Carpenter International, Inc. v. Kaiser Jamaica Corp.

369 F. Supp. 1138, 1974 U.S. Dist. LEXIS 12722
CourtDistrict Court, D. Delaware
DecidedJanuary 17, 1974
DocketCiv. A. 4352
StatusPublished
Cited by7 cases

This text of 369 F. Supp. 1138 (Carpenter International, Inc. v. Kaiser Jamaica Corp.) is published on Counsel Stack Legal Research, covering District Court, D. Delaware primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Carpenter International, Inc. v. Kaiser Jamaica Corp., 369 F. Supp. 1138, 1974 U.S. Dist. LEXIS 12722 (D. Del. 1974).

Opinion

OPINION

LATCHUM, Chief Judge.

Plaintiff, Carpenter International, Inc. (“Carpenter”), a Texas corporation, seeks to recover a .total of $534,942.38 from the defendants, Kaiser Jamaica Corp., Reynolds Jamaica Aluminum, Ltd. and Anaconda Jamaica, Inc., each a Delaware corporation and a partner in Alumina Partners of Jamaica (“Alpart”) for an alleged breach of a contract which Carpenter had entered into with Alpart. The jurisdiction of this Court is conferred by 28 U.S.C. § 1332.

The defendants have moved for summary judgment pursuant to Rule 56, F. R.Civ.P., on the ground that a release executed by the plaintiff bars the present action. The plaintiff has also moved for summary judgment to strike as insufficient at law the defense that the present action is barred by the proffered release. The background dealings between the parties concerning the alleged release may be summarized as follows:

On June 24, 1970 plaintiff entered into a written contract with Alpart to perform certain concrete work in connection with, construction of defendants’ St. Elizabeth Plant in Jamaica, West Indies. Plaintiff’s construction work was apparently near completion on June 8, 1971 when Douglas A. Robertson (“Robertson”), plaintiff’s project manager, wrote to R. W. Hart (“Hart”), defendants’ project manager, requesting that monies retained under the contract by defendants were due to the plaintiff and should be released immediately. (Hart afft., Ex. A). 1 The same day, Kenneth L. Sipes, Jr. (“Sipes”), plaintiff’s viee *1140 president of purchasing, also wrote to the defendants requesting that monies retained on the construction contract be released to the plaintiff. (Hart afft., Ex. B). Sipes included in his letter a “Release and Waiver of Lien” form which was signed by Daniel J. Shea (“Shea”), plaintiff’s executive vice-president. (Carpenter afft., Ex. A). 2 This release contained the following pertinent language:

RELEASE AND WAIVER OF LIEN ST. ELIZABETH PLANT CONTRACTS
“In consideration of the past payment of Kaiser Engineers Americas, Inc. (hereinafter called ‘Engineer’) acting as agent for the Owner, Alumina Partners of Jamaica, of $875,714. 40, receipt of which is hereby acknowledged, and in consideration of $132,960.55 to be paid by Engineer, acting as agent for the Owner to Carpenter International, Inc. (hereinafter called ‘Contractor’) and for other good and valuable consideration and in accordance with the Terms and Conditions of Contract No. 6942-0026 between Owner and Contractor dated as of 24 June 1970, as changed or amended through Change Order T Contractor hereby releases Owner and Engineer, their directors, officers, agents and employees and property from any and all claims arising directly or indirectly under said Contract, as amended including Field Transmittal Memoranda numbered 1 through 87, except for the following claims which are hereby expressly reserved.
Wage Escalation per Exhibit ‘G’ Any and all insurance claims.”

Hart reportedly received Robertson’s letter on June 9 and Sipes’ letter on June 14. (Hart afft., par. 8). Hart, after receiving Robertson’s letter which did not include a form of release, wrote on June 9 to Robertson explaining that the plaintiff must first comply with the procedures precedent to final payment outlined in the contract before the retained monies could be turned over to the plaintiff. (Hart afft., Ex. C). Article 23 E of the contract specifically required the plaintiff to execute a general release of any and all claims against the defendants arising from the contract before the defendants were obligated to turn over the final payment. 3 Robertson was assured by Hart’s letter that once the procedures precedent were complied with, the retention monies would be promptly paid.

Hart afterward received Sipes’ letter and Shea’s Release and Waiver of Lien but still was reportedly not satisfied with the express reservation of “Wage Escalation per Exhibit ‘G’ ” and “any and all insurance claims” contained in the release. (Hart afft., par. 10). However, after a telephone conversation with Robert D. Carpenter (“Carpenter”), president of plaintiff, the exceptions to the release were reworded to read: “Wage Escalation per Terms and Conditions of Contract”. Furthermore, the wording of the Shea release was altered to define the contract “as changed or amended through Change Order ‘J’ ” instead of “through Change Order T ” and the monetary recitations in the release were altered to reflect additional money which had been subsequently turned over to plaintiff. This revised release was signed on June 14, 1971 by Robertson (Hart afft., Ex. D) and apparently at least a major portion of the retained funds was released shortly thereafter (Hart afft., par. 12); although Carpenter points out the funds were not completely paid out until December 1971 (Carpenter afft., par. 31).

Defendants now contend that since the present action is based upon claims allegedly arising out of the contract, the *1141 Robertson release is an absolute bar at law.

Plaintiff disputes this assertion by, inter alia, 4 presenting an affidavit of Carpenter which contends that the actions and conduct of the defendants misled the plaintiff into believing that regardless of the broad language of the Robertson release, it was no bar to an action on the claims which are asserted in this case. This affidavit includes a letter by Carpenter to Hart dated June 1, 1971, requesting the defendants to give some consideration to relieving the economic burden placed on plaintiff due to unwarranted and unanticipated costs incurred in construction of the defendants’ plant which costs ultimately have come to form the basis of the claims in the present action. (Carpenter afft., Ex. B). Carpenter stated in the June 1 letter that while no claims had been filed as of that date, relief should be afforded the plaintiff in the form of a contract adjustment or future work. A conference was requested by Carpenter to discuss the matter of economic relief.

Carpenter further avers (par. 16) that in the very conversation with Hart on June 14 in which the language of the exceptions to the release was discussed, Hart assured him that a meeting concerning Carpenter’s June 1 letter was being planned and would be held in a short time. No suggestion was made by Hart that the release to be executed that day would in any way jeopardize plaintiff’s bargaining position at the contemplated meeting for the economic relief requested.

Plaintiff further argues that the release was executed primarily for the purpose of freeing funds to be used by the plaintiff for the benefit of the defendants. This is so, plaintiff asserts, because the money which was freed from retention was used by the plaintiff to satisfy a wage increase awarded unilaterally by defendants to plaintiff’s labor force and that the payment of the higher wages avoided a strike which would have crippled defendants’ entire plant construction and operation.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Simonson v. Travis
728 P.2d 999 (Utah Supreme Court, 1986)
Steinberg v. Shearson Hayden Stone, Inc.
598 F. Supp. 273 (D. Delaware, 1984)
Deakyne v. Department of Army
530 F. Supp. 1322 (D. Delaware, 1982)
Franchetti v. Intercole Automation, Inc.
529 F. Supp. 533 (D. Delaware, 1982)
Carroll v. Getty Oil Co.
498 F. Supp. 409 (D. Delaware, 1980)
Carpenter International, Inc. v. Kaiser Jamaica Corp.
393 F. Supp. 396 (D. Delaware, 1975)

Cite This Page — Counsel Stack

Bluebook (online)
369 F. Supp. 1138, 1974 U.S. Dist. LEXIS 12722, Counsel Stack Legal Research, https://law.counselstack.com/opinion/carpenter-international-inc-v-kaiser-jamaica-corp-ded-1974.