of intent acknowledged the presence of vegetated
wetlands along the westerly side of the project site and a
twenty-five-foot wetlands protection zone along the boundary of
those vegetated wetlands; it also recognized two vernal pools to
the south of the proposed roadway, a 125-foot protected area
surrounding each of the vernal pools,3 and a riverfront area4
bordering the southerly part of the project site.
After several extensions of time for the commission's
consideration of the proposal, and several modifications to the
proposed work, Cave submitted a final revised proposal to the
commission on October 16, 2014. Following a hearing on November
5, 2014, the commission voted to approve the roadway extension
project, with conditions. The commission issued its order of
conditions on November 12, 2014. Of particular note among the
conditions, for present purposes, is condition number twenty-
3 As defined in the ordinance, a "vernal pool" includes the basin depression itself and an area of vernal pool habitat extending 100 feet from the boundary of the mean annual boundary of the depression; the ordinance rules and regulations prohibit disturbance of any land within both the vernal pool basin and its surrounding 100-foot habitat area. The ordinance rules and regulations further prohibit any disturbance of land within the additional twenty-five-foot wetlands protection zone extending beyond the boundary of the defined vernal pool (including the 100-foot habitat perimeter), so that the total area of protection extends 125 feet from the boundary of the basin depression. 4 The act defines "riverfront area" as an "area of land situated between a river's mean annual high-water line and a parallel line located [200] feet away." G. L. c. 131, § 40, inserted by St. 1996, c. 258, § 18. 5
nine, which prohibited any disturbance of the area within 125
feet of the two vernal pools based on a finding that "any
disturbance to the [125-foot area] on the subject parcels of
land will result in cumulative adverse impacts upon the resource
area values." Cave appealed the order of conditions for the
roadway extension project to the DEP, seeking a superseding
order of conditions,5 and, on February 26, 2015, the DEP approved
the work proposed in Cave's notice of intent for the roadway
extension project, subject to conditions set forth in a
superseding order of conditions.
While the roadway extension notice of intent was under
consideration by the commission, but before it was approved,
Cave also submitted on October 14, 2014, notices of intent for
work (including proposed construction of homes and related
improvements) on lots 4, 5, 6, and 7 of the proposed
subdivision.6 Thereafter, the commission took no action on the
notices of intent for those lots until the evening of November
5, 2014, when it opened a hearing. However, that date was
beyond the twenty-one-day period within which a hearing must be
5 Cave's request for a superseding order of conditions for the roadway extension project does not appear in the record, although there appears to be no dispute that it was timely made. 6 Cave attempted to file the notices of intent on October 10, 2014, but the commission did not accept them as filed until October 14, 2014, for procedural reasons. Nothing turns on this. 6
held under the act. See G. L. c. 131, § 40; Oyster Creek
Preservation, Inc. v. Conservation Commn. of Harwich, 449 Mass.
at 863. Accordingly, on November 5, 2014, prior to commencement
of the hearing that evening, Cave initiated a request to the DEP
for a superseding order of conditions.7 Thereafter, on February
26, 2015, the DEP approved the work proposed in Cave's notice of
intent for lot 7, subject to conditions set forth in a
superseding order of conditions.8 In practical effect, however,
condition number twenty-nine of the order of conditions issued
by the commission for the roadway extension project precludes
construction of the driveway proposed to serve lot 7 because it
cuts through a portion of one of the 125-foot protected areas
located on lot 7, and it similarly precludes certain other work
proposed within that area.
By complaint filed in the Superior Court on January 9,
2015, Cave sought certiorari review and declaratory relief. In
substance, Cave sought a declaration that the superseding order
of conditions issued by the DEP with respect to lot 7 governed
7 At the hearing on November 5, 2014, the commission considered the notices of intent for the four lots. As pertinent to this appeal, the commission eventually purported to deny approval of the work proposed in the notice of intent for lot 7. 8 Before the Superior Court and in this appeal, the commission concedes that its denial of approval of the notice of intent for lot 7 was a nullity because the DEP subsequently issued a superseding order of conditions. 7
the work described in Cave's notice of intent for that lot, and
sought certiorari review of the order of conditions issued by
the commission on the roadway extension notice of intent insofar
as it purported to regulate work on lot 7. A judge concluded
that the superseding order of conditions for lot 7 governed the
performance of the work described in the notice of intent for
that lot, but that the conditions set forth in the order of
conditions issued by the commission on the roadway extension
notice of intent was valid and enforceable. Subsequently, in an
order on Cave's motion for clarification or reconsideration, the
judge explained that his ruling means that the order of
conditions issued by the commission under the ordinance for the
roadway extension project, including condition number twenty-
nine, remain applicable to the subdivision, notwithstanding the
superseding order of conditions issued by the DEP on the notice
of intent for lot 7. This appeal followed.
Discussion. Cave lodges three challenges to the validity
of condition number twenty-nine. First, it contends that the
ordinance is no more stringent than the act; accordingly, the
superseding order of conditions issued by the DEP on the roadway
extension project superseded any conditions imposed by the
commission. Second, Cave argues that because the commission
"lost jurisdiction" over the work described in the notice of
intent for lot 7 when it failed to conduct a timely hearing, it 8
was without authority to impose conditions affecting work on
that lot in the order of conditions it issued for the roadway
extension project. Third, Cave asserts that the record does not
contain substantial evidence supporting the imposition of
condition number twenty-nine in the order of conditions for the
roadway extension project. We address each claim in turn.
"It is well established that municipalities may enact more
stringent requirements than those provided in the act.
Lovequist v. Conservation Commn. of Dennis, 379 Mass. 7, 14-15
(1979). When a local conservation commission rests its decision
on a wetlands by-law [or ordinance] that provides greater
protection than the act, its decision cannot be preempted by a
DEP superseding order." FIC Homes of Blackstone, Inc. v.
Conservation Commn. of Blackstone, 41 Mass. App. Ct. 681, 686-
687 (1996). Where the local by-law or ordinance does not impose
more stringent controls than those set by the Legislature (in
the act), a DEP superseding order would control. See DeGrace v.
Conservation Commn. of Harwich, 31 Mass. App. Ct. 132, 136
(1991).
It is plain that the ordinance here imposes more stringent
controls than the act as to matters regulated under the order of
conditions issued by the commission for the roadway extension
project. As we have described supra, the ordinance includes
vernal pools (including the area extending 100 feet beyond the 9
basis depression comprising the pool itself) as resource areas
entitled to protection. By contrast, the act makes no mention
of vernal pools; "vernal pool habitat" as defined in 310 Code
Mass. Regs. 10.04 (2008) is protected only to the extent that it
falls within an "Area Subject to Protection" under the act. In
addition, the ordinance prohibits entirely any disturbance
within the additional wetland protection zone established by the
ordinance for the area extending twenty-five feet from the
boundary of any resource area (including vernal pools); under
the act, the additional twenty-five-foot area is not restricted
at all. There is no error in the conclusion by the judge that
the ordinance imposes more stringent requirements than the act;
thus, the order of conditions issued by the commission for the
roadway extension project was not preempted by the DEP's
superseding order concerning that project. See FIC Homes of
Blackstone, Inc. v. Conservation Commn. of Blackstone, 41 Mass.
App. Ct. at 687.
Cave fares no better with its contention that the
commission was divested of all authority over the land
comprising lot 7 once the commission failed to conduct a hearing
within the statutory time frame mandated by the act. In
essence, Cave's argument is that it is anomalous and illogical
to suggest that the work described in the notice of intent for
lot 7 can be authorized by the superseding order of conditions 10
issued by the DEP on that notice of intent, but prohibited by
the order of conditions issued by the commission under the
ordinance on the notice of intent for the roadway extension
project. Cave cites no authority for its contention, and we are
aware of none. Nor do we share Cave's perception of anomaly.
As a threshold matter, we observe that Cave filed its
notice of intent for the roadway extension project long before
it filed the notice of intent for lot 7, and had engaged in
detailed substantive discussions with the commission about the
roadway extension project over the course of several hearings,
continued with Cave's consent. Moreover, the commission issued
the order of conditions for the roadway extension project before
the DEP undertook review of the notice of intent for lot 7 and,
therefore, before the DEP issued its superseding order of
conditions on that lot. It would be anomalous indeed for the
DEP's superseding order of conditions for lot 7 to abrogate the
terms of a previously and validly issued order of conditions
regulating that lot simply because the same land was the subject
of additional work described in a subsequently filed notice of
intent.
Cave's third and final argument is to some extent a
variation of the second. Without conceding that the commission
could regulate activity on lot 7 after it failed to act timely
on Cave's separate notice of intent for that lot, Cave observes 11
that, although the roadway extension notice of intent does not
propose any work on lot 7 itself, the order of conditions issued
by the commission for the roadway extension project nonetheless
imposes conditions prohibiting any disturbance of resource areas
on lot 7. Accordingly, Cave asserts, the imposition of
condition number twenty-nine was arbitrary or capricious, and
not supported by substantial evidence. See Pollard v.
Conservation Commn. of Norfolk, 73 Mass. App. Ct. 340, 348
(2008).
In response, the commission observes that § 18-1.8 of the
ordinance directs it to "take into account the cumulative
adverse effects of loss, degradation, isolation, and replication
of protected resource areas throughout the community and the
watershed, resulting from past activities, permitted and exempt,
and foreseeable future activities." Moreover, the commission
notes, the project described in the roadway extension notice of
intent was not merely the construction of the roadway; it
described the creation and the development of the subdivision
itself. Accordingly, in evaluating appropriate conditions for
the roadway extension, the commission was not merely entitled
but required to consider the cumulative effects of the proposed
subdivision on wetlands resource areas and wildlife habitat
within the subdivision. 12
As the judge observed, in evaluating the notice of intent
for the roadway extension, the commission had before it the
report of its conservation agent highlighting the need to
insulate vernal pool habitats from human construction
activities, and explaining the delicate balance between the
ecosystem and Cave's proposed construction activities. The
commission also considered civil engineering and environmental
consulting reports and an ecological restoration plan for the
project. The record indicates that the commission analyzed and
weighed the reports indicating the potential cumulative and
indirect effects the subdivision project might cause, and
considered the potential effects in light of the purpose and the
criteria set forth in the ordinance.
"'Substantial evidence [is] such evidence as a reasonable
mind might accept as adequate to support a conclusion.' The
applicable standard of review is 'highly deferential to the
agency' and requires the reviewing court to accord 'due weight
to the experience, technical competence, and specialized
knowledge of the agency, as well as to the discretionary
authority conferred upon it.' 'We give deference to the
decision of an agency interpreting its own regulations . . .
[and] do not intrude lightly within the agency's area of
expertise, as long as the regulations are interpreted with
reference to their purpose and to the purpose and design of the 13
controlling statute.'" Healer v. Department of Envtl.
Protection, 75 Mass. App. Ct. 8, 13 (2009) (citations omitted).
In light of the commission's mandate to consider the
cumulative effects of the proposed subdivision with regard to
the purpose and the objectives of the ordinance, and the
evidence before it suggesting that disturbance of the wildlife
habitat within the 125-foot perimeter surrounding the two vernal
pools on the project site would be detrimental to the interests
protected by the ordinance, we discern no error of law in the
conclusion by the judge that the imposition by the commission of
condition number twenty-nine, prohibiting disturbance of land
within the wetlands protection zone, was supported by
substantial evidence and was not arbitrary or capricious. See
Pollard v. Conservation Commn. of Norfolk, 73 Mass. App. Ct. at
348.
Judgment affirmed.