Carrington Gardens Associates v. United States

49 F. App'x 427
CourtCourt of Appeals for the Fourth Circuit
DecidedOctober 25, 2002
Docket01-1495
StatusUnpublished
Cited by3 cases

This text of 49 F. App'x 427 (Carrington Gardens Associates v. United States) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fourth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Carrington Gardens Associates v. United States, 49 F. App'x 427 (4th Cir. 2002).

Opinion

OPINION

PER CURIAM.

Carrington Gardens Associates (Carrington) appeals from the district court’s decision affirming the bankruptcy court’s grant of summary judgment in favor of the United States of America through the Secretary of Housing and Urban Development (HUD). After Carrington filed for bankruptcy relief pursuant to Chapter 11 of the Bankruptcy Code, it filed a breach of contract action against HUD in the bankruptcy court based on HUD’s refusals to grant rent increases and access to Carrington’s reserve account. The bankruptcy court determined that some of Carrington’s claims were time-barred by the six-year statute of limitations, 28 U.S.C.A. § 2401(a) (West 1994), and that HUD did not breach the contract regarding the remaining claims because Carrington had first breached the contract, and thus, because the contract was in default, HUD did not have to comply with its remaining ex-ecutory promises. In re Carrington Gardens Assoc., 248 B.R. 752 (Bankr.E.D.Va. 2000). On appeal, the district court affirmed the bankruptcy court in all respects. Carrington Gardens Assoc. v. United States, 258 B.R. 622 (E.D.Va.2001). Carrington argues on appeal that both courts erred in their characterization of its claims that they found time-barred, which made them only appear to have occurred six years prior to the filing of their suit, and erred regarding the remaining claims in determining that Carrington first breached the contract at issue. If the district court had considered the totality of *429 the circumstances, Carrington argues, Carrington’s one technical breach would be insufficient to allow HUD to deny it necessary rent increases and access to its reserve account. Unpersuaded, we affirm.

I.

Since May 15, 1985, Carrington has operated a low-income apartment project in Richmond, Virginia. To finance the operation of the apartment project, Carrington entered into a regulatory agreement with HUD pursuant to Section 236 of the National Housing Act, 12 U.S.C.A. § 1715z-l (West 2001) (the 236 Agreement), wherein Carrington assumed a nonrecourse, secured loan with an independent mortgagor, which HUD agreed to insure (the 236 Loan). The 236 Agreement regulated the rents that Carrington was permitted to charge and required compliance with HUD’s regulations. Upon default, HUD could accelerate the mortgage, proceed with foreclosure, collect the rents, and take possession of the project.

Carrington also entered into a Housing Assistance Payments (HAP) contract with HUD, wherein HUD agreed to subsidize roughly half of the rental units upon Carrington’s compliance with HUD’s housing regulations. As part of those regulations, HUD requires Carrington to submit a request to increase rent or obtain other funding. HUD then evaluates whether Carrington is in compliance with its regulations and contractual agreements and determines if the increase is financially justified based on Carrington’s financial statements for the project.

On February 28, 1989, Carrington obtained a nonrecourse, secured loan with an independent mortgage company pursuant to Section 241 of the National Housing Act, codified at 12 U.S.C.A. § 1715^6 (West 2001) (the 241 Loan), which HUD insured, based on a regulatory agreement that Carrington executed with HUD (the 241 Agreement). The 241 Agreement reiterated that HUD regulated the rents that Carrington was permitted to charge and required compliance with HUD’s regulations. As with the 236 Agreement and Loan, upon default, HUD could accelerate the mortgage, proceed with foreclosure, collect the rents, and take possession of the project.

The 241 Loan was made to finance capital improvements, and its funds were to be disbursed as the construction proceeded in accordance with the percentage completed. The capital improvements were specified in a construction contract that was part of the 241 Loan, which stated that no changes to the construction contract could be made without HUD’s prior approval and that the loan must remain in balance (i.e., the undistributed loan balance must equal or exceed the costs of completion). The 241 Loan would go into default if Carrington abandoned the project, ceased work, failed to complete the construction in accordance with the contract, or made changes to the contract without HUD’s approval.

After Carrington declared that most of the construction project was complete, HUD determined, through two inspectors, that the percentage of the work that Carrington had declared was complete was not, in fact, complete, that construction deviated from the construction contract, and that funds were used for projects for which they were not permitted. Therefore, in April 1990, HUD declined to allow further advances from the 241 Loan until the construction project’s completion was brought back into balance with the 241 Loan schedule. Efforts to resolve the problems were unsuccessful. Carrington later defaulted on the 241 Loan, which remained in default from 1991 onwards. On April 8 and 20, 1992, HUD reminded Carrington, by letter, that no funds were available under the 241 Loan because it *430 was in default. HUD audited Carrington in 1992 to determine if the project was being operated in accordance with the 236 Agreement and HUD’s regulations. HUD issued its report on June 22, 1992, for the time period between January 1, 1989, to September 30, 1991. HUD made twenty-eight adverse findings, which it presented to Carrington.

By 1995, Carrington had cleared all but four of HUD’s audit findings. On October 26,1995, HUD issued a supplemental audit report, which contained the following four violations of the 236 Agreement, which Carrington has failed to clear and which Carrington does not dispute: 1 (1) Carrington overpaid payroll costs to an independent management agency; (2) Carrington improperly used project operating funds for capital improvements; (3) Carrington did not provide sufficient documentation to support the costs paid out of the project funds; and (4) Carrington’s owners improperly withdrew money from the reserve account to fund operating deficiencies. Based on the supplemental audit report violations of the 236 Agreement, HUD declared the 236 Loan in default.

Between 1992 and 1997, Carrington requested five rent increases, which HUD denied based on the 236 Loan and 241 Loan defaults, Carrington’s failure to maintain sufficient funds in the reserve account, as required by the 236 Agreement and HUD’s regulations, and the uncleared audit findings. Carrington also made several requests between October 1992 and October 1995 for releases of funds from its reserve account. HUD denied these requests on the same bases. The project thus deteriorated because Carrington believed that it deserved rent increases and access to its reserve account before making any changes while HUD required that Carrington remedy its financial problems first.

Finally, HUD advised Carrington on October 12, 1995, that the entire balance on the 241 Loan was due and that HUD would proceed with foreclosure because the 241 Loan had remained in default since 1991. In October 1996, HUD proceeded with foreclosure because Carrington was $59,475.19 delinquent on the 236 Loan, was $179,803.37 delinquent on the 241 Loan, failed to provide financial statements, and otherwise failed to maintain the property. HUD set a foreclosure sale for December 12, 1997.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Arlene Delores Klemkowski
D. Maryland, 2025
Cenlar FSB v. Klemkowski
D. Maryland, 2025
Parkwood Associates Ltd. Partnership v. United States
97 Fed. Cl. 809 (Federal Claims, 2011)

Cite This Page — Counsel Stack

Bluebook (online)
49 F. App'x 427, Counsel Stack Legal Research, https://law.counselstack.com/opinion/carrington-gardens-associates-v-united-states-ca4-2002.