Caroline-A-Contracting, LLC v. J. Scott Campbell Constr. Co.

CourtCourt of Appeals of North Carolina
DecidedMarch 16, 2021
Docket20-60
StatusPublished

This text of Caroline-A-Contracting, LLC v. J. Scott Campbell Constr. Co. (Caroline-A-Contracting, LLC v. J. Scott Campbell Constr. Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of North Carolina primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Caroline-A-Contracting, LLC v. J. Scott Campbell Constr. Co., (N.C. Ct. App. 2021).

Opinion

IN THE COURT OF APPEALS OF NORTH CAROLINA

2021-NCCOA-62

No. COA20-60

Filed 16 March 2021

Haywood County, No. 16 CVS 266

CAROLINE-A-CONTRACTING, LLC, Plaintiff,

v.

J. SCOTT CAMPBELL CONSTRUCTION COMPANY, INC., Defendant.

Appeal by Plaintiff from judgment entered 14 June 2019 by Judge Bradley B.

Letts in Haywood County Superior Court. Heard in the Court of Appeals 27 January

2021.

McAngus Goudelock & Courie, PLLC, by John E. Spainhour and Lucienne H. Peoples, for Plaintiff-Appellant.

Van Winkle, Buck, Wall, Starnes & Davis, P.A., by Allan R. Tarleton and Martin E. Moore, for Defendant-Appellee.

INMAN, Judge.

¶1 Caroline-A-Contracting, LLC (“CAC”), a subcontractor found liable in tort for

damages it caused on a construction project, appeals from the trial court’s judgment

applying the collateral source rule to deny a credit for payments made to the general

contractor, J. Scott Campbell Construction Company (“Campbell”), by another

subcontractor. After careful review, we affirm.

I. FACTUAL & PROCEDURAL HISTORY CAROLINE-A-CONTRACTING, LLC V. J. SCOTT CAMPBELL CONSTR. CO.

Opinion of the Court

¶2 In early 2015, Campbell contracted to build a house in Maggie Valley, North

Carolina. As part of the project, Campbell hired Ariel Mendoza (“Mr. Mendoza”) of

Mendoza Masonry and Landscaping to construct a boulder retaining wall to support

a vehicle turnaround area. The wall collapsed twice during construction because its

water drainage system failed and its foundation was compromised after significant

rains. To remove his own damaged work, stabilize the slope, and erect the wall anew,

Mr. Mendoza contracted with CAC. Mr. Mendoza and CAC were the only parties to

the written contract, but the contract committed CAC to the “[c]ompletion of the work

and satisfaction of [Campbell] and [home-owner].”

¶3 While CAC was reconstructing the boulder wall, Campbell determined that the

new construction was a failure1 and ordered CAC to immediately stop work and

remove its equipment and employees from the site. Campbell then hired a

replacement contractor, Tim Burress (“Mr. Burress”), to raze the existing

construction and rebuild the wall, at a cost of $106,000. Campbell and Mr. Mendoza

each refused to pay CAC.

1At trial, Campbell testified that CAC had not correctly compacted the site to prevent

saturation and to stabilize the area for construction of the wall: “You could take a piece of rebar with your hand and sink it out of sight. It looked like a pond. There was so much water standing there. . . . It was just unacceptable work. . . . Everything about that job was questionable.” CAROLINE-A-CONTRACTING, LLC V. J. SCOTT CAMPBELL CONSTR. CO.

¶4 On 15 March 2015, CAC filed separate lawsuits against Campbell and Mr.

Mendoza.

¶5 CAC’s lawsuit against Mr. Mendoza for breach of contract alleged CAC had

incurred $20,000 in damages. Mr. Mendoza filed an answer and counterclaim

alleging that CAC’s work was defective, was not supervised by an engineer as

required by the contract, and caused damages to Mr. Mendoza exceeding $50,000.

¶6 CAC’s separate lawsuit against Campbell sought to recover damages for

breach of contract in the amount of $30,000 and, in the alternative, damages of

$35,000 in quantum meruit. Campbell denied the existence of a contract with CAC

as well as the basis for the quantum meruit claim. Campbell also asserted a

counterclaim of negligence for damages as a result of CAC’s work. In response to the

counterclaim, CAC raised a defense requesting a credit or offset against any amounts

paid by another source to Campbell for the damages Campbell claimed against CAC.

¶7 While both actions were pending, CAC learned that Mr. Mendoza had paid

money to Campbell related to damages caused by the defective retaining wall.

¶8 In the lawsuit against Campbell, CAC moved for summary judgment, arguing

that Campbell was not entitled to recover from CAC money damages that had already

been paid by Mr. Mendoza. In response, Campbell argued that the collateral source

rule should exclude evidence of such payments because Mr. Mendoza was an CAROLINE-A-CONTRACTING, LLC V. J. SCOTT CAMPBELL CONSTR. CO.

independent party. The trial court denied CAC’s motion for summary judgment in

September 2018.

¶9 Three months later, in December 2018, CAC and Mr. Mendoza dismissed with

prejudice their claims against each other. The terms of the dismissal are not reflected

in the record on appeal.

¶ 10 Following the dismissal of its action against Mr. Mendoza and two months

before trial of the action from which the appeal arises, CAC filed a motion for a credit

of at least $90,000 in the event of an adverse verdict on Campbell’s counterclaim,

based on payments Campbell had received from Mr. Mendoza. Campbell filed a

motion to exclude evidence of these payments. The trial court granted Campbell’s

motion based on the collateral source rule and because such evidence “might confuse

the jury or diminish any award based on the evidence.” The trial court allowed CAC

to proffer evidence pre-trial on its motion for credit and decided that if a verdict was

returned adverse to CAC, “the court will hear arguments that the award should be

reduced or credited by payments from [Mr.] Mendoza.”2

¶ 11 The case came on for trial in May 2019. The jury determined that CAC did not

have a contract with Campbell, but it awarded $5,000 to CAC in quantum meruit for

2By the time of trial, Mr. Mendoza had paid a total of $147,500 to repair damage

related to the wall––$105,000 to Campbell and $42,500 to the replacement contractor, Mr. Burress. CAROLINE-A-CONTRACTING, LLC V. J. SCOTT CAMPBELL CONSTR. CO.

its supplies and efforts to remediate the site. The jury also found that Campbell had

been damaged by CAC’s negligence in construction and awarded Campbell

$41,678.09 plus interest in damages.

¶ 12 After trial, CAC renewed its motion for credit based on Mr. Mendoza’s prior

payments to Campbell. The trial court denied CAC’s motion in an order that restated

the jury verdict and found, in relevant part:

28. . . . [Mr. Mendoza] paid [Campbell] $105,000 for costs attributable to the repair of the wall.

....

32. [T]he payments made by [Mr. Mendoza] to [Campbell] were not the result of any type of insurance coverage that [Campbell] had purchased.

38. The gravamen of this case turns on the status of [Mr.] Mendoza. The evidence is uncontroverted that [Mr.] Mendoza is independent of the Plaintiff, Caroline-A- Contracting, LLC. [Mr.] Mendoza is not an employee or agent of [CAC]. [Mr.] Mendoza was not a party to this lawsuit.

39. . . . [T]he work performed by [CAC] independent of [Mr. Mendoza] was determined to be negligent and damages were awarded to Campbell Construction.

42. Under the unique facts of this case . . . the payments made by [Mr.] Mendoza constitute payments made from an independent, collateral source. CAROLINE-A-CONTRACTING, LLC V. J. SCOTT CAMPBELL CONSTR. CO.

The trial court denied CAC’s motion for a credit, concluding:

2. [Mr.] Mendoza is a source independent of [CAC].

3. The collateral source rule applies in this case and as such its application bars the tortfeasor [CAC] from reducing its own liability for damages by any amount of compensation the injured party [Campbell] received from an independent source.

4.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hurd v. Nelson
714 P.2d 767 (Wyoming Supreme Court, 1986)
RPR & Associates, Inc. v. University of North Carolina-Chapel Hill
570 S.E.2d 510 (Court of Appeals of North Carolina, 2002)
Humphries v. City of Jacksonville
265 S.E.2d 189 (Supreme Court of North Carolina, 1980)
Fisher v. Thompson
275 S.E.2d 507 (Court of Appeals of North Carolina, 1981)
Ryals v. Hall-Lane Moving & Storage Co.
468 S.E.2d 69 (Court of Appeals of North Carolina, 1996)
Cates v. Wilson
361 S.E.2d 734 (Supreme Court of North Carolina, 1987)
Wilson v. Burch Farms, Inc.
627 S.E.2d 249 (Court of Appeals of North Carolina, 2006)
Young v. Baltimore and Ohio Railroad Company
146 S.E.2d 441 (Supreme Court of North Carolina, 1966)
Woodson v. Rowland
407 S.E.2d 222 (Supreme Court of North Carolina, 1991)
New Foundation Baptist Church v. Davis
186 S.E.2d 247 (Supreme Court of South Carolina, 1972)
Shaffer v. Debbas
17 Cal. App. 4th 33 (California Court of Appeal, 1993)
Holland v. Southern Public Utilities Co.
180 S.E. 592 (Supreme Court of North Carolina, 1935)
Hairston v. Harward
821 S.E.2d 384 (Supreme Court of North Carolina, 2018)
Katy v. Capriola
742 S.E.2d 247 (Court of Appeals of North Carolina, 2013)

Cite This Page — Counsel Stack

Bluebook (online)
Caroline-A-Contracting, LLC v. J. Scott Campbell Constr. Co., Counsel Stack Legal Research, https://law.counselstack.com/opinion/caroline-a-contracting-llc-v-j-scott-campbell-constr-co-ncctapp-2021.