Cary-Lombard Lumber Co. v. Fullenwider

37 N.E. 899, 150 Ill. 629
CourtIllinois Supreme Court
DecidedJune 19, 1894
StatusPublished
Cited by12 cases

This text of 37 N.E. 899 (Cary-Lombard Lumber Co. v. Fullenwider) is published on Counsel Stack Legal Research, covering Illinois Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Cary-Lombard Lumber Co. v. Fullenwider, 37 N.E. 899, 150 Ill. 629 (Ill. 1894).

Opinion

Mr. Justice Shope

delivered the opinion of the Court:

This was a proceeding to enforce a mechanic’s lien by appellants for material furnished to a contractor with appellee, who erected a house for appellee upon certain lots of which he was owner. Section 29, chapter 82, of the statute, gives to every sub-contractor, mechanic, workman or other person who shall, in pursuance of the purposes of the original contract between the owner of any lot or piece of ground and the original contractor, perform any labor or furnish any material in building, altering, repairing, etc., any house or other building, shall have a lien for the value of such labor and materials, upon the house and lot, etc. Section 30 of the act provides that the person performing such labor or furnishing material shall cause a notice, in writing, to be served on the owner or his agent, the form of which notice is prescribed by the statute ; and it is provided therein that such notice shall not be necessary when the sworn statement of the contractor, provided for in section 35 of the act, shall serve to give the true owner notice of the amount due and to whom due. (See Butler & McCracken v. Gain, 128 Ill. 23.) Section 31 of the act is as follows: “If there is a contract in writing between the contractor and the sub-contractor, a copy of said sub-contract, if the same can. be obtained, shall be served with said notice and attached thereto, which notice shall be served within forty days from the completion of said sub-contract, or within forty days after payment should have been made to the person performing such labor or furnishing such material.”

We have repeatedly held that the law is to he strictly construed, and that a party seeking a lien thereunder must show compliance with its provisions. Butler et al. v. Gain, supra, and cases cited on page 27.

The principal difficulty in this case arises in construing section 31. It is contended, and has been held by the lower-courts, that to preserve a sub-contractor’s or material-man’s right to a lien, the notice must be served upon the owner after the completion of the sub-contract, or after payment should have been made to the person performing such labor or furnishing the material, and within forty days after the completion of the sub-contract or after the maturity of payment, and that a notice served prior to completion of the sub-contract, or prior to the time when payment should be made by the person performing the labor or furnishing the material, is not a compliance with the statute, and effective to preserve the lien. In this case it appears that, under the sub-contract,appellants, on February 2, 1892, commenced delivering to the contractor and builder, lumber and material to be used in erecting the building. By the contract all materials delivered in one month should be paid for on the first day of the succeeding month. The lumber delivered in February amounted to $214.70, and the balance, amounting in gross to $1241.45, was delivered in March, April, May and June, the last delivery being on the 16th day of the latter month. It is not seriously questioned that this was an entire contract, payments to he made as stipulated.

On February 8, six days after the sub-contract was entered into, and after the delivery of material had begun, appellant served a notice upon appellee, as owner, which, in form, was in strict compliance with the statute. It is said, that to preserve the lien, the notice should have been given after the completion of the delivery, June 16, and within forty days thereof, or after and within forty days of the first day of each month in which the lumber was delivered, for the- payment then falling due under the contract. We are not inclined to adopt this construction. It is to be observed that the 29th section of the statute creates the lien in favor of the subcontractor or material-man without limitation, other than that the liens therein authorized shall not exceed the price fairly-stipulated to be paid by the owner to the original contractor for the building or improvement made, and shall not exceed the amount of indebtedness due from the owner to the original contractor. (Sec. 33.) The purpose of sections 30 and 31 was to require notice to the owner, to the end that he should be protected against liens of which he had no notice. That the legislature had this purpose in view is clearly evinced by the proviso to section 30, that “such notice shall not be necessary where the sworn statement of the contractor provided for in section 35” of the act “shall serve to give notice to the true owner of the amount due and to whom due. ” And in the Butler-Gains case, supra, it was held, that where the contractor furnished the owner with a sworn statement, as provided in section 35 of the act, all the purposes intended by the notice provided for in section 30 are accomplished, and that the sub-contractor or material-man would not be required to serve the notice provided for in the latter section.

It might again be remarked that there is nothing in the prescribed notice to indicate that the work has been completed or that the money is due. It is: “You are hereby notified that I have been employed by......to (here state whether to labor or furnish material, and substantially the nature of the undertaking, etc.,) and that I shall hold the building, etc., liable for the amount that is or may become due me on account thereof.” It is apparent that, within the legislative contemplation, the notice would apply to contracts to labor or furnish material in the future, as well as to sums of money to become due; and while the substance of the notice, or substantial form of it, only, is prescribed, it clearly shows that the attention of the legislature was directed to, and the notice intended to apply to, sub-contracts not completed when it was given.

Keeping in view the purpose of requiring notice to enable the sub-contractor or material-man to enforce a lien upon the building and lot, what is fairly intended by the requirements of section 31, that the notice shall be served within forty days from the completion of the sub-contract, etc. ? It was clearly intended to place a limitation of time, beyond which notice would cease to be effective to protect the rights of the subcontractor under section 29 of the statute. The legislature has fixed forty days from or after the completion of the subcontract, or from or after the time payments thereunder would become due, as the period after which notice would cease to be effective to preserve the sub-contractor’s lien. This seems to admit of no controversy. “Prom the completion of the contract” would necessarily mean “after” the completion of the contract. But it will be observed that the statute does not prescribe that the notice shall be served within the forty days from or after the completion of the contract, etc. True, it says the “notice shall be served within forty days from the completion” of said sub-contract; but the word “within,” as here employed, is clearly used as a preposition, and in the sense that the service of notice is to be within the limit or compass of forty days after the completion of the sub-contract or the maturity of payments thereunder, and not later.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Jensen v. Nelson
19 N.W.2d 596 (Supreme Court of Iowa, 1945)
McKesson-Fuller-Morrisson Co. v. Chapell Ice Cream Co.
2 N.E.2d 561 (Appellate Court of Illinois, 1936)
People's Holding Co. v. Bray
173 A. 233 (Supreme Court of Connecticut, 1934)
Abromson v. Edmundson
136 N.E. 22 (Indiana Court of Appeals, 1922)
Hahn v. Citizens State Bank
171 P. 889 (Wyoming Supreme Court, 1918)
Brennan v. William P. McEvoy & Co.
196 Ill. App. 336 (Appellate Court of Illinois, 1915)
I. Lurya Lumber Co. v. Bernstein
168 Ill. App. 77 (Appellate Court of Illinois, 1912)
Bellion v. Durand
117 P. 798 (Utah Supreme Court, 1911)
Johnston v. New Omaha Thomson-Houston Electric Light Co.
125 N.W. 153 (Nebraska Supreme Court, 1910)
Grace v. Oakland Building Ass'n
46 N.E. 1102 (Illinois Supreme Court, 1897)

Cite This Page — Counsel Stack

Bluebook (online)
37 N.E. 899, 150 Ill. 629, Counsel Stack Legal Research, https://law.counselstack.com/opinion/cary-lombard-lumber-co-v-fullenwider-ill-1894.