Carro & Carro Enterprises, Inc.

CourtArmed Services Board of Contract Appeals
DecidedMarch 10, 2015
DocketASBCA No. 59485
StatusPublished

This text of Carro & Carro Enterprises, Inc. (Carro & Carro Enterprises, Inc.) is published on Counsel Stack Legal Research, covering Armed Services Board of Contract Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Carro & Carro Enterprises, Inc., (asbca 2015).

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS

Appeal of -- ) ) Carro & Carro Enterprises, Inc. ) ASBCA No. 59485 ) Under Contract No. W912EP-07-C-0024 )

APPEARANCES FOR THE APPELLANT: Steven L. Reed, Esq. Douglas L. Tabeling, Esq. Lochlin B. Samples, Esq. Jonathan R. Mayo, Esq. Vianney Lopez, Esq. Smith, Currie & Hancock LLP Atlanta, GA

APPEARANCES FOR THE GOVERNMENT: Thomas H. Gourlay, Jr., Esq. Engineer Chief Trial Attorney Charles T. Pino, Esq. Susan E. Symanski, Esq. Engineer Trial Attorneys U.S. Army Engineer District, Jacksonville

OPINION BY ADMINISTRATIVE JUDGE HARTMAN ON APPELLANT'S MOTION TO DIRECT THE GOVERNMENT TO FILE THE COMPLAINT

Appellant seeks an Order from the Board directing the government to file the initial pleading or complaint in this appeal. The government opposes the motion. We deny the motion.

STATEMENT OF FACTS FOR PURPOSES OF THE MOTION

The United States Army Corps of Engineers, Jacksonville District (Corps), awarded Contract No. W912EP-07-C-0024 (Contract) to appellant, Carro & Carro Enterprises, Inc. (CCE), on 28 September 2007 for the performance of construction work on the Rio Puerto Nuevo flood control project in Puerto Rico that included the making of modifications to the De Diego Bridge abutments and piers due to widening and deepening of the existing channel, such as the drilling of shafts between existing piles of bridge abutments and piers and the tying of those shafts to the existing bridge structure with new cast-in-place caps (ASBCA No. 57821 (57821), R4 1, tab 4 at 1, 74). The

1 This appeal is consolidated with Carro & Carro Enterprises, Inc., ASBCA No. 57821, and 19 other appeals by CCE under the captioned contract. We, however, have Contract contained various standard Federal Acquisition Regulation (FAR) clauses, including FAR 52.232-5, PAYMENTS UNDER FIXED-PRICE CONSTRUCTION CONTRACTS (SEP 2002); FAR 52.233-1, DISPUTES (JUL 2002); and FAR 52.246-12, INSPECTION OF CONSTRUCTION (AUG 1996) (57821, R4, tab 4 at 104-05, 157-59, 168-70, 182-83). FAR 52.232-5 provides in pertinent part:

(b) Progress payments. The Government shall make progress payments monthly as the work proceeds, or at more frequent intervals as determined by the Contracting Officer, on estimates of work accomplished which meets the standards of quality established under the contract, as approved by the Contracting Officer.

(e) Retainage. If the Contracting Officer finds that satisfactory progress was achieved during any period for which a progress payment is to be made, the Contracting Officer shall authorize payment to be made in full. However, if satisfactory progress has not been made, the Contracting Officer may retain a maximum of 10 percent of the amount of the payment until satisfactory progress is achieved. When the work is substantially complete, the Contracting Officer may retain from previously withheld funds and future progress payments that amount the Contracting Officer considers adequate for protection of the Government and shall release to the Contractor all the remaining withheld funds. Also, on completion and acceptance of each separate building, public work, or other division of the contract, for which the price is stated separately in the contract, payment shall be made for the completed work without retention of a percentage.

(57821, R4, tab 4 at 158-59)

Under the "REMARKS" block of Payment Estimate No. 31 for the performance period of 1 November 2011 to 25 December 2011, the Corps stated:

Pay Activity 0009 lA Install 10 Drill Shafts - At this moment the Government will retain $75,000 (will not pay) of the actual remaining amount of $152,851.23. Therefore,

directed that complaints, answers, and supplemental Rule 4 files be filed in each of the different appeals.

2 $77,851.23 has been included in this payment application (No. 31) until a modification for a credit is negotiated.

(App. reply2, ex. 3)

On 9 April 2014, CCE submitted to the Corps contracting officer (CO) a certified claim stating she is withholding either $51,413.32 or $75,000.00, or both from CCE, for alleged known Pier 2 defects and demanding Corps payment of $126,413 .42 3 for "improper, unjustified, and unreasonable" withholding of progress payments. The claim added that, by withholding money based on alleged defects, the Corps is effectively asserting a government claim for which the Corps has the burden of proof. (Notice of Appeal (NOA), ex. 8 at 1, 4)

On 25 July 2014, the CO issued her final decision denying CCE's claim. The CO stated the Corps "began withholding retainage" and "continued through payment estimate #43," and "CCE was aware that the value of the deficiencies in Pier 2 were greater than the $75,000 [the Corps] withheld." The CO added: the Corps "withheld an additional $51,413.42" for Pier 2 defective work; the total withheld was based on "a reasonable calculation of the damages sustained" by the Corps but is unlikely "to cover the actual cost of the deficient work"; and "[a]s th[is] project draws to completion, the [Corps] plans to issue a Request for Proposal...to negotiate a credit for the Pier 2 work that did not comply with the specified quality requirements of the contract and maximum loading requirements of the original design." (NOA, ex. 7 at 3, 5)

On 11 August 2014, CCE timely appealed the CO's final decision to this Board.

2 CCE submitted a reply (to the Corps' opposition to CCE's motion to have the Corps file the complaint) which sought, in part, to strike parts of the Corps opposition without obtaining leave to file such a reply. The Corps subsequently submitted an amended opposition to CCE's motion deleting some material objected to by CCE without seeking leave to do so. It also filed a "response" to CCE's request to strike parts of the Corps' opposition asking the Board to disregard CCE's reply because the reply was supplied without CCE demonstrating good cause and receiving leave to file that reply. We grant both parties leave to file their respective documents with respect to the motion to have the Corps file the complaint, accept the parties' documents for filing, and consider the materials in ruling upon CCE' s motion. 3 Throughout the claim document, CCE sought the withheld amounts of$51,413.32 or $51,413.42 and $75,000.00. Since CCE specifically demanded a sum certain amount of$126,413.42, by calculation it appears that CCE's claim seeks $75,000.00 plus "$51,413.42" as withheld amounts.

3 DECISION

CCE has filed a motion with the Board for an order directing the government to file the complaint in this appeal contending the Corps' withholding of $126,413.42 for Pier 2 defects was a government claim for a reduction in contract price, and that the Corps bears the burden of proving its withholding was proper (app. mot. at 1-2). The Corps has responded that it asserted a claim against CCE for the withheld amounts due to CCE's failure to comply with contract requirements but argues that CCE possesses sufficient information to file a complaint here and the information to accurately and fairly determine the extent of damages due to CCE's non-conforming work rests with CCE, which was required by contract to maintain inspection records (gov't opp'n at 1-3).

As explained in Beechcraft Defense Co., ASBCA No. 59173, 14-1 BCA ii 35,592 at 174,395, CCE's motion to have the Board order the Corps to file the complaint in this appeal arises from the Contract Disputes Act's requirement that (1) all claims (whether asserted by the contractor or government) be the subject of a CO's decision (or deemed decision), 41 U.S.C. § 7103

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Kaminer Construction Corp. v. United States
488 F.2d 980 (Court of Claims, 1973)

Cite This Page — Counsel Stack

Bluebook (online)
Carro & Carro Enterprises, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/carro-carro-enterprises-inc-asbca-2015.