Cavanaugh Landscaping Co. v. Department of Natural Resources

7 Ct. Cl. 200
West Virginia Court of Claims·Decided January 27, 1969·No. No. D-77·Published

Opinion

Jones, Judge:

On October 26, 1965, the claimant, Cavanaugh Landscaping Company of Akron, Ohio, entered into a written contract with the respondent, Department of Natural Resources, to construct four golf courses at West Virginia State Parks, two at Pipestem State Park, in Summers County, one at Twin Falls State Park, in Wyoming County, and one at Canaan Valley State Park, in Tucker County, for the contract sum of $710,000.00 One paragraph of the contract provides the following: “The Contractor hereby agrees to commence work under this contract on or before a date to be specified in a written ‘Notice to Proceed’ of the owner and to fully complete the project by October 14, 1966, as stipulated in the specifications. The Contractor further agrees to pay, as liquidated damages, the sum of $100.00 for each successive calendar day thereafter as provided in Paragraph 19 of the General Conditions.” The contract further provides that no changes in the work shall be made without the written approval of the Owner, charges or credits to be determined by specified methods, and the claimant was emphatically warned that no additional costs could be paid for without a Change Order. The State of West Virginia issued a Purchase Order dated October 30, 1965, acknowledging acceptance of the claimant’s proposal dated September 27, 1965 showing the deletion of several Alternates and a base contract price of $710,000.00. The Notice to Proceed was given on January 28, 1966. Sundry change orders increased the total contract price to $762,399.80, and extended the contract time from October 15, 1966, to June 1, 1968.

[201] The claimant contends that it is entitled to damages under the well established rule of law that a contractor is entitled to damages for delay caused by the owner, and also for damages for extra work done. Items of this claim as identified in the claimant’s petition are as follows: 2 (b) Delay in giving notice to proceed, including $11,564.00 not alleged in the claimant’s petition but permitted by the Court to be shown under an amendment of the pleadings at the time of hearing, $53,172.20; 2 (c) Delay resulting from faulty design and changes recommended by a “Citizens Committee” appointed by the governor, $20,750.00; 2 (d) Delay of the Department in furnishing mowing equipment, $42,715.00; 2 (e) Failure of the Department to furnish adequate water, $1,155.00; 2 (f) Damage to sprinkler heads, $1,295.00; 2 (g) Failure of the Department to provide adequate drainage, $16,430.00; 2 (h) Erroneous staking of courses, $24,255.00; 2 (i) Damages caused by heavy rains and delay relating to automatic water systems, $53,662.50; 2 (j) Delay due to traffic over public roads through two courses, $6,400.00; 2 (k) Delay caused by Farmer Mallow, who refused to vacate condemned land at Canaan Valley and threatened harm to the claimant’s officers and employees, $5,952.00; 2 (1) Failure of the Department to provide an adequate water supply at the Pipestem Nine Hole Course, $1,245.00 ; 2 (m) Delay in location of a practice fairway at Pipestem Nine Hole Course, $1,720.00; and 2 (n) General delays causing injury to claimant’s financial position and hindrance to its business as a going concern, $350,000.00; a total of $578,751.70.

The Department of Natural Resources denies that it owes the claimant anything and contends that any losses which the claimant may have sustained were due to the claimant’s own fault.

The State had no right to delay the Notice to Proceed indefinitely, for example, to the day before the completion date of the contract as suggested by counsel for the claimant, and if the delay was unreasonable, claimant would have been entitled to an extension of time. The claimant made much of its concern about the $100.00 per day penalty after the completion date, but the record does not disclose that it ever requested an extension, and, in fact, it appears that the eventual change order extending the time was initiated by the respondent. The clai[202] mant was put on notice at the outset that the contract must be approved by the Community Facilities Administration, a federal agency which was to furnish matching funds for the project, and that there were other preliminary matters which had to be consummated before work could be started. The claimant was told that if it performed any work prior to the Notice to Proceed, “It’s on your own.” During the latter part of November and early December, 1965, the claimant did send skeleton work forces to the several State Parks, being supervisory personnel who had no other work to do and apparently were making preparations for the following Spring. The severe Winter weather made work on the project practically impossible. The The Community Facilities Administration approved the project on January 12, 1966, whereupon the Attorney General’s approval was obtained and other necessary requirements were completed, and the Notice to Proceed was issued on January 28, 1966. Contrary to the claimant’s contentions, it was able to submit a work schedule dated February 22, 1966 showing that all work would be completed within the term of the contract. Under date of March 17, 1966, Daniel Cavanaugh, President of the claimant company wrote to the associate Architect/Engineer, Irving Bowman and Associates, in part as follows: “In answer to your letter of March 11, 1966, we wish to advise you that there has been no construction delays and we expect to finish on the specified date.” Cavanaugh testified that this letter was written under coercion and fear of retaliation, but'there is no corroboration of such averment, and in another letter written by him to Irving Bowman and Associates on May 10, 1966, he said: “We have had our normal share of problems so far and we have not been too concerned, but if you are not going to approve any more payments for Pipe Stem 18, we will have to stop all work there and request additional money for hold up.” The claimant undoubtedly had problems during the period involved in Item 2 (b), but all of them should have been anticipated and were substantially “normal” problems as indicated by Cavanaugh in his letter of May 10, 1966. The claimant accepted the Notice to Proceed and undertook performance of the contract, without making any request for additional compensation or a change order. We are of opinion that there was no unreasonable delay on the part of the respondent; [203] and the damages claimed for this period in the total amount of $53,172.20 are clearly not supported by the evidence.

Free access — add to your briefcase to read the full text and ask questions with AI

Cavanaugh Landscaping Co. v. Department of Natural Resources, 7 Ct. Cl. 200 (W. Va. Super. Ct. 1969).

7 Ct. Cl. 200 (Cavanaugh Landscaping Co. v. Department of Natural Resources) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.