Carstens Packing Co. v. Granger Irrigation District

295 P. 930, 160 Wash. 674, 1931 Wash. LEXIS 928
CourtWashington Supreme Court
DecidedFebruary 16, 1931
DocketNo. 22553. Department One.
StatusPublished
Cited by2 cases

This text of 295 P. 930 (Carstens Packing Co. v. Granger Irrigation District) is published on Counsel Stack Legal Research, covering Washington Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Carstens Packing Co. v. Granger Irrigation District, 295 P. 930, 160 Wash. 674, 1931 Wash. LEXIS 928 (Wash. 1931).

Opinion

Mitchell, J.

This action was brought by Carstens Packing Company, a corporation, to recover upon an appraisal of damages alleged to have been suffered *675 upon a breach of a written contract between the Gran-ger Irrigation District and Carstens Packing Company.

The Carstens Packing Company owned certain lands throug’h and over which, on March 23, 1923, it conveyed by deed to the United States a right of way for a pipe line, to be constructed by the United States for its use and the use of the Granger Irrigation District, in connection with the YaHma-Sunnyside division of the Yakima project of the United States Reclamation Bureau. On the same day, and in connection with the conveyance of that right of way, a written contract was entered into between the Granger Irrigation District, party of the first part, and Carstens PacHng Company, party of the second part, reciting that the second party had that day conveyed to the United States a right of way across its land in the south half of section 10, township 10 north, range 21 E. W. M., and reciting that whereas, the consideration for the agreement of conveyance of the right of way was the promise of the Granger Irrigation District to pay to Carstens PacHng Company

“. ... any actual damage accruing to the party of the second part, and to the above described land by virtue of the operations of the United States Reclamation Service in constructing of the pipe line for which said right of way was granted.
“Now, Therefore, in consideration of the execution of the aforementioned right of way agreement by the party of the second part, the party of the first part does hereby agree to pay to second party as damages to existing improvement upon said land such amounts as the parties hereto shall agree upon as of date September 1, 1923.
“It is understood and agreed that the party of the first part shall refill the trench and remove all surplus dirt and refuse, and in case of their failure so to do, *676 to pay to said party of the second part the actual costs of the labor necessary to accomplish said purpose.
“The District further agrees to pay such additional damages, if any, accruing to the party of the second part or its lessees by reason of injury to growing crops upon said land or crops to be grown upon said land during the season of 1923 by reason of the construction of said pipe line by party of the first part.
“It is hereby understood and agreed that if the parties hereto cannot agree upon the amount of damages suffered by the party of the second part by virtue of the location and construction of said pipe line, exclusive of the actual value of the land occupied, then a board of appraisers shall be selected, one by each party hereto, and the third by the two thus selected, who shall appraise the damage done to said property in accordance with the agreement herein contained, and the parties hereto agree to be bound by such appraisement. ’ ’

The United States Reclamation Bureau dug the necessary trench, and installed a concrete pipe line along this right of way for carrying water for irrigation purposes to other lands, refilled the trench (leaving the surplus dirt over the pipe line appreciably higher than the adjoining land), and finished all of the work performed by it upon and across the lands of the Carstens Packing Company, in the month of June, 1923. Shortly thereafter, upon completing the line across the lands beyond those of Carstens Packing Company, the United States Reclamation Bureau turned the irrigation line over to the Granger Irrigation District, which at all times since has controlled and operated it.

Plaintiff, claiming that it had sustained damage, appointed an appraiser and made written demand on the defendant in August, 1929, more than six years after construction had been completed across plaintiff’s lands, for the appointment of an appraiser to act as *677 a member of a board of appraisers under tbe terms of the contract to appraise damages. Tbe defendant refused to appoint an appraiser, whereupon tbe one appointed by plaintiff appointed another, and those two, upon giving notice of time and place, made, and, on August 30,1929, signed a written appraisal in favor of tbe plaintiff in tbe sum of $4,200 “by reason of tbe operation of tbe United States Reclamation Service in tbe constructing of a pipe line for irrigation purposes across said land (exclusive of tbe actual value of tbe land, occupied by said pipe line), as provided in said agreement,” and tbe further sum of $500 “by reason of tbe failure of said Granger Irrigation District to remove tbe surplus dirt and refuse on said land by reason of tbe construction of said pipe line, thereby leaving a mound or ridge of surplus dirt several feet higher than tbe level of tbe surrounding land. ’ ’

On tbe next day, August 31, 1929, this suit was brought to recover those two amounts. Tbe action is based upon tbe written appraisal. Tbe defendant’s answer consisted of general denials and an affirmative plea of tbe statute of limitations. Upon tbe trial without a jury, findings of fact and judgment were entered in favor of tbe defendant. Tbe plaintiff has appealed.

During tbe trial, tbe respondent was permitted, over objection, to amend its answer by alleging that, as to tbe item of $4,200, tbe appraisal was made upon a fundamentally wrong basis. This ruling has been assigned as error. Tbe amendment, as we understand it, went only to the appraisement as it appeared from tbe testimony of tbe appraisers themselves, and it is doubtful if any pleading was necessary in order to present tbe question respondent desired to present, which was more largely a question of law. However, appellant claimed no surprise on account of tbe amendment, nor asked for any continuance. Such matters *678 are subject to review and reversal only for abuse of discretion on the part of the trial court, which does not appear in this instance.

Error is assigned in refusing the item of $4,200. Appellant’s argument in this respect is that, by reason of the construction of the pipe line, the alkaline condition of its farm lands became increased, to its damage in the sum mentioned. An examination of the contract shows that after the preamble, it provides for only three kinds of possible damages: (1) Damages to existing improvements on the lands, nothing of which is claimed in this case; (2) the agreement to refill the trench and remove the surplus dirt, which, it is claimed, is involved in this action; and (3) damages, if any, to growing crops of the owner or its lessees during the season of 1923, nothing of which is claimed in this action.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Washington Security Co. v. State
114 P.2d 965 (Washington Supreme Court, 1941)
Temirecoeff v. American Express Co.
20 P.2d 23 (Washington Supreme Court, 1933)

Cite This Page — Counsel Stack

Bluebook (online)
295 P. 930, 160 Wash. 674, 1931 Wash. LEXIS 928, Counsel Stack Legal Research, https://law.counselstack.com/opinion/carstens-packing-co-v-granger-irrigation-district-wash-1931.