Carolina Steel Corp. v. Palmetto Bridge Constructors

444 F. Supp. 2d 577, 2006 U.S. Dist. LEXIS 42278, 2006 WL 1726768
CourtDistrict Court, D. South Carolina
DecidedJune 20, 2006
DocketC.A. 2:05-1178-PMD
StatusPublished
Cited by2 cases

This text of 444 F. Supp. 2d 577 (Carolina Steel Corp. v. Palmetto Bridge Constructors) is published on Counsel Stack Legal Research, covering District Court, D. South Carolina primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Carolina Steel Corp. v. Palmetto Bridge Constructors, 444 F. Supp. 2d 577, 2006 U.S. Dist. LEXIS 42278, 2006 WL 1726768 (D.S.C. 2006).

Opinion

AMENDED FINDINGS OF FACT AND CONCLUSIONS OF LAW

DUFFY, District Judge.

This matter was tried without a jury from Monday, April 24, 2006, through Wednesday, April 26, 2006. The court— having heard the arguments, read the briefs of counsel, and considered the evidence, including the testimony of live witnesses, deposition testimony, and exhibits — enters a judgment in favor of Plaintiff Carolina Steel Corporation (“CSC”) in the amount of $1,062,816.61, plus interest thereon from February 18, 2005, at the legal rate of 8% percent, pursuant to S.C.Code Ann. § 34-31-20.

FINDINGS OF FACT

1. This case arises from a contractual dispute between Plaintiff CSC and Defendant Palmetto Bridge Constructors, Inc. (“Palmetto”).

2. CSC is a North Carolina corporation qualified to do business in South Carolina.

3. Defendant Palmetto is a joint venture between Defendant Tidewater Skans-ka, Inc. (“Tidewater”) and Defendant Flatiron Constructors, Inc. (“Flatiron”). Hereinafter, the court collectively refers to Defendants Palmetto, Tidewater, and Flatiron as “PBC.”

4. PBC, as prime contractor, entered into a contract (“the Prime Contract”) with the South Carolina Department of Transportation (“SCDOT”) to perform a construction project (“the Project”) commonly referred to as the Cooper River and Town Creek Bridge in Charleston, South Carolina, and more specifically identified by SCDOT File Numbers 10.257A & 10.432A and SCDOT Identification Number 7227.

5. In conjunction with the Prime Contract and the Project, PBC, as principal, and American Home Assurance Company (“American”), Federal Insurance Company (“Federal”), Fidelity & Deposit Company of Maryland (“Fidelity”), National Union Fire Insurance Company Of Pittsburgh, PA (“National”), and Zurich American Insurance Company (“Zurich”) (hereinafter collectively referred to as “the Sureties”) issued a payment bond (the “Bond”) and bound themselves, jointly and severally, pursuant to S.C.Code Ann. § 11-35-3030, to ensure the payment by PBC of the claims of all persons furnishing labor or *580 materials, or both, in the prosecution of the Project.

6. The Project was a “design-build” project. AlS a result, the final design was not complete when CSC bid the Project. CSC based its bid on five drawings (the “As-Bid Drawings”) provided by PBC; the five As-Bid Drawings all related solely to the interchange bridges and did not reflect that the Project would incorporate a seismic design rather than a standard SCDOT design.

7. In discussions during the summer and fall of 2001, CSC contemplated entering into a joint venture with High Steel Structures, Inc. (“High Steel”) and Augusta Iron & Steelworks, Inc. (“Augusta Iron”), whereby CSC, High Steel, and Augusta Iron would jointly fabricate all of the steel required for the Project.

8. Plaintiff contends that it did not form a joint venture with High Steel and Augusta Iron. Moreover, CSC asserts that it never authorized High Steel or Augusta Iron to represent CSC in any capacity and that neither High Steel nor Augusta Iron ever did so. Rather, Plaintiff CSC asserts that it represented its own interests at all times.

9. Based upon CSC’s bid, PBC awarded CSC a Purchase Order (“Purchase Order”), dated November 2, 2001, wherein CSC agreed to detail, furnish, fabricate, prime, paint, and deliver certain structural and miscellaneous steel to PBC for use in the Project.

10. The Purchase Order originally required CSC to supply approximately 11,-514,080 pounds of steel for the Charleston interchange bridges and provided that CSC be paid at the unit cost of $0,933 per pound of steel supplied for the Project.

11. Because the Project was a design-build project, the Purchase Order included a clause providing that a “[sjubstantial deviation in design may necessitate a change in cost which will be determined on a case by case basis per the Terms and Conditions of the Purchase Order.” (Vol.I, Ex. 11.) The Purchase Order set forth the following examples of a substantial deviation in design: “changing fillet welds to full penetration welds, changing straight girders to curved, changing structure designed as an I-girder structure to boxes, and changes in lengths of individual girders that exceed 160 lineal feet.” (Vol.I, Ex. 11.)

12. In August of 2002, PBC furnished to CSC the Released For Construction Drawings (“RFC Drawings”) for two of the nine interchange bridges for which CSC was responsible. The RFC Drawings reflected, among other things, that the interchange bridges had increased weight and complexity because of, among other things, earthquake, hurricane, and ship collision criteria. Due to the various bridge design changes and because CSC assumed the obligations of Augusta Iron, CSC ultimately supplied more than 20 million pounds of steel to PBC for the Project.

13. CSC asserts that on September 4, 2002, it made proposals for simplifying the design during a meeting with PBC and the Project’s designers. For example, CSC asserts that it made suggestions to simplify the girder webs, intermediate cross frames, cross box diaphragms, end plate diaphragms, and temporary cross frames. (Vol.I, Ex. 15.) However, CSC claims that its suggestions were not incorporated into the Project.

14. CSC asserts that it fully and timely performed its obligations under the Purchase Order.

15. CSC last furnished materials for the Project on or about February 4, 2005.

16. CSC states that it invoiced PBC for $21,654,130.55, but that PBC has only paid *581 $20,108,142.16. 1 CSC claims that it timely served upon Defendants notice of its claim under the Bond as well as its formal Proof of Claim for the outstanding balance which was then due and owing to CSC under the terms of the Purchase Order.

17. On or about July 14, 2004, PBC’s Joint Venture Executive Committee instructed PBC’s management to “[a]udit representative shop drawings of structural steel and rebar for exact final payments to subcontractors and suppliers and for the E & 0 claim” and to “[vigorously dispute vendor/subcontractor claims for extras.” (Vol.I, Ex. 41.)

18. Thereafter, PBC identified the following six issues to support its withholding of payment to CSC: (a) straddle bents; (b) increased web thicknesses; (c) intermediate cross frames; (d) cross box diaphragms and end plate diaphragms; (e) tie-in steel; and (e) temporary cross frames.

19. PBC did not notify CSC that it would be withholding payment until August of 2004.

20. CSC asserts that on February 18, 2005, it demanded that the Sureties make a fair and reasonable investigation of the merits of the amounts CSC claims PBC owes. CSC asserts that it also demanded that PBC and the Sureties pay the entire amount due or pay whatever amount was deemed due after investigation, as required by S.C.Code Ann. § 27-1-15.

21. Plaintiff CSC asserts that Defendants did not make a fair and reasonable investigation into the merits of the amounts CSC claimed PBC owed to it. CSC states that although PBC made a partial payment to CSC after February 18, 2005, no evidence exists that the Sureties made any investigation after February 18, 2005.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
444 F. Supp. 2d 577, 2006 U.S. Dist. LEXIS 42278, 2006 WL 1726768, Counsel Stack Legal Research, https://law.counselstack.com/opinion/carolina-steel-corp-v-palmetto-bridge-constructors-scd-2006.