Cashman Equipment Corp. v. Boh Bros. Construction Co.

643 F. App'x 386
CourtCourt of Appeals for the Fifth Circuit
DecidedApril 11, 2016
Docket15-30038
StatusUnpublished
Cited by1 cases

This text of 643 F. App'x 386 (Cashman Equipment Corp. v. Boh Bros. Construction Co.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fifth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Cashman Equipment Corp. v. Boh Bros. Construction Co., 643 F. App'x 386 (5th Cir. 2016).

Opinion

PER CURIAM: **

This case involves a maritime contract dispute arising from a crane barge (the “barge”) charter agreement between Appellant Cross-Appellee Boh Brothers Construction Company, L.L.C. (“Boh”) and Appellee Cross-Appellant Cashman Equipment Corporation (“Cashman”). In the district court, the parties litigated multiple claims and cross-claims for damages and contract breach. After a bench trial, the district court prepared comprehensive findings and conclusions. On appeal, the parties continue to dispute, inter alia, whether an instrument titled the “Equipment Lease Agreement” (the “Equipment Lease”) was binding and enforceable, whether Boh owed six months of charter payments after it returned the crane barge to Cashman, whether Boh was entitled to “down time” compensation, and whether the district court properly adjudicated certain charter payment deductions and credits. We substantially agree with many of the court’s conclusions, but hold, in particular, that there was no meeting of the minds on the Equipment Lease. Accordingly, we AFFIRM in part, and REVERSE and REMAND in part for further proceedings to assess the impact of this conclusion, reassess interest, and revise a couple individual damages items.

BACKGROUND

Boh needed to charter a crane barge from Cashman to use on a bridge project in Sanibel Island, Florida. The parties entered into negotiations and signed a bare vessel charter agreement (the “Char *388 ter”) for use of the barge in 2005. The Charter references an Equipment Lease designed to cover the crane, but the Equipment Lease was separately negotiated by the parties.

In June 2008, Boh docked the barge in Cashman’s yard. An Off-Hire Survey (the “Survey”), however, was not conducted until December 2008. 1 In March 2009, Boh received an invoice for monthly charter payments spanning July 2008 to January 2009 and for repairs disclosed by the Survey. Boh refused to pay. Cashman sued to recover the invoice balance. Boh counter-claimed for repair expenses and for “down time” — when Boh’s crews were unable to work because the crane needed repair.

After a bench trial, the distinct court concluded that the Equipment Lease was binding, awarded charter payments and contractual interest to Cashman, awarded some, and disallowed other, charter payment deductions or credits, denied Boh’s “down time” claim, and denied Cashman’s request for attorneys’ fees. Both parties appeal.

STANDARD OF REVIEW

The interpretation of maritime contract terms is a matter of law reviewed de novo. Int'l Marine, L.L.C. v. Delta Towing, L.L.C., 704 F.3d 350, 354 (5th Cir.2013). When courts interpret maritime contracts, federal admiralty law applies. See HarWin, Inc. v. Consol. Grain & Barge Co., 794 F.2d 985, 987 (5th Cir.1986). “Factual findings are reviewed for clear error.... ” Tricon Energy Ltd. v. Vinmar Int'l Ltd., 718 F.3d 448, 453 (5th Cir.2013) (citing Hughes Training Inc. v. Cook, 254 F.3d 588, 592 (5th Cir.2001)). In light of these standards, the briefs, oral argument and pertinent portions of the record, we review the parties’ most significant issues.

DISCUSSION

a. The Equipment Lease

A maritime charter agreement is interpreted using the general rules of commercial contract interpretation and construction. 2 See E.A.S.T., Inc. of Stamford, Conn. v. M/V Alaia, 673 F.Supp. 796, 799-800 (E.D.La.1987) (“A charter comes into existence when the parties have a meeting of the minds on the essential terms of the charter.”), aff'd 876 F.2d 1168 (5th Cir.1989); 22 Williston on Contracts § 58;5 (4th ed. 2015) (“A charter is formed as soon as the traditional elements of a contract are present....”); see also G. Gilmore & C. Black, The Law of Admiralty § 4-1 at 196 (2d ed. 1975) (“Since most points of charter law involve construction of the charter, the principles are much the same as those of ordinary contract law”).

Where a contract expressly refers to and incorporates another instrument in specific terms, both instruments are to be construed together. This is known as the incorporation by reference doctrine. See 11 Williston cm Contracts § 30:25 (4th ed.1999). The doctrine may apply even if the second document is unsigned. One Beacon Ins. Co. v. Crowley Marine Servs., Inc., 648 F.3d 258, 268 (5th Cir.2011). But the reference to the second document must be clear and the document must be ascertainable beyond doubt. Id. The “[t]erms incorporated by reference will be valid so long as it is ‘clear that the parties to the agreement had knowledge of and assented *389 to the incorporated terms.’” Id. (quoting 11 Williston on Contracts § 30:25 (4th ed.1999)).

The district court relied on the incorporation by reference doctrine, concluding that the Equipment Lease was binding because (1) the Charter and the Equipment Lease referenced each other, and (2) Boh received a copy of the Equipment Lease. The district court added that Boh’s actions in inspecting the crane (as required by ¶ 2 of the Equipment Lease) further evidenced Boh’s assent to the terms of the Equipment Lease. This conclusion bore ramifications for several of the contract claims asserted by the parties.

On appeal, Boh contends that the Equipment Lease is unenforceable because there was no “meeting of the minds” as to the essential terms of the Equipment Lease. To support its contention, Boh cites uncon-troverted trial testimony revealing the following:

• The Charter was negotiated between Cashman’s vice president Brian Jones (“Jones”) and Boh employee Ron Bryl-ski.
• The Equipment Lease was negotiated on a separate and parallel track by Jones and Boh employee Mr. Biggers.
• The negotiation of the Equipment Lease involved the exchange of multiple drafts of the instrument. The proposed changes in the drafts included the assignment of responsibility for repairs between the parties.
• The Charter was ultimately signed. The Equipment Leasé was never signed and the negotiation of that instrument ceased when the Charter was signed.
• Boh believed that the Charter alone governed the parties’ relationship.

Based on this evidence, Boh argues that no meeting of the minds as to the essential terms of the Equipment Lease was ever reached.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Calicdan v. M D Nigeria
Fifth Circuit, 2023

Cite This Page — Counsel Stack

Bluebook (online)
643 F. App'x 386, Counsel Stack Legal Research, https://law.counselstack.com/opinion/cashman-equipment-corp-v-boh-bros-construction-co-ca5-2016.