Castle Restoration & Construction, Inc. v. Castle Restoration, LLC

122 A.D.3d 789, 997 N.Y.S.2d 147
CourtAppellate Division of the Supreme Court of the State of New York
DecidedNovember 19, 2014
Docket2014-01448
StatusPublished
Cited by15 cases

This text of 122 A.D.3d 789 (Castle Restoration & Construction, Inc. v. Castle Restoration, LLC) is published on Counsel Stack Legal Research, covering Appellate Division of the Supreme Court of the State of New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Castle Restoration & Construction, Inc. v. Castle Restoration, LLC, 122 A.D.3d 789, 997 N.Y.S.2d 147 (N.Y. Ct. App. 2014).

Opinion

In an action to recover on a promissory note, commenced by motion for summary judgment in lieu of complaint pursuant to CFLR 3213, the plaintiff appeals from an order of the Supreme Court, Nassau County (Bucaria, J.), entered November 14, 2013, which denied its motion for summary judgment in lieu of complaint.

Ordered that the order is reversed, on the law, with costs, and the motion for summary judgment in lieu of complaint is granted.

The plaintiff made a prima facie showing of its entitlement to judgment as a matter of law by submitting the promissory note and proof of the defendants’ failure to make payments on the note according to its terms (see Banco Popular N. Am. v Victory *790 Taxi Mgt., 1 NY3d 381, 383 [2004]; Rachmany v Regev, 115 AD3d 840, 841 [2014]; Quadrant Mgt. Inc. v Hecker, 102 AD3d 410, 410 [2013]).

In opposition, the defendants failed to raise a triable issue of fact (see Banco Popular N. Am. v Victory Taxi Mgt., 1 NY3d at 383; Rachmany v Regev, 115 AD3d at 841; Cutter Bayview Cleaners, Inc. v Spotless Shirts, Inc., 57 AD3d 708, 709-710 [2008]). The defendants contend that they were not delinquent on the note because the parties entered into a subsequent oral construction management agreement, pursuant to which the defendants were to provide the plaintiff with labor and materials for additional construction projects, and the value of the labor and materials were to offset the defendants’ obligation under the promissory note. However, the defendants’ contention that the plaintiff and its president breached their contractual obligations under the alleged oral construction management agreement by refusing to offset the value of the labor and materials is not a defense to the plaintiffs motion. “ ‘[T]he general rule is that the breach of a related contract cannot defeat a motion for summary judgment on an instrument for money only unless it can be shown that the contract and the instrument are “intertwined” and that the defenses alleged to exist create material issues of triable fact’ ” (New York Community Bank v Fessler, 88 AD3d 667, 668 [2011], quoting Mlcoch v Smith, 173 AD2d 443, 444 [1991]). Here, the defendants failed to demonstrate that the alleged oral construction management agreement was “inextricably intertwined” with the promissory note (New York Community Bank v Fessler, 88 AD3d at 668; see Quadrant Mgt. Inc. v Hecker, 102 AD3d at 411; Nordea Bank Finland PLC v Holten, 84 AD3d 589, 590 [2011]; Stevens v Phlo Corp., 288 AD2d 56, 56 [2001]). Additionally, the defendants’ allegations of fraud are not set forth with specificity and are supported by mere conclusory allegations, which are insufficient to raise a triable issue of fact (see CPLR 3016 [b]; O’Brien v O’Brien, 258 AD2d 446, 446 [1999]; see generally Eurycleia Partners, LP v Seward & Kissel, LLP, 12 NY3d 553, 559 [2009]; Heffez v L&G Gen. Constr., Inc., 56 AD3d 526, 527 [2008]).

Accordingly, the court should have granted the plaintiffs motion for summary judgment in lieu of complaint.

Rivera, J.R, Skelos, Dickerson and Barros, JJ., concur.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

LCS Capital, LLC v. Luis
2025 NY Slip Op 01211 (Appellate Division of the Supreme Court of New York, 2025)
Matrix Bellport, LLC v. Crest Bellport, LLC
219 A.D.3d 725 (Appellate Division of the Supreme Court of New York, 2023)
Melrose Credit Union v. Itskovich
172 N.Y.S.3d 705 (Appellate Division of the Supreme Court of New York, 2022)
LoRusso v. DeLuca
204 A.D.3d 660 (Appellate Division of the Supreme Court of New York, 2022)
Melrose Credit Union v. Matatov
2020 NY Slip Op 05897 (Appellate Division of the Supreme Court of New York, 2020)
Bethpage Fed. Credit Union v. Luzzi
2019 NY Slip Op 8550 (Appellate Division of the Supreme Court of New York, 2019)
Loewenberg v. Basnight
2019 NY Slip Op 4157 (Appellate Division of the Supreme Court of New York, 2019)
Intermax Eco, LLC v. Eco Family Food Mart Corp
2019 NY Slip Op 3776 (Appellate Division of the Supreme Court of New York, 2019)
Margarella v. Ullian
2018 NY Slip Op 5926 (Appellate Division of the Supreme Court of New York, 2018)
Castle Restoration & Construction, Inc. v. Castle Restoration, LLC
2017 NY Slip Op 2625 (Appellate Division of the Supreme Court of New York, 2017)
Ahmad v. Luce
2017 NY Slip Op 1170 (Appellate Division of the Supreme Court of New York, 2017)
Jason J. Weindorf, CPA, P.C. v. Wightman
133 A.D.3d 822 (Appellate Division of the Supreme Court of New York, 2015)
Chervinsky v. Rezhets
132 A.D.3d 713 (Appellate Division of the Supreme Court of New York, 2015)
Wilson v. Neighborhood Restore Housing
129 A.D.3d 948 (Appellate Division of the Supreme Court of New York, 2015)

Cite This Page — Counsel Stack

Bluebook (online)
122 A.D.3d 789, 997 N.Y.S.2d 147, Counsel Stack Legal Research, https://law.counselstack.com/opinion/castle-restoration-construction-inc-v-castle-restoration-llc-nyappdiv-2014.