Carr & Baal Co. v. Consolidated Independent District

187 Iowa 930
CourtSupreme Court of Iowa
DecidedNovember 22, 1919
StatusPublished
Cited by5 cases

This text of 187 Iowa 930 (Carr & Baal Co. v. Consolidated Independent District) is published on Counsel Stack Legal Research, covering Supreme Court of Iowa primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Carr & Baal Co. v. Consolidated Independent District, 187 Iowa 930 (iowa 1919).

Opinion

Preston, J.

1. Counsel for appellant state that, as the appeal will be presented, the sole issue is this: Is the defendant Chicago Bonding & Surety Company liable to the plaintiff for the value of building materials furnished by plaintiff to the contractor, and used in the construction of the school building, by virtue of the bond furnished by said surety company to the school district? Errors are assigned by appellant, and they are that the trial court erred in holding that there was no privity between plaintiff and the bonding company; in holding that the bond was not given for the benefit of the plaintiff; in holding that there was no requirement of the bond or contract upon which plaintiff could base a claim for payment; and in dismissing the petition. The material part of the contract between the contractor and the school district is as follows:

“This agreement ' * * * witnesseth: That the said [932]*932party of the first part, for and in consideration of the payments to be made to and by the said second parties as hereinafter provided do hereby covenant, contract and agree to furnish all labor and materials necessary to finish and complete all the work of a two-story and basement school building (excepting the plumbing and heating) otherwise all work and material according to the plans, specifications and drawings (which are declared to be a part of this agreement), made by Morrison & Thorne architects (acting as agent for said owner), in a good substantial and workmanlike manner, to the satisfaction of and under the direction of the superintendent.

“And said first party also do agree to find, provide and furnish all labor and materials of such kinds, qualities and descriptions, as shall be fit, proper and sufficient for completing and finishing all the work or works mentioned (provided that possession of the premises be given to the contractor), on or before June 15, 1915, and completing the building on or before October 15, 1915. Time to be extended only in case of general strike, alterations, fire or unusual action of elements.

“And the second parties for and in consideration of the first party completely and faithfully executing the aforesaid work, and furnishing all the materials therefor, so as fully to carry out this contract, and the design, according to its true spirit, meaning and intent, and by and at the times mentioned, and to the full and complete satisfaction of Morrison & Thome superintendent do we hereby agree to pay to said party the sum of fifteen thousand seven hundred and eighty-three ($15,783.00)' dollars, lawful money of the United States on certificates of superintendent, from time to time, as the work progresses, to wit: 85 per cent of the estimated value of the same, subjected to additions and reductions, as hereinafter provided, and the remainder [933]*933on satisfactory completion and acceptance of the entire work, after the expiration of 20 days.

“It is agreed by the parties that fifteen per cent of the contract price shall be held by the owner as security for the faithful completion of the work, and may be applied, under the direction of the superintendent, in the liquidation of any damages under this contract; furnishing to the owner a release from any liens or right of lien, also a sworn statement, as required by law, before commencing work on this contract and hereby acknowledges receipt of notice to furnish same. * * *

“In witness whereof: The said parties have hereunto set their hands and seal the 4th day and year first above written.

“Oskar Knutson, (Seal)

“In presence of ' “J. Wilbur Anderson, (Seal)

“J. Cample W. Morrison “J. E. Sandiland. (Seal)”

It appears that a printed form of contract was used, and its blanks filled in. At the top of this form, the following appears in print:

“Copyrighted. For sale by Eugene Dietzgen Co. Chicago, New York, San Francisco, New Orleans, Pittsburg, Toronto.”

Appellees contend that this has a bearing on the construction of the contract; that the form is one in use in other states and Canada, and evidently refers to some requirement in the laws of some place other than Iowa; that the contractor must furnish some kind of a sworn statement to the owner “before commencing work on the contract.” The bond given by the contractor and surety company follows:

“Know All Men By These Presents: That we Oskar Knutson, of the city of Des Moines, and state of Iowa, as principal, and the Chicago Bonding and Surety Company, as surety, are held and firmly bound unto the Independent [934]*934School District of Bussey, Iowa, in the penal sum of forty-eight hundred dollars ($4,800), lawful money of the United States, well and truly to be paid to the said Independent School District of Bussey, Iowa.

“The condition of the above obligation is such that whereas the above-named Oskar Knutson has this day entered into a contract with the above mentioned Independent School District for the erection of a public school in the said town .of Bussey, Iowa. Now therefore if the said Oskar Knutson shall well and faithfully perform and keep all the conditions of said contract on his part to be kept and performed, and shall well and truly protect the interests of the said Independent School District, then this bond to be void, otherwise to remain in full force and effect.

“Witness our hands this 4th day of June, 1915.

“Signed by Oskar Knutson,

(Corporate Seal) “Chicago Bonding and Surety Co.,

“By Fred S. Young, Attorney in Fact.”

Thereafter, and pursuant to agreement between the contractor, Knutson, the plaintiff furnished lumber and mill work which was used in the construction of the school building, only a part of which has been paid. The contractor abandoned the work, and the district, under proper certificate of the architect, completed the building, and charged the expense thereof against the funds in his hands. This action is brought to establish plaintiff’s claim against funds alleged to be yet in the hands of the district, as provided by Code Section 3103, and to enforce payment by the Bonding Company of the balance of its account, on the theory that the original contract between the district and the contractor required the contractor to provide for the payment of materialmen, and that the Bonding Company had obligated itself to plaintiff in such sums as should be found due and unpaid, after exhausting the funds in the hands of the district. The trial court did establish and allow plaintiff’s [935]*935claim against the funds and in the amount that the court found was then in the hands of the district. Appellees contend that the bond is purely an indemnifying agreement; that the contract and specifications are not made a part of the bond; that the bond merely agrees to indemnify the School District against loss. Appellees say that, though appellant does not directly state that the building contract requires the contractor to furnish the district with releases from sworn statements, filed with the district by subcontractors, under Code Section 3102, yet appellant intimates this, by saying that plaintiff filed its sworn statement with the School District within the time and manner provided by that statute. Appellees think these two last-mentioned matters are of some importance. They deny that the contract contains any provision which requires the contractor to furnish the School District releases of claims filed under our statute.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bourrett v. W. M. Bride Construction Co.
84 N.W.2d 4 (Supreme Court of Iowa, 1957)
Cities Service Oil Co. v. Longerbone
6 N.W.2d 325 (Supreme Court of Iowa, 1942)
Conley v. Jamison
219 N.W. 485 (Supreme Court of Iowa, 1928)
Monona County v. O'Connor
215 N.W. 803 (Supreme Court of Iowa, 1927)
Philip Carey Co. v. Maryland Casualty Co.
206 N.W. 808 (Supreme Court of Iowa, 1926)

Cite This Page — Counsel Stack

Bluebook (online)
187 Iowa 930, Counsel Stack Legal Research, https://law.counselstack.com/opinion/carr-baal-co-v-consolidated-independent-district-iowa-1919.