Carnett's Properties, LLC v. Jowayne, LLC

CourtCourt of Appeals of Georgia
DecidedMarch 19, 2015
DocketA14A1604
StatusPublished

This text of Carnett's Properties, LLC v. Jowayne, LLC (Carnett's Properties, LLC v. Jowayne, LLC) is published on Counsel Stack Legal Research, covering Court of Appeals of Georgia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Carnett's Properties, LLC v. Jowayne, LLC, (Ga. Ct. App. 2015).

Opinion

FOURTH DIVISION DOYLE, P. J., MILLER and DILLARD, JJ.

NOTICE: Motions for reconsideration must be physically received in our clerk’s office within ten days of the date of decision to be deemed timely filed. http://www.gaappeals.us/rules/

March 19, 2015

In the Court of Appeals of Georgia A14A1604. CARNETT’S PROPERTIES, LLC v. JOWAYNE, LLC. DO-082

DOYLE, Presiding Judge.

Carnett’s Properties, LLC, (“Carnett”) filed the instant action for breach of

contract and declaration of a special lien, alleging that JoWayne, LLC, (“JoWayne”)

failed to pay sums due under a maintenance agreement related to storm water runoff

and water detention needs of the two entities’ property. After the parties filed dueling

motions for summary judgment, the trial court granted JoWayne’s motion, finding

that JoWayne was not liable under the contract for the sums in question. Carnett

appeals, arguing that the trial court erred by finding that the maintenance agreement

did not contemplate that JoWayne would be liable for construction of an additional

detention pond. For the reasons that follow, we reverse and remand for further

proceedings. To prevail on a motion for summary judgment, the moving party must

demonstrate that there is no genuine issue of material fact and that the undisputed

facts warrant judgment as a matter of law. We review the evidence and record de

novo, construing all reasonable conclusions and inferences in favor of the

nonmovant.1

The construction of a contract is a question of law for the court. This Court construes contracts so as to give them the meaning which will best carry out the intent of the parties. In doing this, we must look at the instrument as a whole and consider it in light of all the surrounding circumstances. Thus, the favored construction will be that which gives meaning and effect to all the terms of the contract over that which nullifies and renders meaningless a part of the document. If the trial court determines that the language is clear and unambiguous, the court simply enforces the contract according to its clear terms; the contract alone is looked to for its meaning.2

So viewed, the evidence shows that in October 2002, Carnett sold to JoWayne

(which operates a daycare center) a parcel of approximately 1.69 acres of its 13.85-

1 Bank of North Ga. v. Windermere Dev., 316 Ga. App. 33, 34 (728 SE2d 714) (2012). 2 (Citations and punctuation omitted.) Primary Investments, LLC, v. Wee Tender Care III, Inc., 323 Ga. App. 196, 198 (1) (746 SE2d 823) (2013), quoting OCGA § 13-2-1.

2 acre property, and at that time, the parties executed a “Declaration of Joint Easement

and Joint Maintenance Agreement” (“the Agreement”). In the Agreement, Carnett

provided JoWayne with a drainage easement over the property it retained after the

sale, and JoWayne agreed to pay 12 percent of costs associated with the maintenance,

upkeep, redesign, or improvement of the detention facility serving the total 13.85

acres of Carnett’s original property.

Over the next few years, Carnett sold off additional portions of the remaining

acres, entering into similar easements and agreements with those new property

owners. Because of various regulations, Carnett added a detention pond to the

property in order to service all of the various property owners of the 13.85 acres. The

cost of this expansion was $237,442 of which 12 percent totaled $28,493.04. Carnett

invoiced JoWayne for the 12 percent, but JoWayne refused to pay, contending that

the agreement did not encompass the construction of a new detention pond into which

its drainage did not flow.

Carnett brought suit claiming breach of contract, and the parties filed cross

motions for summary judgment. The trial court granted summary judgment to

JoWayne finding that the Agreement did not contemplate the construction of a new,

separate detention pond. The trial court also found that the Agreement only referred

3 to “the Detention Facility,” such that the plain language concluded that JoWayne was

liable only for 12 percent of the sums related to the maintenance and upkeep of the

then-existing detention pond and not a newly constructed detention pond.

Carnett argues on appeal that the trial court erred by ruling that the contract

does not contemplate the construction of additional detention ponds.

The cardinal rule of contract construction is to ascertain the intention of the parties. If the terms of a contract are plain and unambiguous, the contractual terms alone determine the parties’ intent. A dictionary can supply the plain and ordinary meaning of a term, but a dictionary does not always provide a complete answer. If a term used in a contract is of uncertain meaning and may be fairly understood in more ways than one, it is ambiguous, and we apply the rules of contract construction in an effort to resolve the ambiguity. The proper construction of a contract is a question of law for a court to determine.3

The trial court used a number of pages to explain the meaning of the word

“the” before determining that the detention “facility” for which JoWayne was

responsible under the contract was limited to the detention pond already in use. This

conclusion, however, “ignores an equally plausible and opposite construction of the

[Agreement] language,” i.e., that “facility” means any portion of the two properties

3 (Citations and punctuation omitted.) Garrett v. Southern Health Corp. of Ellijay, Inc., 320 Ga. App. 176, 182 (1) (739 SE2d 661) (2013).

4 used for storm water detention to meet the needs of the two properties and their future

purchasers.4

While it is correct that the contract initially describes the first detention pond,

the contract later states that the parties

do mutually covenant and agree that all expenses associated with any upkeep and maintenance of the detention facility including, but not limited to, any redesign or expansion of the detention facility to meet the future needs of the Carnett Property, the JOWAYNE property[,] and any other properties currently using the Carnett Detention Facility as of the date of this agreement shall be shared by the owner of the JOWAYNE property and the Carnett property. Each of the parties to this agreement acknowledge that the total number[s] of acres being served by the Carnett’s Detention Facility is 13.85 acres.5

The contract specifically references anticipated future development of the remaining

Carnett property and explains that those future owners would contribute to detention

facility costs under a similar percentage share as JoWayne.

4 Amah v. Whitefield Academy, Inc., __ Ga. App. __ (1) (Case No. A14A2101; decided Mar. 18, 2015). See also Webster’s Third New International Dictionary 812- 813 (1981) (defining facility as “something . . . that is built, constructed, installed, or established to perform some particular function or to serve or facilitate some particular end”). 5 (Emphasis supplied.)

5 Other terms in the contract lend support to the conclusion that “facility” could

mean any number of ponds in addition to or in place of the original one, i.e.,

“expansion,” “redesign,” and “improvement,” which are anticipated activities for

which JoWayne accepted the responsibility to pay. Redesign, for instance, means “to

revise in appearance, function, or content”6 or to “design (something) again in a

different way.”7 And the contract did not limit “upkeep and maintenance” only to

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Higginbotham v. Knight
719 S.E.2d 1 (Court of Appeals of Georgia, 2011)
Bank of North Georgia v. Windermere Development, Inc.
728 S.E.2d 714 (Court of Appeals of Georgia, 2012)
Kammerer Real Estate Holdings, LLC v. PLH Sandy Springs, LLC
740 S.E.2d 635 (Court of Appeals of Georgia, 2012)
Garrett v. Southern Health Corp. of Ellijay, Inc.
739 S.E.2d 661 (Court of Appeals of Georgia, 2013)
Artson, LLC v. Hudson
747 S.E.2d 68 (Court of Appeals of Georgia, 2013)
Primary Investments, LLC v. Wee Tender Care III, Inc.
746 S.E.2d 823 (Court of Appeals of Georgia, 2013)

Cite This Page — Counsel Stack

Bluebook (online)
Carnett's Properties, LLC v. Jowayne, LLC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/carnetts-properties-llc-v-jowayne-llc-gactapp-2015.