Carter-Waters Oklahoma, Inc. v. Bank One Trust Co., N.A. (In Re Eufaula Industrial Authority)

266 B.R. 483, 2001 Colo. J. C.A.R. 4259, 2001 Bankr. LEXIS 1005
CourtBankruptcy Appellate Panel of the Tenth Circuit
DecidedAugust 21, 2001
DocketBAP No. EO-00-083, Bankruptcy No. 97-71225, Adversary No. 98-7021
StatusPublished
Cited by21 cases

This text of 266 B.R. 483 (Carter-Waters Oklahoma, Inc. v. Bank One Trust Co., N.A. (In Re Eufaula Industrial Authority)) is published on Counsel Stack Legal Research, covering Bankruptcy Appellate Panel of the Tenth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Carter-Waters Oklahoma, Inc. v. Bank One Trust Co., N.A. (In Re Eufaula Industrial Authority), 266 B.R. 483, 2001 Colo. J. C.A.R. 4259, 2001 Bankr. LEXIS 1005 (bap10 2001).

Opinion

OPINION

BOULDEN, Bankruptcy Judge.

Carter-Waters Oklahoma, Inc. (Carter-Waters) and Wells Enterprises, Inc. (Wells) (collectively, the Contractors) appeal a Judgment dismissing their complaint seeking to equitably subordinate the claim of Bank One Trust Co. (Bank One Trust) to the claims of the Contractors pursuant to 11 U.S.C. § 510(c) or, alternatively, upon theories of unjust enrichment, third party beneficiary, and misrepresentation. The bankruptcy court concluded that inequitable conduct was a necessary element of the Contractors’ claim for equitable subordination and found that the Contractors failed to prove that Bank One Trust had engaged in inequitable conduct. Having carefully reviewed the record, the parties’ arguments and applicable case law, we AFFIRM.

BACKGROUND

Sometime prior to 1993, the Debtor, Eu-faula Industrial Authority (Debtor), decided to develop and construct an outdoor amphitheater and amusement park (the Project) in Eufaula, Oklahoma. The Project was to be financed, in part, by a $5 million bond issue. The bonds were sold, and the proceeds were turned over to Bank One Trust, acting as Trustee of the Eufaula Industrial Bond Indenture (the Indenture) of December 1,1993. The beneficiaries of the Indenture trust were the related bondholders (the Bondholders). Both the real and the personal property comprising the Project were mortgaged to Bank One Trust as security for the bond obligations and for the benefit of the Bondholders.

In October 1994, the Debtor and Wells entered into a Contract for Concrete Foundation and Slabs for the Mega Star Amphitheater (the Wells Contract) for a total bid price of $340,700. Approximately a month later, the Debtor and Carter-Waters entered into a Contract for the Stage Building and Seating Roof for the Mega Star Amphitheater (the Carter-Waters Contract) for a total bid price of $535,446. Bank One Trust was not a party to either of these contracts. The Contractors commenced work and thereafter submitted payment requisitions to Bank One Trust.

Under the terms of the Indenture, Bank One Trust established an account into which proceeds of the Bonds were deposited for payment of approved requisitions (the Project Fund). As of February 1995, *486 the Project Fund balance was $572,209.48. Under Section 5.07 of the Indenture, “[a]ny disbursement by the Trustee [tjhereunder is a ministerial act and the Trustee has no duty or obligation to examine, review or monitor the use of such monies by the Authority.” Indenture at 27, in Appellants’ Appendix at 142. The Indenture further provides:

If the amounts requested to be disbursed exceed the Construction Budget, the Authority must, prior to disbursement [by the Trustee], set forth an amendment to the Construction Budget which either (1) provides for elimination or redesign of portions [of] the Project which have not yet been made the subject of a Construction Contract so that the total amount of the Construction Budget does not exceed the total amount of the Project Fund, or (ii) provide for the Authority to deposit in the Project Fund the full amount of the excess of the Construction Budget, as amended, over the Project Fund prior to such additional deposit.

Id. at 28-29, in Appellants’ Appendix at 143-44.

During the fall of 1994, Bank One Trust became aware that the Debtor was experiencing financial problems and had insufficient revenues to make a scheduled payment to the Bondholders. Bank One Trust was further advised in late January or early February of 1995 that there were additional problems and that the Project might be over-budget. Jake Riley (Riley), a senior vice-president in Bank One Trust’s Trust Department and the officer responsible for the day-to-day operations of Bank One Trust under the Indenture, testified that the $5 million raised under the Indenture was not intended to be the only source of funds for the Project. Along with the money raised through the issuance of bonds under the Indenture, the Debtor envisioned raising additional funds from other sources, including grants. Riley further testified that even after the Project appeared to be facing funding problems, representatives of the Debtor assured Bank One Trust that additional funding was in process.

On March 15, 1995, Bank One Trust paid $100,000 from the Project Fund to special workout counsel pursuant to a resolution of the Debtor and after receiving a requisition from the Debtor .requesting such payment. Based upon the Debtor’s assurances of additional funding, Bank One Trust, with other participants in the financing, assisted in preparing a March 30,1995, letter to the Bondholders explaining that the Debtor would need to obtain an additional $3.1 million to complete the Project, but the Debtor “is still committed to the project and has resolved to make every effort to get the project completed and operating successfully, including meeting all of the principal and interest obligations of the Bonds.” Letter at ¶ I, in Appellants’ Appendix at 139. As of March 31, 1995, the balance of the Project Fund was $369,066.93.

From December 1994 to May 1995, the Contractors submitted properly approved invoices for their work to Bank One Trust. Wells submitted invoices totaling $183,867.80, of which $139,759.46, or 76.01%, was paid by the Trust. Carter-Waters submitted invoices totaling $275,197.97, of which $193,604.85, or 70.3%, was paid by the Trust. No agent or employee of either of the Contractors ever inquired of Bank One Trust, and Bank One Trust never advised either of the Contractors, as to the existence in the Project Fund, or elsewhere, of sufficient funds to pay the Contractors’ invoices for construction work related to the Project.

The Debtor ultimately defaulted on its obligation under the Indenture and filed *487 for relief under Chapter 9 in 1997. The Project has not been completed, and its entire value has recently been appraised at $679,038. Of that amount, only $94,184 was attributable to the amphitheater on which Contractors performed their work. Bank One Trust’s claim on behalf of the Bondholders against the Debtor’s bankruptcy estate, and secured by a first lien on the Project, is $6,096,459.38. The Contractors Wells and Carter-Waters have asserted claims against the Debtor’s bankruptcy estate for $87,476.98 and $155,112.25, respectively.

After the Debtor filed its bankruptcy petition, the Contractors brought an adversary proceeding seeking to equitably subordinate the claim of Bank One Trust to their claims. Specifically, the Contractors assert claims against both the Debtor and Bank One Trust, and they seek an order equitably subordinating the claim of Bank One Trust pursuant to 11 U.S.C. § 510(c). 1 The Complaint alternatively asserts claims based on state law theories of unjust enrichment, third party beneficiary, and misrepresentation, and it seeks a money judgment against Bank One Trust and the Debtor.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
266 B.R. 483, 2001 Colo. J. C.A.R. 4259, 2001 Bankr. LEXIS 1005, Counsel Stack Legal Research, https://law.counselstack.com/opinion/carter-waters-oklahoma-inc-v-bank-one-trust-co-na-in-re-eufaula-bap10-2001.