Carpenter v. Lennane

132 N.W. 477, 166 Mich. 610, 1911 Mich. LEXIS 568
CourtMichigan Supreme Court
DecidedSeptember 29, 1911
DocketNo. 185.
StatusPublished
Cited by5 cases

This text of 132 N.W. 477 (Carpenter v. Lennane) is published on Counsel Stack Legal Research, covering Michigan Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Carpenter v. Lennane, 132 N.W. 477, 166 Mich. 610, 1911 Mich. LEXIS 568 (Mich. 1911).

Opinion

McAlvay, J.

Defendants have removed this case to this court, asking the reversal of a judgment obtained against them on account of claimed errors committed during the trial before a jury in the circuit court.

Such facts as may be necessary for an understanding of the case as are set forth in appellants’ brief, and not disputed by appellee, are adopted by the court and briefly stated as follows:

The defendants are copartners and conduct a general contracting business. In 1908 they entered into a contract with the Michigan Central Railroad to construct the subways on eight streets in the city of Detroit, Mich.; these subways being necessary to complete the grade separation then in progress in Detroit. Defendants’ contract with the Michigan Central Railroad, briefly stated, required them to excavate the earth, construct the retaining walls, lay the necessary sewers, grade the streets, grade the sidewalks, pave the streets, and construct the *612 cement sidewalks. In the preceding year, defendants had had a similar contract with the Michigan Central Railroad for the construction of a subway on Junction avenue. In the performance of the Junction avenue work, defendants sublet a part of the sidewalk construction to the plaintiff.

In June, 1908, defendant William E. Lennane and the plaintiff had an interview, which resulted in an agreement, the exact terms of which are a matter of dispute, respecting a portion of the construction work of the sidewalks on the eight streets where defendants were constructing subways. No other person was present at the interview. They both agree that the Junction avenue walk was mentioned in their interview, and that both parties wanted a different agreement than the one covering the Junction avenue work. Lennane says that defendants were to “ grade ” the work and furnish the cinders, and that Carpenter was then to take charge of the work and finish it; defendants were to advance all of the money needed, and guaranteed the price of most of the necessary materials, all of which Carpenter admits is true, but claims that the “grading” was, later in their interview, turned over to him to do. They both agree that 8£ cents was named as the price to govern on the work in question.

The dispute or difference between them is that: Lennane says the cost of the work performed under Carpenter’s supervision was to be figured on a basis of 8i cents per square foot, and the profit arising from its performance was to be divided, 60 per cent, to Carpenter, and 40 per cent, to Lennane. Carpenter says he was to receive Si cents for the work, making no division or accounting to Lennane in connection with the same, and in addition they agreed to let Carpenter do the grading, and the profit arising on the “ grading ” was to be divided, 60 per cent, to Carpenter, and 40 per cent, to Lennane.

The specifications for the sidewalk, in a general way, require a foundation of cinders, on top of which is placed the concrete mixture of sand and cement. Before laying *613 the cinders, the earth must be dug out, so that the sidewalk, when finished, comes to a proper grade. The “grading” therefore designated in the record was the preparation of the earth, by digging it to a proper depth and leveling it off, so that it was ready to receive the cinders. The excavating of the entire job, both for the street and the sidewalk, was done in the first instance, and in so far as possible, with steam shovels, and the finishing portion only was done by hand. Mr. Lennane’s explanation of the reason why he retained the grading of the walks, and would not include that in the work in which Carpenter was to participate, was because, in his general digging, he virtually covered all of the digging needed for the walks, and it was therefore simpler and better for him to do it all, looking to Carpenter to take the work when it was ready to receive the cinders. Defendants at no time during the trial admitted that the computations of plaintiff, even upon his own theory, were correct. It was agreed that plaintiff had constructed 101,357 square feet of sidewalk, and defendants admitted that a balance of $1,739.48 was due plaintiff. The trial resulted in a verdict for plaintiff in the sum of $3,781.09, being the entire amount claimed by him, with interest.

It is contended upon the part of appellants that error was committed by the court in refusing to instruct a verdict in their behalf, on the ground that the contract between the parties was a partnership contract, to be adjudicated only in a court of chancery, and that at least as to the percentage part (if a divisible contract) the court should have so instructed. In our view of the case, it will be of no importance to determine whether this was an entire contract or divisible. We do not agree that it was a partnership agreement. There is no indication that such was the intention of the parties, nor does the contract in question, as claimed by either party, contain the elements of a partnership, “which are, at the very least, community of interest in some business, for the conduct of which the parties are mutually principals of and agents for each *614 other, with general powers within the scope of the business.” Beecher v. Bush, 45 Mich. 188 (7 N. W. 785, 40 Am. Rep. 465). It is apparent in this case that the parties considered the agreement between them relative to percentage as one measuring the compensation for services to be rendered by plaintiff. Stockman v. Michell, 109 Mich. 348 (67 N. W. 336); Morrow v. Murphy, 120 Mich. 204 (79 N. W. 193, 80 N. W. 255). There is no evidence in the case tending to show that any losses incurred were to be shared by the parties. The only inference to be drawn from the evidence is that losses were not in any manner to be considered. No error was committed by the court in refusing the request of the defendants to instruct a verdict for them, or in refusing to grant a new trial upon the ground that this was a partnership agreement.

Defendants also contend that the court erred in excluding from the case testimony relative to the Junction avenue contract between these parties, in 1907, relative to other work of the same character, on the ground that it was referred to and considered by both parties at the time this contract was entered into, and some testimony in regard to it got into the case. In view of the fact that both parties agree that 8£ cents per square foot was the basis upon which the construction of the sidewalk was to be computed, and also agree upon the prices at which defendants offered to furnish materials, we do not see the materiality of this evidence relative to terms of the Junction avenue contract. So far as the record shows, nothing definite appears to be claimed for it, except as bearing upon the price. The dispute upon this branch of the case is whether plaintiff, for the construction of the 101,357 square feet of walk, was to receive the full price at 8£ cents per foot, or whether, with that price as a basis, after deducting the entire cost of construction, he was to receive 60 per cent, of the difference between such cost and the full amount computed at such price. Upon that dispute the testimony excluded *615 was not shown to be material.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Gilroy v. General Motors Corp.
448 N.W.2d 777 (Michigan Court of Appeals, 1989)
Cook v. Vineyard
289 N.W. 181 (Michigan Supreme Court, 1939)
Woodworth v. Ward
224 N.W. 397 (Michigan Supreme Court, 1929)
State v. Rosenberg
192 N.W. 194 (Supreme Court of Minnesota, 1923)

Cite This Page — Counsel Stack

Bluebook (online)
132 N.W. 477, 166 Mich. 610, 1911 Mich. LEXIS 568, Counsel Stack Legal Research, https://law.counselstack.com/opinion/carpenter-v-lennane-mich-1911.