Cascadia Wildlands Project v. Goodman

393 F. Supp. 2d 1041, 2004 U.S. Dist. LEXIS 28959, 2004 WL 2958420
CourtDistrict Court, D. Oregon
DecidedDecember 20, 2004
DocketCiv.04-1424-HO
StatusPublished
Cited by4 cases

This text of 393 F. Supp. 2d 1041 (Cascadia Wildlands Project v. Goodman) is published on Counsel Stack Legal Research, covering District Court, D. Oregon primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Cascadia Wildlands Project v. Goodman, 393 F. Supp. 2d 1041, 2004 U.S. Dist. LEXIS 28959, 2004 WL 2958420 (D. Or. 2004).

Opinion

Order

HOGAN, District Judge.

The first amended complaint alleges violations of the National Environmental Poli *1045 cy Act and National Forest Management Act related to the Davis Fire Recovery Project. Plaintiffs move for an order enjoining the project pending resolution of the merits of their claims.

Background

The Davis Fire burned approximately 21,000 acres in an area roughly ten miles west of LaPine, Oregon during late June and early July, 2003. Davis Fire Recovery Final Environmental Impact Statement (EIS) 1-2-3. Approximately 56% of the fire occurred within the Davis Late Suc-cessional Reserve (LSR). EIS 1-4. The Forest Service determined that “complete mortality” resulted on approximately 15,-600 acres. EIS 1-3. The Service identified a need to accelerate reforestation to meet objectives of the Davis LSR. EIS 1-6. Forest Supervisor Leslie Weldon decided to implement alternative B as described in the EIS, with minor modifications. Record of Decision (ROD) at 1. Proposed actions include 6,355 acres of commercial salvage logging, 8,400 acres of reforestation, including salvage units, 1,450 acres of fuels treatments outside of salvage units, and construction of eleven miles of temporary roads. EIS 2-30. Determining an emergency situation exists due to potential loss of value to the government, Regional Forester Linda Goodman exempted four salvage timber sale components of the project from the usual stay of decisions that are appealed to the Service. Defs’ Exs. 5 & 7.

Discussion

Plaintiffs will be entitled to an injunction if they demonstrate a sufficient degree of irreparable harm, considering the likelihood they will ultimately succeed on their claims, and whether the public interest favors an injunction. See United States v. Nutricology, Inc., 982 F.2d 394, 397 (9th Cir.1992).

I. Likelihood ofSixcess on Merits

A. 1st Claim — NEPA: Range of Alternatives

Plaintiffs argue that the Service failed to consider a project alternative that would initially abstain from intervening in the post-fire landscape, but would leave open the option of fuels reduction treatments if future conditions warrant, perhaps beginning in ten, thirty or sixty years. See Pis’ Memo, at 9. This alternative is not so likely to have consequences dissimilar to the no-action alternative that separate NEPA analysis is required. See Headwaters v. Bureau of Land Management, 914 F.2d 1174, 1181 (9th Cir.1990).

B. 2nd Claim — NEPA: Impacts to Soils

Plaintiffs argue defendants underestimated direct and indirect effects on soils for several reasons, and failed to assess cumulative effects of the Five Buttes Interface 1 and Crescent Lake Wildland Urban Interface projects.

■1. Direct and Indirect Effects

a. Burning of Slash Piles

Plaintiffs argue the Service does not disclose and discuss in the EIS detrimental soil conditions that will result from burning slash piles generated by commercial logging activities. The EIS states that studies show dramatic increases in soil pH below burn piles for up to “10 cm soil horizons,” nitrogen concentrations in these horizons is not reduced due to downward distillation of organic nitrogen from the burn piles and possibly from oxidation of nitrogen from roots in the top horizons, few studies have monitored long-term recovery of soil underneath burn piles, soil below burn piles may be depleted in nutrients and organic matter for a period of *1046 years, affected areas would vary unit by unit but generally would average less than 2% of unit areas, and most burn piles would occur on existing skid trails and landings. EIS 3-97-98. The Service provided some quantified information and a reasoned analysis. Moreover, the area where slash burning will occur has experienced high intensity wildfire. The court is ultimately likely to find the Service’s analysis sufficient.

b.Vagueness Re: Detrimental Soil Conditions

Plaintiffs next argue that it is impossible to determine from the EIS whether predicted quantities of detrimental soil conditions in table B-l of appendix B assume the implementation of planned mitigation measures. In text referring to table B-l, the EIS discloses that the subsoiling 2 mitigation measure will be applied in 20 activity units where the cumulative effects of project activities combined with past and foreseeable future actions could result in exceeding the standard and guideline amount (20%) of detrimental soil conditions in an activity area. EIS 3-96. The table itself indicates that subsoiling is planned for units with predicted detrimental soil conditions in excess of 20%. It appears to the court from the text and the table that the Service did not subtract acres planned for the subsoiling mitigation measure from the predicted quantities of detrimental soil conditions. Deschutes National Forest (DNF) Soil Scientist Peter Sussman confirms that table B-l lists predicted percentages of detrimental soil conditions before implementation of mitigation measures. Sussman Deck, ¶ 3.

Plaintiffs similarly fault the table for stating a “range class” of existing detrimental soil conditions for each unit, in addition to the percentage of existing detrimental soil conditions. The court finds nothing improper about this.

c. Scale of Analysis

Plaintiffs argue defendants limited their analysis of project effects on soils to the largest two subwatersheds within the project area, and failed to analyze effects at the timber sale unit level as required by the DNF Land and Resource Management Plan (RMP). The Service provided some separate analysis and data for the Odell Creek and Davis Lake subwatersheds for the stated reason that these subwat-ersheds contribute to perennial or intermittent streams. EIS 3-69. It is plain from the body of the EIS (EIS 3-96) and table B-l of appendix B that the Service analyzed existing conditions and predicted detrimental effects on soils for each harvest unit.

d. Misleading Use of Appendix B

Plaintiffs complain that the Service misleads the public by hiding information on individual harvest units in the appendix. The court disagrees. At oral argument, counsel for the Service asserted that the Service located table B-l in the appendix because of its size. That justification is reasonable, considering that table B-l is nearly three pages long. Moreover, the table is accurately summarized in the body of the EIS in text that refers the reader to the table. EIS 3-96. Plaintiffs’ cited authority does not prohibit the Service from using an appendix in this manner. 3

*1047 e. Omission of Road System

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
393 F. Supp. 2d 1041, 2004 U.S. Dist. LEXIS 28959, 2004 WL 2958420, Counsel Stack Legal Research, https://law.counselstack.com/opinion/cascadia-wildlands-project-v-goodman-ord-2004.