Caulkins Designs v. Trieb, No. 549374 (Dec. 20, 1999)

1999 Conn. Super. Ct. 16341
CourtConnecticut Superior Court
DecidedDecember 20, 1999
DocketNo. 549374
StatusUnpublished

This text of 1999 Conn. Super. Ct. 16341 (Caulkins Designs v. Trieb, No. 549374 (Dec. 20, 1999)) is published on Counsel Stack Legal Research, covering Connecticut Superior Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Caulkins Designs v. Trieb, No. 549374 (Dec. 20, 1999), 1999 Conn. Super. Ct. 16341 (Colo. Ct. App. 1999).

Opinion

[EDITOR'S NOTE: This case is unpublished as indicated by the issuing court.]

MEMORANDUM OF DECISION ON DEFENDANT'S MOTION FOR SUMMARY JUDGMENT
This is a suit by a contractor, the plaintiff, Caulkins Designs, to recover the balance it claims is due for work performed at the home of Karen and Gerhard Trieb. A certificate of Mechanic's Lien was filed to secure the balance of $97,425.77 with interest that the plaintiff claims is owing to it. The sum due on the lien remains unpaid and the plaintiff has instituted this action to foreclose the lien. CT Page 16342

The defendants have filed a motion for summary judgment claiming there was a failure to comply with the requirements of the Home Improvement Act § 20-418 et seq. (the act). There is no doubt and both parties seem to agree that the contract entered into between the parties was a "home improvement contract," see §§ 20-419 (4) and (5) of the General Statutes. Section 20-429 of the act provides that "(a) no home improvement contract shall be valid or enforceable against an owner unless it . . . (7) contains a starting and completion date. . . ." Subsection (f) states a contractor who has complied with various of the requirement of subsection (a) including (a)(7) can recover for work performed if a court determines it would be inequitable to deny such recovery.

The defendants have filed a motion for summary judgment based on the alleged noncompliance with the provision of subsection (7) of § 20-429 (a). The contract between the parties referred to as the "proposal" was prepared by the defendant and in the blanks on the upper right-hand corner of the first page where it says, "approximate starting date" and "approximate completion date," it says in both blank spaces "not available."

The defendants argue that because the proposal fails to set forth a starting and completion date as required by § 20-429 (a)(7), it is unenforceable as a matter of law pursuant to the holding in Rizzo Pool Co. v. DelGrosso, 232 Conn. 666 (1995).

The plaintiff argues that under the circumstances as existed here, there was compliance with the act. Mr. Caulkins submitted an affidavit claiming that on April 14, 1997, he and the Triebs met to review a proposed contract. He claims the terms of the contract were discussed "including the specific issues of starting and completion dates, as all were aware that these dates were required elements of the contract." The affidavit goes on to say that firm dates would not be given "because full permitting was not yet available and the scope of the project was still unclear due to incomplete architectural plans. . . ." The Caulkins' affidavit goes on to say that "nevertheless," the Triebs wanted the plaintiff to begin work "and as a result, the portions of the contract which related to starting and completion dates were typed in as `not available' being the only specification of starting and completion dates. The Triebs were aware of and consented to this form of contracting at the time of our meeting and executed the contract as such." The Triebs do not CT Page 16343 contest these just mentioned factual allegations but argue that despite these claims the act was not complied with.

The plaintiff also argues that apart from the strict question of compliance with the act it has presented a question of fact as to whether the defendants have knowingly and voluntarily waived the requirements of the act with respect to including a specific and firm starting and completion date in the contract proposal. Finally, the plaintiff argues that it has raised a question of fact as to whether the defendants have made a bad faith invocation of the protections of the act.

Regarding the waiver issue, the second Trieb affidavit states when he signed the proposal, Mr. Trieb was unaware of the provisions of the act and that he was signing a "home improvement contract."

He states that he did not know the act required a commencement and completion date and that their absence would entitle him to invalidate the contract. He first learned of the act's requirements from his attorney several months after signing the proposal.

The rules applicable to deciding a motion for summary judgment are well known. A court cannot grant such a motion if a genuine material issue of fact must be decided. A party has a constitutional right to a jury trial. On the other hand, if no genuine issue of material fact exists and the dispute between the parties can be decided as a matter of law, it should be so decided to prevent the continuation of litigation that is not meritorious.

Compliance with Act
The purpose of the act is remedial in nature; the law was passed for the protection of the public. Caulkins v. Petrillo,200 Conn. 713, 720 (1986). The legislative history indicates the bill was intended to provide "minimal" safeguards for consumers and the problems the bill was intended to address "include contractors' workmanship, diligence, substitution of inferior materials, high costs and extra charges," Id. at 200 Conn. 719.

The language of the act is mandatory in nature. Certain provisions "shall" be complied with under subsection (a) to §20-429. The words "not available" do not set forth firm dates, CT Page 16344 the fact that the parties talked about the inability to determine such dates does not belie the fact that no such firm dates were written into the contract which is a mandatory and explicit requirement of subsection (a)(7).

The plaintiff argues that this case should be distinguished from Rizzo because as noted the date issue was discussed, the parties realized no such dates could be set forth at the time the contract was signed, "the law does not require one to perform the impossible," "not available was the best that could be done under the circumstances." (Page 7 of plaintiff s brief).

But this act posits the notion of an unsophisticated homeowner dealing with an experienced business person engaging in these contracts for a living and well aware of factors such as the time it takes to complete jobs, get permits, receive materials, etc. Given this scenario, the dangers to the consumer presented by absence of firm commencement and completion dates still exist even though their absence and the "reasons" therefore were brought to the homeowner's attention by the contractor and even though after the "conversation" between the homeowner and experienced businessperson the homeowner wants work to start without firm dates.

Taking an overview of the purposes of the act, but still mindful of fairness to the contractor, it makes more sense to say what the legislature made clear. Firm dates must be set forth. If the contractor is still pressed by the homeowner to begin work even though no such firm dates can be indicated through no one's fault, then the solution is easy. Let the contractor secure a written waiver from the homeowner of his or her rights under the act, specifically the right to have a commencement and completion date, cf. Wadia Enterprises, Inc. v. Hirschfeld, 224 Conn. 240,251 (1992).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Novella v. Hartford Accident & Indemnity Co.
316 A.2d 394 (Supreme Court of Connecticut, 1972)
Caulkins v. Petrillo
513 A.2d 43 (Supreme Court of Connecticut, 1986)
Barrett Builders v. Miller
576 A.2d 455 (Supreme Court of Connecticut, 1990)
Liljedahl Bros. v. Grigsby
576 A.2d 149 (Supreme Court of Connecticut, 1990)
Habetz v. Condon
618 A.2d 501 (Supreme Court of Connecticut, 1992)
Wadia Enterprises, Inc. v. Hirschfeld
618 A.2d 506 (Supreme Court of Connecticut, 1992)
Rizzo Pool Co. v. Del Grosso
657 A.2d 1087 (Supreme Court of Connecticut, 1995)
Dinnis v. Roberts
644 A.2d 971 (Connecticut Appellate Court, 1994)

Cite This Page — Counsel Stack

Bluebook (online)
1999 Conn. Super. Ct. 16341, Counsel Stack Legal Research, https://law.counselstack.com/opinion/caulkins-designs-v-trieb-no-549374-dec-20-1999-connsuperct-1999.