Carlson v. Doran

90 N.W.2d 323, 252 Minn. 449, 1958 Minn. LEXIS 631
CourtSupreme Court of Minnesota
DecidedMay 23, 1958
Docket37,390
StatusPublished
Cited by11 cases

This text of 90 N.W.2d 323 (Carlson v. Doran) is published on Counsel Stack Legal Research, covering Supreme Court of Minnesota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Carlson v. Doran, 90 N.W.2d 323, 252 Minn. 449, 1958 Minn. LEXIS 631 (Mich. 1958).

Opinion

Frank T. Gallagher, Justice.

Appeal from a judgment of the district court.

This case was commenced by plaintiffs, Albert E. Carlson and Harold G. Hawkinson, for specific performance of a contract for deed which they entered into as vendees with the defendants, Allen J. Doran and Mary Doran.

Prior to the events giving rise to these proceedings, the defendants owned certain property in Grand Rapids, Minnesota, which was platted as “Doran’s Addition to Grand Rapids.” On June 10, 1952, plaintiffs and defendants entered into a contract in connection with this property. By the terms of the contract the plaintiffs were to pay $27,500, plus interest and taxes and assessments on the property. The defendants were to convey by warranty deed certain tracts as the same were paid for at the rate of $6 per front foot for property not fronting on Pokegama Avenue and $20 per front foot for property fronting on Pokegama Avenue. At this point it was agreed that all of the lots should be purchased before December 31, 1954. The contract further provided that the parties should work jointly to revamp the plat of Doran’s Addition. Paragraph 5 of the contract provided:

“It is contemplated that there will be sewer and water mains con *451 structed so as to accommodate all of the lots of the plat of Doran’s Addition to Grand Rapids, Minnesota, except lots One (1) and Two (2), Twenty-three (23) and Twenty four (24) of Block One (1), and that all parties hereto shall work jointly to secure the construction of sewer lines and water mains so as to servicé all of the plat of Doran’s Addition, including those which have been contracted for sale pursuant to the terms of this contract and also those described as lots Seventeen (17) to Thirty-two (32) inclusive of Block Six (6) and Lots Seventeen (17) to Thirty-two (32) of Block Three (3), which are being retained by the parties of the first part, all in accordance with the overall plan as discussed by the parties hereto. It is being specifically understood and agreed that the sewer as the same shall be constructed in or on Ninth Street Southeast, and connecting with present manhole in intersection of 7th Street, S. E. and 2nd Avenue S. E. which shall service Blocks Three (3) and Six (6) of said Doran’s Addition shall be as deep as construction regulations permit or less as will prove necessary to provide sewer service availablility for property fronting on the West side of Pokegama Avenue South opposite Blocks Three (3) and Six (6) of Doran’s Addition to Grand Rapids, Minnesota.”

Thereafter the parties did secure a vacation of Doran’s Addition, and two additions were made from the old plat. The new additions were known as New Doran Addition and Clover First Addition. New Doran Addition was changed to business property on June 1, 1953. Due to the replatting, additional lots were made available to plaintiffs. Up until December 31, 1954, the plaintiffs had paid a total of $20,540 and had secured deeds to 55 lots. On this basis the plaintiffs had actually paid less for the lots received than $6 per front foot and $20 per front foot as provided in the contract.

The plaintiffs and defendants had also entered into a contract with the village of Grand Rapids and its public utilities commission under which plaintiffs and defendants agreed to pay the costs of sewers and water mains for the property contained in the original plat of Doran’s Addition. In return the village agreed to accept the property. On December 31, 1954, the plaintiffs had not caused to be constructed sewers to service lots 3 through 16, block 2, of Doran’s Addition or lots 25 *452 through 33, block 7, Clover First Addition, or the property on the west side of Pokegama Avenue facing New Doran Addition. During the period prior to December 31, 1954, the plaintiffs did cause to be constructed sewer lines within the property in question.

On December 31, 1954, the plaintiffs tendered the amount of principal due under the contract. The defendants refused this tender and on January 5, 1955, notice of cancellation of contract for deed was served on plaintiffs. Following this and within 30 days the plaintiffs commenced this action for specific performance and filed a lis pendens with the registrar of titles of Itasca County. It appeared that on December 31, 1954, there were 21 lots left to be conveyed to the plaintiff under the contract. At that time there was $6,960 due on the contract.

The case was submitted to the district court on a stipulation of facts. This stipulation, among other things, provided that the testimony of the parties contained in their affidavits would have the same force and effect as if they had been called to testify and the right to cross-examination was waived by all the parties and their attorneys. It was also provided that the affidavits and depositions of P. C. Warner, village engineer, and a certain exhibit would have the same force and effect as if he had been called to testify. This same provision was made with respect to affidavits of one Henry B. Gabrielson and with respect to an affidavit and report of Donald Jackson, both men being registered civil engineers.

The findings of fact in this case were lengthy and complicated. The plaintiffs have assigned most of them as error on the ground that they are not justified by the evidence. They also assigned as error that the conclusions of law are not supported by the evidence and are contrary to law. The only issues in this case, therefore, are whether the findings assigned as error are justified by the evidence and, if so, whether they support the conclusions of law.

We will discuss only those issues necessary to a determination of this case. These fall into four categories: (1) The findings concerning whether paragraph 5 of the contract above referred to was a dependent covenant; (2) findings concerning whether the plaintiff had breached the contract; (3) findings concerning whether the plaintiff had substantially performed under the contract; and (4) findings concerning whether the defendant waived his right to demand performance under *453 paragraph 5.

The district court found that the defendants at all times insisted that sewer lines as they would be constructed in Old Doran Addition to Grand Rapids should be of sufficient depth to service all that addition and to provide sewer service for property owned by defendants on the west side of Pokegama Avenue; that before executing the contract for deed the defendants insisted on inserting in paragraph 5 the words “and connecting with present manhole in intersection of 7th Street, S. E. and 2nd Avenue S. E.”; and that paragraph 5, and particularly the last sentence thereof, was a material part of the consideration flowing from plaintiffs to defendants at the time said contract for deed was executed. The court then specifically found that paragraph 5 was intended by the parties to be a dependent covenant and that the purchase price had been lowered because of its insertion in the contract due to the fact that the cost of sewers would be appreciably higher under this provision.

Plaintiffs cite Clark v. Clark, 164 Minn. 201, 207, 204 N. W. 936, 938, to the effect that:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Leiendecker v. Asian Women United of Minnesota
895 N.W.2d 623 (Supreme Court of Minnesota, 2017)
Frandsen v. Ford Motor Co.
801 N.W.2d 177 (Supreme Court of Minnesota, 2011)
City of Minneapolis v. Minneapolis Police Relief Ass'n
800 N.W.2d 165 (Court of Appeals of Minnesota, 2011)
Valspar Refinish, Inc. v. Gaylord's, Inc.
764 N.W.2d 359 (Supreme Court of Minnesota, 2009)
In Re the Civil Commitment of Giem
742 N.W.2d 422 (Supreme Court of Minnesota, 2007)
Hedged Investment Partners, L.P. v. Norwest Bank Minnesota, N.A.
578 N.W.2d 765 (Court of Appeals of Minnesota, 1998)
Stephenson v. Martin
259 N.W.2d 467 (Supreme Court of Minnesota, 1977)
Target Stores, Inc. v. Twin Plaza Co.
153 N.W.2d 832 (Supreme Court of Minnesota, 1967)
Albrecht v. Sell
110 N.W.2d 895 (Supreme Court of Minnesota, 1961)

Cite This Page — Counsel Stack

Bluebook (online)
90 N.W.2d 323, 252 Minn. 449, 1958 Minn. LEXIS 631, Counsel Stack Legal Research, https://law.counselstack.com/opinion/carlson-v-doran-minn-1958.