Carmel Lofts LLC and Keystone Construction Corp. v. Elbrecht Investments, LLC

CourtIndiana Court of Appeals
DecidedNovember 20, 2012
Docket29A05-1205-PL-266
StatusUnpublished

This text of Carmel Lofts LLC and Keystone Construction Corp. v. Elbrecht Investments, LLC (Carmel Lofts LLC and Keystone Construction Corp. v. Elbrecht Investments, LLC) is published on Counsel Stack Legal Research, covering Indiana Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Carmel Lofts LLC and Keystone Construction Corp. v. Elbrecht Investments, LLC, (Ind. Ct. App. 2012).

Opinion

Pursuant to Ind.Appellate Rule 65(D), this Memorandum Decision shall not be FILED regarded as precedent or cited before any Nov 20 2012, 8:52 am court except for the purpose of establishing the defense of res judicata, collateral CLERK of the supreme court, estoppel, or the law of the case. court of appeals and tax court

ATTORNEYS FOR APPELLANTS: ATTORNEYS FOR APPELLEE:

LAURA S. REED GENE R. LEEUW KEVIN N. THARP JOHN M. MEAD Riley Bennett & Egloff, LLP Leeuw Oberlies & Campbell, P.C. Indianapolis, Indiana Indianapolis, Indiana

IN THE COURT OF APPEALS OF INDIANA

CARMEL LOFTS LLC and ) KEYSTONE CONSTRUCTION CORP., ) ) Appellants-Plaintiffs, ) ) vs. ) No. 29A05-1205-PL-266 ) ELBRECHT INVESTMENTS, LLC, ) ) Appellee-Defendant. ) )

APPEAL FROM THE HAMILTON SUPERIOR COURT The Honorable William J. Hughes, Judge The Honorable William P. Greenaway, Magistrate Cause No. 29D03-1101-PL-546

November 20, 2012

MEMORANDUM DECISION - NOT FOR PUBLICATION

VAIDIK, Judge Case Summary

Carmel Lofts LLC and Keystone Construction Corp. appeal the trial court’s grant

of summary judgment to Elbrecht Investments, LLC. Concluding that there is no genuine

issue of material fact that Keystone did not give Elbrecht proper notice pursuant to the

parties’ subcontract to deduct a reasonable cost from Elbrecht’s payments for an alleged

default or neglect in its work and that the amount of Elbrecht’s mechanic’s lien against

Carmel Lofts is for the full value of its retainage, we affirm the trial court.

Facts and Procedural History

Carmel Lofts is the owner of a mixed-use real estate development at 110 West

Main Street in Carmel known as the Carmel Arts District Lofts & Shoppes (“the

project”). Keystone, a related entity, was the general contractor for the project, which

consisted of an underground parking garage, retail space on the first floor, and four floors

of apartments and lofts.

On June 15, 2009, Keystone and Elbrecht entered into a Standard Form of

Agreement Between Contractor and Subcontractor (“the Subcontract”), in which Elbrecht

agreed to serve as a concrete subcontractor for the project. Section 3.4 of the Subcontract

placed the following obligations on Keystone before it could deduct from sums owed to

Elbrecht:

If the Subcontractor defaults or neglects to carry out the Work in accordance with this Agreement and fails within three working days after receipt of written notice from the Contractor to commence and continue correction of such default or neglect with diligence and promptness, the Contractor may, by appropriate Modification, and without prejudice to any other remedy the Contractor may have, make good such deficiencies and may deduct the reasonable cost thereof from the payments then or thereafter

2 due the Subcontractor including any administrative or legal fees incurred by the Contractor.

Appellant’s App. p. 75.

Pursuant to the Subcontract and all change orders, the total amount due was

$2,017,835.40. Elbrecht began work under the Subcontract and submitted pay

applications to Keystone totaling $2,009,835.40. Keystone paid 90% of that amount and

held back 10%, or $200,983.54, in retainage as provided for in the Subcontract.

On December 13, 2010, Elbrecht filed a notice of intention to hold a mechanic’s

lien against Carmel Lofts’ real estate in the amount of $200,983.54 in order to secure

payment of the retainage.

Carmel Lofts filed a complaint against Elbrecht in January 2011. Carmel Lofts

alleged that because Elbrecht had not fully performed the Subcontract (Elbrecht allegedly

still needed to pour concrete for a staircase and a pool deck), Elbrecht’s mechanic’s lien

slandered Carmel Lofts’ title to the real estate. Pursuant to Indiana Code section 32-28-

3-11, which allows substitution of a surety in place of a mechanic’s lien, see Bailey v.

Holliday, 806 N.E.2d 6, 10 (Ind. Ct. App. 2004), the trial court released the mechanic’s

lien, and Carmel Lofts posted a surety bond in the amount of $225,000. Appellant’s App.

p. 59.

In February 2011, Elbrecht filed a counterclaim against Carmel Lofts and

Keystone for breach of the Subcontract, foreclosure of its mechanic’s lien (by proceeding

against the bond instead of the real estate), and unjust enrichment.

Although Elbrecht had requested a “punch list” for the project in December 2010,

it was not until May 6, 2011, that Keystone presented Elbrecht with a punch list of items

3 that needed to be corrected. Id. at 217-18. The twenty-four-item punch list was created

by the project architect, CSO Architects, and was entitled “Field Observation.” Elbrecht

worked on the punch-list items in May and June 2011. Elbrecht’s project manager, Jason

Kiser, then met with Keystone’s project director, Bob Crowder, at the project site on July

5, 2011, to discuss the punch list. Although the parties dispute what was discussed at the

meeting, it is undisputed that following the meeting, Crowder thought that “it was

pointless for Keystone to ask Elbrecht to return to fix deficiencies in [its] work, or to give

notice to Elbrecht that Keystone was hiring replacement contractors to perform

Elbrecht’s work.” Id. at 302 (supplemental affidavit of Crowder). Thereafter, Keystone

supplemented Elbrecht’s work to address some of the alleged deficiencies.

In late November 2011, CSO Architects and Crowder performed a walk through at

the project site, and CSO Architects, with Crowder’s input, issued a revised punch list.

Elbrecht was not notified of or invited to participate in this walk through.

Also in November 2011, Elbrecht moved for summary judgment. Carmel Lofts

and Keystone filed a cross-motion for summary judgment. Following a hearing, in May

2012, the trial court entered summary judgment in favor of Elbrecht. Specifically, the

trial court found:

6. Keystone presented Elbrecht with a punch list dated May 6, 2011. Elbrecht worked on the items listed on the punch list in May and June, 2011, and met with Keystone’s project director, Bob Crowder, on July 5, 2011.

7. Keystone did not give the written notice required by the Subcontract Agreement following the July 5, 2011, meeting that it intended to commence correction of any claimed default or neglect on the part of Elbrecht.

4 Id. at 7. Accordingly, the court said that Elbrecht was entitled to recover from Keystone

the sum of $200,983.54 plus prejudgment interest of $11,100.60. Finding that Elbrecht’s

notice of intention to hold a mechanic’s lien “was timely recorded and create[d] a valid,

enforceable lien against the property,” the court concluded that Elbrecht was “entitled to

judgment in rem against Carmel Lofts and foreclosure of its mechanic’s lien against the

property in the sum of $200,983.54,” plus prejudgment interest of $11,100.60, post-

judgment interest, and attorney’s fees of $23,129.30. Id. at 7, 10. The court released the

mechanic’s lien bond with Hudson Insurance Company. Id. at 10. The court denied

Carmel Lofts and Keystone’s cross-motion for summary judgment.

Carmel Lofts and Keystone obtained a stay of execution of the final judgment

pending their appeal by posting a $265,000 letter of credit. Id. at 327.

Discussion and Decision

Carmel Lofts and Keystone argue that the trial court erred in entering summary

judgment in favor of Elbrecht and asks us to remand the case for trial. In reviewing an

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bernel v. Bernel
930 N.E.2d 673 (Indiana Court of Appeals, 2010)
Hayes v. Chapman
894 N.E.2d 1047 (Indiana Court of Appeals, 2008)
Niccum v. Niccum
734 N.E.2d 637 (Indiana Court of Appeals, 2000)
Korellis Roofing, Inc. v. Stolman
645 N.E.2d 29 (Indiana Court of Appeals, 1995)
Premier Investments v. Suites of America, Inc.
644 N.E.2d 124 (Indiana Supreme Court, 1994)
Bailey v. Holliday
806 N.E.2d 6 (Indiana Court of Appeals, 2004)
Presbytery of Ohio Valley, Inc. v. OPC, Inc.
973 N.E.2d 1099 (Indiana Supreme Court, 2012)

Cite This Page — Counsel Stack

Bluebook (online)
Carmel Lofts LLC and Keystone Construction Corp. v. Elbrecht Investments, LLC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/carmel-lofts-llc-and-keystone-construction-corp-v--indctapp-2012.