Carlson v. Metropolitan Sanitary District of Greater Chicago

213 N.E.2d 129, 64 Ill. App. 2d 331, 1965 Ill. App. LEXIS 1132
CourtAppellate Court of Illinois
DecidedNovember 2, 1965
DocketGen. 50,094
StatusPublished
Cited by11 cases

This text of 213 N.E.2d 129 (Carlson v. Metropolitan Sanitary District of Greater Chicago) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Carlson v. Metropolitan Sanitary District of Greater Chicago, 213 N.E.2d 129, 64 Ill. App. 2d 331, 1965 Ill. App. LEXIS 1132 (Ill. Ct. App. 1965).

Opinion

MR. PRESIDING JUSTICE BURKE

delivered the opinion of the court.

Plaintiff appeals from a summary judgment against him in an action to recover damages for personal injuries occasioned by an alleged wilful violation of the Illinois Structural Work Act, commonly called the Scaffold Act (Ill Rev Stats, 1963, c 48, Pars 60-69). The court found that there was no just reason to delay enforcement of or appeal from the judgment. The facts presented are those well pleaded. The complaint alleges that on March 2, 1960, the defendant, the Metropolitan Sanitary District of Greater Chicago (hereinafter referred to as the defendant), was in the process of constructing a building in Skokie, Illinois; that plaintiff, Reuben Carlson, was an employee of J. L. Simmons Company, Inc. (hereinafter referred to as Simmons), a contractor engaged to perform some of the work in the construction of the building; that plaintiff was performing his work upon a scaffold constructed upon the premises by or on behalf of the defendant; that the defendant wilfully violated or wilfully failed to comply with the Structural Work Act, in that the scaffold upon which plaintiff was working was not safe and that as a proximate result thereof the scaffold fell causing plaintiff to sustain serious and permanent injuries. He asked judgment for $100,000.

Defendant’s answer admitted ownership of the premises, but denied that it owed any duty to plaintiff under the Structural Work Act, and denied all other allegations of the complaint. The defendant filed a third-party complaint against Simmons, plaintiff’s employer, for indemnity, pursuant to a written agreement between defendant and Simmons. Defendant filed a motion for summary judgment in which it alleged that Simmons, plaintiff’s employer, was an independent contractor and that defendant did not retain control nor was it “in charge” of Simmons during the course of its work. The motion was supported by affidavits of certain supervisory employees of Simmons and the affidavit of Leonard Magnusson, senior civil engineer for the defendant. The substance of these affidavits was that the defendant did not erect the scaffold in question and did not control or direct or take charge of the work done by Simmons. Plaintiff filed objections supported by the affidavit of plaintiff in which he stated that at least on one occasion he heard defendant’s employee tell a Simmons’ carpenter to scrape a form used in the work and saw such employee point to the area to be scraped. Plaintiff also filed the discovery deposition of Leonard Magnusson, an engineer employed by defendant. In his written objections filed in opposition to the motion for summary judgment, plaintiff noted that Magnusson in his deposition testified that he was “in complete charge of the supervision and the — seeing to it that these plans and specifications were followed”; that he (Magnusson had 8 employees working under him at the construction site; that all of these men were either engineers or assistant civil engineers or inspectors; that the defendant maintained a trailer at the site which was used by Magnusson and the men working under him as their site headquarters; that he met daily with Chambers, the job superintendent for Simmons, and that the purpose of these meetings was to arrange concrete pour and make general arrangements for the construction schedule.

According to his deposition, Magnusson determined when to pour concrete in certain areas on the construction project; when weather conditions were proper for pouring and the rate of pour; that 60% of all the work on the project concerned the concrete pour; that all his dealings were with Chambers (Simmons’ superintendent) ; that Chambers in turn would direct or deal with the foremen or superintendents of construction of the various subcontractors on the job; that the names of all contractors had to first be submitted to defendant’s engineering department for approval and that it was necessary for such approval to be given in writing by defendant’s chief engineer before Simmons could employ any subcontractors; that the inspection of the work was the function of the defendant’s engineers and inspectors; that during the progress of the work, Simmons submitted to the defendant, force accounts, which showed the number of men employed on the job at different times and the work they performed. In addition to the field inspections, the defendant made prefield inspections of most of the material used in the course of construction. This was done by the defendant at the manufacturer’s premises. Shop drawings had to be submitted by Simmons to the defendant’s engineering department for approval .as well as plans which specified the manner of installing or applying the material or equipment involved in the construction project. Mr. Magnusson further testified that the defendant’s engineers or inspectors examined all forms used for the pour of concrete; that he gave Chambers directions about the cleaning of the forms and that the rate of pour of the concrete was given to Simmons by defendant engineering department and that the defendant’s inspectors checked to see that the recommended rate was followed. In addition to the affidavit and deposition of Magnusson, plaintiff filed as an exhibit to Magnusson’s deposition, the contract between defendant and Simmons, which consisted of 102 pages. It provided, among other things, that the work shall be executed under supervision of the chief engineer of defendant and his properly authorized agents; that the engineer, shall in all cases, decide all questions of an engineering character which may arise relative to the execution of the work; that the contractor had to submit layouts and schedules of his proposed method of conducting the work to the engineer for approval; that the engineer had the right to reject any inadequate or unsafe procedural method (temporary) structures or equipment and that the engineer could disapprove and reject any of the same which to him seemed “unsafe for the work, . . . for the public or for any workmen, engineers and inspectors employed thereon.” The contract further provided that before commencing work the contractor had to submit his proposed order of procedure to the engineer for approval; and further provided that the contractor was at all times to have present at the site a competent foreman, superintendent or other representative with authority to act for the contractor and execute the orders from the engineer; and who would see to it that the work was executed in accordance with the specifications and the orders of the engineer. It further provided that the contractor shall discharge, at the request of the engineer, any incompetent or unfaithful men in his employ.

The defendant points out that the contract is very detailed; that some of the provisions reserve certain rights to the defendant, as the right to inspect and accept or condemn all work, to require the contractor to discharge incompetent or unfaithful employees, etc.; and that the contractor place the responsibility of performing the contract, for taking safety precautions and for determining the manner and method of performing the work upon the contractor, but reserves the right of approval of such performances unto the defendant. The defendant concedes for the purposes of this appeal that its “right to control” can be found to exist in the contract but that actual control of the work is delegated to the contractor and was not, in fact, exercised by the defendant.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cutuk v. Hayes/Gallardo, Inc.
586 N.E.2d 357 (Appellate Court of Illinois, 1991)
Manisco v. Marseilles Fire Protection District
477 N.E.2d 534 (Appellate Court of Illinois, 1985)
Roedner v. Central Illinois Public Service Co.
452 N.E.2d 842 (Appellate Court of Illinois, 1983)
Fruzyna v. Walter C. Carlson Associates, Inc.
398 N.E.2d 60 (Appellate Court of Illinois, 1979)
Crothers v. La Salle Institute
370 N.E.2d 213 (Illinois Supreme Court, 1977)
Norton v. Wilbur Waggoner Equipment Rental & Excavating Co.
367 N.E.2d 516 (Appellate Court of Illinois, 1977)
Beebe v. Commonwealth Edison Co.
358 N.E.2d 1343 (Appellate Court of Illinois, 1977)
Voss v. Kingdon and Naven, Inc.
291 N.E.2d 235 (Appellate Court of Illinois, 1972)
Krause v. Caterpillar Tractor Co.
268 N.E.2d 904 (Appellate Court of Illinois, 1971)
Moroni v. Gulf, Mobile & Ohio Railroad
230 N.E.2d 55 (Appellate Court of Illinois, 1967)

Cite This Page — Counsel Stack

Bluebook (online)
213 N.E.2d 129, 64 Ill. App. 2d 331, 1965 Ill. App. LEXIS 1132, Counsel Stack Legal Research, https://law.counselstack.com/opinion/carlson-v-metropolitan-sanitary-district-of-greater-chicago-illappct-1965.