Cavanaugh v. C. P. Boland Co.

149 Misc. 576, 268 N.Y.S. 390, 1933 N.Y. Misc. LEXIS 1408
CourtNew York Supreme Court
DecidedNovember 25, 1933
StatusPublished
Cited by2 cases

This text of 149 Misc. 576 (Cavanaugh v. C. P. Boland Co.) is published on Counsel Stack Legal Research, covering New York Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Cavanaugh v. C. P. Boland Co., 149 Misc. 576, 268 N.Y.S. 390, 1933 N.Y. Misc. LEXIS 1408 (N.Y. Super. Ct. 1933).

Opinion

Schenck, J.

The plaintiff, an employee of defendant Manhattan Fireproofing Co., Inc., instituted this action against the defendant C. P. Boland Co., Inc., the general contractor for the erection of an addition to St. Joseph’s Seminary building, in Troy. The defendant Manhattan Fireproofing Co., Inc., was a subcontractor. The accident which resulted in the injuries to plaintiff occurred July 14, 1932, when a container loaded with concrete fell off the platform of a material hoist and through a protecting roof, under which plaintiff was standing at the time.

Subsequent to the commencement of the action an order was made by Mr. Justice Russell bringing in the Manhattan Fireproofing Co., Inc., as a party defendant, and permitting the Boland Company to issue and serve supplemental summons with a pleading setting forth the alleged liability of the Manhattan Company to reimburse the Boland Company for such sum as the plaintiff might recover against it. Pursuant to the terms of said order a supplemental summons and cross-complaint were served upon the Manhattan Company by the Boland Company, to which the Manhattan Company served its answer.

At the time of the trial it was stipulated by the attorneys for the defendant that the question of the right to reimbursement claimed by defendant Boland Company against defendant Manhattan Company, for any judgment which plaintiff might recover against the defendant Boland Company, should be submitted to the court for its determination and that such question should not be submitted to the jury.

On the trial of this action there was submitted to the jury only the question of the right of the plaintiff to recover against the defendant Boland Company, and the jury was expressly instructed that it had no right to consider any question as to the liability of the defendant Manhattan Company, as no claim was made [578]*578against the Manhattan Company in the plaintiff’s complaint. The jury returned a verdict of $8,000 against the Boland Company.

From the evidence produced upon the trial it appeared that the Boland Company, as general contractor for the erection of a chapel building for the Society of the Sisters of St. Joseph, entered into a subcontract with the Manhattan Company, whereby the Manhattan Company was to perform certain work, including the installation of a concrete roof upon a portion of the building. In the construction of said concrete roof, it was necessary to hoist concrete from the ground level, where a concrete mixer was located. The Boland Company had constructed two material hoists, one on the south side and one on the north side of the building in the course of erection. On July 12, 1932, pursuant to its agreement with the Boland Company, the Manhattan Company commenced the work of constructing the concrete roof, making use of the material hoist on the south side of the building, on which material hoist, containers, commonly called “ buggies,” filled with concrete, were hoisted to the roof level.

It further appeared upon the trial that the engine which supplied the power to lift the material hoist and the concrete mixer in which the concrete was mixed were operated by the Manhattan Company, and that the workmen engaged in filling the containers from the concrete mixer and placing the same on the material hoists were all employed by the Manhattan Company on the day of the accident.

The original contract entered into between the Boland Company and the Manhattan Company contained this provision: “ 6. That you save harmless the person giving this order from all liability to any person whomsoever by reason of any neglect bn the part of yourself or your employees, or by reason of any defect in the supplies or materials furnished, or by reason of any neglect on the part of yourself or your employees in the doing of the work which is ordered. Certificates of insurance to be filed with C. P. Boland & Co.”

The contract is dated October 31, 1931. Thereafter, under date of March 17, 1932, the Manhattan Company wrote the Boland Company with reference to the use of the material hoist and other equipment belonging to the Boland Company, as follows:

“ C. P. Boland & Company,
“ 30 Fourth Street,
“ Troy, N. Y.
“ Gentlemen: We are writing to confirm our agreement with you to supply us without charge the use of your hoisting equipment, scaffolding, plank, concrete mixer, wheel-barrows, buggies and [579]*579miscellaneous equipment which you have on the St. Joseph’s Chapel job, for our use in carrying out our contract with you. We are to pay only the cost of the engineer for operating same.
Very truly yours,
“ MANHATTAN FIREPROOFING CO. INC.,
“ FCW/B. F. C. Witsell, Pres.”

To this letter the Boland Company replied under date of March twenty-third as follows:

“ Manhattan Fireproofing Co. Inc.,
103 Park Avenue,
New York City
“ Gentlemen: Att. F. Witsell, Pres. We do not accept your letter of the 17th as to furnishing you all your plant on the St. Joseph Chapel Building, Troy, N. Y. Without modifying our contract with your Company we are willing you should have the use of the Hoist and Elevator, runways and concrete mixer, we now have on the job without any renting expense.
Your company is to assume any loss by accident or otherwise when same is in your charge without any expense to us, employing proper men to operate same.
Very truly yours,
“ C. P. BOLAND & CO.
“ CPB: ACB C. P. Boland.”

The Boland Company contends that by virtue of its agreement with the Manhattan Company evidenced by these two letters, the Manhattan Company assumed all liability for any loss or damage which might occur in any manner while this hoist was being operated by it.

It would appear that when the Manhattan Company made use of this material hoist after the receipt of the letter of March twenty-third from the Boland Company, it agreed to the conditions there imposed.

The Boland Company was the general contractor. It was “ the master of the enterprise.” It was liable in the first instance for the use and operation of the hoist and for the violation of its duties in furnishing for use or using a material hoist that had not been properly constructed or one which was out of repair, or by placing material or articles upon the hoist that were hable to fall. To escape any of these duties it must have imposed such duty upon the subcontractor and given up all control and superintendence. (Hooey v. Airport Construction Co., 253 N. Y. 486; DeLee v. Pardy Construction Co., 249 id. 103; McGlone v. Angus, Inc., 248 id. 197.)

[580]*580If the Boland Company can show that any of the duties for the performance of which it was responsible had been shifted to the subcontractor, it is excused from the performance of such duty and thereby escapes liability for such non-performance.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Price v. United States
530 F. Supp. 1010 (S.D. Mississippi, 1981)
United States Fidelity & Guaranty Co. v. Mason & Dulion Co.
145 So. 2d 711 (Supreme Court of Alabama, 1962)

Cite This Page — Counsel Stack

Bluebook (online)
149 Misc. 576, 268 N.Y.S. 390, 1933 N.Y. Misc. LEXIS 1408, Counsel Stack Legal Research, https://law.counselstack.com/opinion/cavanaugh-v-c-p-boland-co-nysupct-1933.