Carolina Casualty Insurance v. Ragan Mechanical Contractors, Inc.

584 S.E.2d 646, 262 Ga. App. 6, 2003 Fulton County D. Rep. 2053, 2003 Ga. App. LEXIS 812
CourtCourt of Appeals of Georgia
DecidedJune 26, 2003
DocketA03A0150
StatusPublished

This text of 584 S.E.2d 646 (Carolina Casualty Insurance v. Ragan Mechanical Contractors, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Georgia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Carolina Casualty Insurance v. Ragan Mechanical Contractors, Inc., 584 S.E.2d 646, 262 Ga. App. 6, 2003 Fulton County D. Rep. 2053, 2003 Ga. App. LEXIS 812 (Ga. Ct. App. 2003).

Opinion

Adams, Judge.

Ragan Mechanical Contractors, Inc. filed suit against Lateo Construction Company, Inc.; Carolina Casualty Insurance Company; and Everest Reinsurance Company seeking to recover for labor and materials supplied as a subcontractor in connection with the construction of Lithonia High School. Lateo was the general contractor, and Carolina Casualty and Everest were co-sureties on the performance and payment bonds on the project. Carolina Casualty and Everest appeal from the trial court’s grant of partial summary judgment to Ragan. We affirm.

In January 2000, Lateo entered into a contract with the DeKalb County Board of Education for the construction of the high school. Pursuant to the terms of this general contract, Lateo obtained performance and payment bonds, and these were issued jointly by Carolina Casualty and Everest on behalf of Lateo and in favor of the board.

In connection with the project, Lateo entered into a subcontract with Ragan on January 18, 2000, for the performance of the mechanical, HVAC and plumbing work. Work proceeded on the project until approximately December 8, 2000, when the board of education issued a stop work directive. As a result, Lateo directed Ragan to cease all work on the project. The subcontractor stopped working at that time and never resumed its work. Ragan was not paid for all of the work it performed on the project, although Lateo was paid for the work.

On March 6, 2001, the board of education terminated Latco’s “right to proceed” on the project, stating that it considered the contractor to be in default. As a result, the board demanded that Carolina Casualty and Everest discharge their obligations under the performance bond. The co-sureties subsequently entered into a Takeover Agreement with the board of education under which they agreed to complete Latco’s general contract. The co-sureties engaged the services of de Oplossing, Inc. to manage the project’s completion, de Oplossing asked each of Latco’s subcontractors to sign a ratification agreement, under which the subcontractor would agree to complete its work on the project.

Ragan declined to sign the ratification agreement, and instead sought to obtain payment for its work on the project from Lateo and from the co-sureties under the payment bond. After they refused to *7 pay Ragan, the company filed this action, and the co-sureties took the position that Ragan had failed to perform its obligation to complete its work under the subcontract. 1 The parties filed cross-motions for partial summary judgment seeking a determination as to whether Ragan’s subcontract was terminated when the board terminated Latco’s right to proceed. The trial court granted Ragan’s motion for partial summary judgment, and denied the co-sureties’ motion, holding that Ragan had no further obligations under the subcontract.

1. Carolina Casualty and Everest first assert that the trial court erred in holding that the board of education’s termination of Latco’s right to proceed also resulted in the downstream termination of Ragan’s subcontract. We find no error.

As an initial matter, we note that nothing in the subcontract specifically obligated Ragan to complete its work for the benefit of the co-sureties in the event of Latco’s termination. Carolina Casualty and Everest contend, however, that Ragan’s obligations to perform continued because the termination provision in the subcontract had not been triggered. Accordingly, this issue is governed by the termination provision found in paragraph 15 of the subcontract, which provides:

Should [the board of education] terminate the [general] Contract or any part of the [general] Contract which includes the Subcontractor’s Work, this Contract shall also be terminated and Subcontractor shall immediately stop Subcontractor’s related Work.

Applying the cardinal rule of contract construction, we must ascertain whether the parties intended at the time they entered into the subcontract that Ragan’s obligations under that agreement would terminate if the board of education terminated Latco’s performance under the general contract. See Atlanta Development v. Emerald Capital Investments, 258 Ga. App. 472, 477 (1) (574 SE2d 585) (2002). It is a fundamental rule of contract construction that we must look to the whole contract in arriving at the construction of any part. OCGA § 13-2-2 (4). Accordingly, we must construe the subcontract as a whole in determining the parties’ intent under paragraph 15.

Although the parties agree that the subcontract incorporated the general contract by reference, Ragan did not agree to be directly bound to the board of education under that contract. Rather, it undertook only certain obligations in connection with the general *8 contract. Specifically, Ragan agreed to perform its work in compliance with the specifications of the general contract and subject to the approval of Lateo, the architect and the board of education. 2

The language of the subcontract demonstrates, however, that Ragan’s primary undertaking was to perform its work for the benefit of Lateo and for the purpose of enabling Lateo to meet its obligations under the general contract. In that connection, under two separate provisions of the subcontract, Ragan assumed “toward [Latco] all of the obligations and responsibilities that [Lateo] assumed toward [the board of education]” in connection with the mechanical, HVAC and plumbing work on the project. (Emphasis supplied.) In addition, Ragan agreed to start work when notified by Lateo and to complete work “at such times as will enable [Lateo] to fully comply with the main contract.” Thus, while Lateo was obligated to the board of education to perform work under the general contract, Ragan was obligated to Lateo under the subcontract to assist in performing that work.

Paragraph 15 of the subcontract provides that if the board of education terminated “any part” of the general contract “which includes the Subcontractor’s Work,” then the subcontract was also terminated. The subcontractor’s work was to assist Lateo in performing its obligations under the general contract. Therefore, we find that when the board of education terminated Latco’s obligation to perform, Ragan’s obligation to assist in that performance was also terminated.

Carolina Casualty and Everest assert, however, that paragraph 15 of the subcontract applied only where the board of education terminated the general contract as a whole. And they contend that the board did not terminate the general contract because it wanted to preserve its rights under the performance bond. But this argument ignores the plain language of paragraph 15, which provides that the subcontract will terminate either when the general contract is terminated or if “any part” of the general contract involving the subcontractor’s work is terminated. This language clearly contemplates that something less than a termination of the entire general contract could trigger the subcontract’s termination.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Atlanta Development, Inc. v. Emerald Capital Investment, LLC
574 S.E.2d 585 (Court of Appeals of Georgia, 2002)

Cite This Page — Counsel Stack

Bluebook (online)
584 S.E.2d 646, 262 Ga. App. 6, 2003 Fulton County D. Rep. 2053, 2003 Ga. App. LEXIS 812, Counsel Stack Legal Research, https://law.counselstack.com/opinion/carolina-casualty-insurance-v-ragan-mechanical-contractors-inc-gactapp-2003.