Carlos Armstrong e Hijos Sucrs., Inc. v. Díaz Santini

95 P.R. 800
CourtSupreme Court of Puerto Rico
DecidedMarch 11, 1968
DocketNo. R-64-225
StatusPublished

This text of 95 P.R. 800 (Carlos Armstrong e Hijos Sucrs., Inc. v. Díaz Santini) is published on Counsel Stack Legal Research, covering Supreme Court of Puerto Rico primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Carlos Armstrong e Hijos Sucrs., Inc. v. Díaz Santini, 95 P.R. 800 (prsupreme 1968).

Opinion

Mr. Justice Rigau

delivered the opinion of the .Court.

The question involved in this case is whether or not it is proper to apply § 1489 of the Civil Code, 31 L.P.R.A. § 4130, which reads as follows:

‘■‘Those who furnish their labor and materials in a work agreed, upon for a lump sum by a contractor have no action against the owner, .except- for the amount the latter may owe the former when the action is brought.”

Although the case should be decided on the basis of■ the contract executed between the Puerto Rico Teachers’ Association, hereinafter referred to as the Association, and contractor Juan Diaz Santini, on March-2, i960, -it is convenient, for a- better understanding of the situation, to make a summary: of the facts- from the beginning. "

In January 1958 the Association bought -some land- in Ponce-' to construct a housing development: The Planning Board -approved the project and on November 24 of said year- the' Association and Diaz Santini executed a contract for the subdivision of the land into lots, streets,' etc. Thé development comprised the preparation of 119- lots. The price of the work, -after undergoing certain adjustments, was agreed' at $195,262.84. A term of 365 days 'was fixed for the completion of the said works — which term expired November 23, -1959 — and it was agreed that in the event- the-work was not completed within said period the contractor would pay to the Association-a. penalty of $50 for each day of delay. SimuL [802]*802taneously with the development of the land the contractor started the construction of houses by individual contracts with the respective teachers. The contractor did not complete the development of the land within the period stipulated and in March 1960 he abandoned said work. The development of the land was completed by the Association in June 1961.

In the course of the events recited above, on March 2, 1960, the Association executed a new contract with Diaz Santini, in San Juan, before Mr. Luis Miranda Correa, for the construction, by Diaz Santini, of 39 houses in the aforementioned housing project. After certain modifications the contract was increased to 41 houses and the price of the work was $306,975. Among others, this contract contains the following clauses. The works would be completed on or before September 1, 1960. The contractor bound himself “to indemnify” the Association with a sum equal to 8% of the value of each house not finished by September 1, 1960, or with a larger sum, if such were the case, for the “additional cost” of the dwellings, in the event it were necessary to obtain a new financing contract. It was also agreed that the Association would retain a sum equal to 5% of each payment to the contractor for work performed, to secure the correction of any construction defects, which sum would be retained for a period of 3 months, as of the date that the Association received each house as finished.. The contractor also bound himself to answer for any other sum, in excess of that 5%, on any date before or after that agreed upon in the contract.

The contractor did not complete either, the works object of this second contract and abandoned them in October 1960. By subsequent agreements the contractor resumed the construction of the houses and finished them later.

Plaintiff, a firm engaged in the sale of construction materials, supplied to Diaz Santini, between May 1 and August 30, 1960, materials of the kind which, were utilized in [803]*803the construction of the aforementioned houses. When extrajudicial attempts to collect failed, plaintiff filed a complaint on September 14, 1960, against contractor Diaz Santini and the Association to collect the sum of $26,982.76 which the contractor owed to plaintiff for material sold to the latter. Plaintiff alleged the existence of the aforementioned contract of March 2, 1960, between the Association and the contractor by virtue of which the construction of the houses was agreed upon; it alleged having supplied the aforementioned construction material; it alleged the existence of the debt; and it alleged that the Association owed to the contractor a sum of money in excess of the debt that the contractor had with plaintiff. Relying on the afore-copied § 1489 of the Civil Code plaintiff requested that the court order defendants to pay to them the aforementioned sum, interest, costs, and attorney’s fees.

Defendant Diaz Santini never answered the complaint and default was timely entered against him. Defendant Teachers’ Association denied “each and every one” of the facts alleged in the complaint but this notwithstanding they were found to be true. We have before us as Exhibit I, plaintiff’s and defendant’s, a photocopy of the contract executed March 2, 1960, between the Association and contractor Diaz Santini. However, there is other documentary and oral evidence. The Superior Court sustained the complaint. It sustained the complaint in full as to Diaz Santini and as to the Association it was limited to the sum of $11,106.50 with costs, without attorney’s fees. Plaintiff did not appeal, but codefendant Teachers’ Association did.

Appellant assigns the following errors:

1. “The Superior Court erred in concluding that the Teachers’ Association made an undue payment to the contractor on August 11, 1960, and that because it is a subsequent modification of the terms of the contract the payment does not prejudice materialman on previous dates.”
[804]*804•• 2. “The court erred in failing to conclude that the Association owed nothing to the contractor.”

Let us see now the nature of the legal provision invoked herein — § 1489 of the Civil Code.

Said section provides, in essence, that those who furnish' their labor and materials in a work ágreed upon for a lump sum by a contractor have no action against the owner of-the work except for the ámount that the latter may owe to the former when the action is brought.

As may be seen this provision, is an exception' to the principles concerning contracts in our law, since the general rule is that contracts shall only be valid between the parties who execute them and their heirs. Civil Code, § 1209; 31 L.P.R.A. § '3374. However, notwithstanding said general rule the aforementioned § 1489 brings, in a certain manner, a third party to the contract, that is, a party which did not appear in the original contract executed between the owner áhd the contractor — those who furnished' labor or material for- the work. Pursuant to the general principles concerning contracts, ánd in the absence of said § 1489 or other special provisions1 the workers and materialmen could only institute action for subrogation against the owner of the work, which on the assumption of § 1064" of the Civil Code, would accrue to them as the contractor’s creditors. But, on the other hánd, § 1489 grants them direct action against the owner or principal.' Of course; in order that the owner of the work shall hot be bound to pay twice, that is, to the contractor and also to the workers and materialmen, § 1489 specifies that the action may be had only for the amouht the owner may owe to the contractor when the action is brought. On this particular you may see 2-III Puig Peña, Compendio de Derecho Civil Español 843 (1966); X Manresa, Comentarios al Código Civil [805]*805Español 934 (5th ed. 1950); IV Castán, Derecho Civil Español, Común y Foral 462 (9th ed. 1961); 24-2 Scaevola,

Free access — add to your briefcase to read the full text and ask questions with AI

Cite This Page — Counsel Stack

Bluebook (online)
95 P.R. 800, Counsel Stack Legal Research, https://law.counselstack.com/opinion/carlos-armstrong-e-hijos-sucrs-inc-v-diaz-santini-prsupreme-1968.