Carlisle v. T & R Excavating, Inc.

704 N.E.2d 39, 123 Ohio App. 3d 277, 1997 Ohio App. LEXIS 4629
CourtOhio Court of Appeals
DecidedOctober 15, 1997
DocketNo. 2616-M.
StatusPublished
Cited by66 cases

This text of 704 N.E.2d 39 (Carlisle v. T & R Excavating, Inc.) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Carlisle v. T & R Excavating, Inc., 704 N.E.2d 39, 123 Ohio App. 3d 277, 1997 Ohio App. LEXIS 4629 (Ohio Ct. App. 1997).

Opinion

Dickinson, Presiding Judge.

Defendant T & R Excavating Inc. has appealed from a judgment of the Medina County Common Pleas Court that awarded $35,790.75 in damages for breach of contract to plaintiffs Janis Carlisle, Wishing Well Preschool Inc., and Janis Carlisle, trustee, The Enrichment Center of Wishing Well, Inc. Defendant has argued that the trial court incorrectly found that there was a contract between the parties because their agreement lacked sufficient consideration and definiteness. This court reverses the judgment of the trial court because there was no consideration for the agreement between the parties and, therefore, no contract existed.

I

Defendant T & R Excavating, Inc. is solely owned and operated by Thomas Carlisle. Plaintiff Janis Carlisle is the owner and director of Wishing Well, Inc. *281 and trustee of The Enrichment Center of Wishing Well, Inc., both of which were also plaintiffs in this action.

Ms. Carlisle and Mr. Carlisle married in 1988. According to Ms. Carlisle’s trial testimony, shortly after they were married, she began doing all of the bookkeeping for T & R, including organizing and modernizing its bookkeeping system. Mr. Carlisle allegedly offered to pay her for her work, but she refused. He then allegedly stated to her that he would, instead, “do [her] work for [her] on [her] building.” No testimony or other evidence was offered regarding when he made this offer to pay her or when he stated his intention to do work on her building.

During 1992, Ms. Carlisle decided to build a preschool and kindergarten facility. Mr. Carlisle helped her find a location for the preschool, and she purchased the land they selected. Following this, he helped her choose a general contractor for the construction of the preschool.

On September 25, 1992, T & R presented a “Proposal” to Ms. Carlisle in which it proposed the following:

“We hereby propose to do all of the excavation and site work at the above new Location. The total amount budgeted for this portion of the new building is $69,800.00. All labor, equipment costs, overhead and profit, necessary for the completion of this project, totalling $40,000.00 will be provided at no cost to Wishing Well Preschool, Inc. The $29,800.00 allotted for materials will be billed to Wishing Well Preschool, Inc. at T & R Excavating’s cost.”

On that same date, Ms. Carlisle signed an “Acceptance of Proposal,” which was printed at the bottom of the “Proposal”:

“The above prices, specifications and conditions are satisfactory and are hereby accepted. You are authorized to do the work as specified. Payment will be made as outlined above.”

During December 1992, Mr. Carlisle and Ms. Carlisle, in anticipation of a possible divorce, prepared a document in which they made provision for the division of certain property and agreed that neither would be responsible for supporting the other. Also included in that document was a paragraph regarding Ms. Carlisle’s secretarial work and T & R’s excavating work:

“In repayment to Jan for her secretarial services and computer programming to T & R Excavating, Inc., Tom agrees to do all the excavating and site work for The Enrichment Center in a timely manner, as set forth in his proposal dated September, 1992. In this proposal, Wishing Well Preschool, Inc., agrees to pay Tom for the materials used at his cost.”

On February 1, 1993, the general contractor prepared and presented to Mr. Carlisle a standardized American Institute of Architects document, signed by Ms. *282 Carlisle, entitled “Abbreviated Form of Agreement Between Owner and Contractor.” Some information specific to the preschool project was typed into the appropriate blank areas of the document, and the last several pages of the agreement consisted of printed contract language. The typed-in information included a description of the site work to be done, an estimate of $29,325.00 for materials, a plan for how payment was to be made, a start date of February 1, 1993, and a completion date of June 25, 1993. Also typed in were the following statements:

“This contract is for material only. There is no charge for labor and equipment.
“The contract sum will be adjusted at the completion of this work to reflect the actual cost of materials installed.”

Mr. Carlisle never signed the document.

Sometime during early 1993, T & R began performing excavation and site work for the preschool. According to Mr. Carlisle’s testimony at trial, Ms. Carlisle was no longer providing any bookkeeping or secretarial services to T & R after January 1993. They separated during March 1993, and T & R continued working on the project until it abandoned it in late May or early June 1993. By that time, Wishing Well Inc. had paid approximately $35,000 for materials used by T & R for excavation and site work. Ms. Carlisle hired other workers to finish the excavation and site work. The preschool opened for business on August 28, 1993, one week later than originally planned. Ms. Carlisle, individually and as trustee of The Enrichment Center, and Wishing Well Preschool sued T & R for breach of contract. They requested damages equal to the amount it cost to have others finish the excavation and site work, as well as the amount lost due to delays allegedly attributable to T & R’s failure to work during certain periods prior to its final abandonment of the job. The trial court found that there was a contract for the excavation and site work and awarded plaintiffs $35,790.75 in damages for the cost of hiring others to finish that work after T & R left the project. The trial court, however, did not award any damages for the cost of delays. It found that plaintiffs had failed to prove that T & R was responsible for losses caused by delays, because there had been significant delays due to late material deliveries which were not its fault. T & R timely appealed to this court.

II

T & R’s sole assignment of error is that the trial court incorrectly found that there was a contract between the parties, because their agreement lacked sufficient consideration and definiteness. It has asserted that its offer to do the excavation and site work for the preschool was in the nature of a gift or a favor, *283 and was not supported by any legally sufficient consideration. In addition, it has asserted that the scope of the work it agreed to do was so uncertain that there could have been no meeting of the minds necessary to the formation of a contract.

A contract consists of an offer, an acceptance, and consideration. See Tersigni v. Gen. Tire, Inc. (1993), 91 Ohio App.3d 757, 760, 633 N.E.2d 1140, 1141-1142. Without consideration, there can be no contract. Brads v. First Baptist Church of Germantown, Ohio (1993), 89 Ohio App.3d 328, 336, 624 N.E.2d 737, 743.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

State v. Dixon
2025 Ohio 326 (Ohio Court of Appeals, 2025)
Cameron v. Mark W. Liberty Midstream & Resources, L.L.C.
2024 Ohio 5279 (Ohio Court of Appeals, 2024)
Tilton v. Geronimo
2024 Ohio 5211 (Ohio Court of Appeals, 2024)
State v. Moore
2024 Ohio 1354 (Ohio Court of Appeals, 2024)
Hal Fab, L.L.C. v. Jordan
2023 Ohio 4535 (Ohio Court of Appeals, 2023)
Fixel v. LSMJ1, LLC
N.D. Ohio, 2023
Sal's Heating & Cooling, Inc. v. Harbour View Assocs., Ltd.
2023 Ohio 3632 (Ohio Court of Appeals, 2023)
Sowry v. Todd
2023 Ohio 1162 (Ohio Court of Appeals, 2023)
Parma VTA LLC v. Parma GE 7400, LLC
Superior Court of Delaware, 2022
Evans v. Evans
2022 Ohio 2167 (Ohio Court of Appeals, 2022)
Thiel's Wheels, Inc. v. State Route 30, Ltd.
2022 Ohio 2093 (Ohio Court of Appeals, 2022)
Digitalight Sys., Inc. v. Cleveland Clinic Found.
2022 Ohio 1400 (Ohio Court of Appeals, 2022)
Adams v. Morningstar
2022 Ohio 918 (Ohio Court of Appeals, 2022)
Widok v. Estate of Wolf
2020 Ohio 5178 (Ohio Court of Appeals, 2020)
Forbes v. Showmann, Inc.
2019 Ohio 2362 (Ohio Court of Appeals, 2019)
Cincinnati Reds, L.L.C. v. Testa (Slip Opinion)
2018 Ohio 4669 (Ohio Supreme Court, 2018)
Bavelis v. Doukas (In re Bavelis)
571 B.R. 278 (S.D. Ohio, 2017)
State v. Blake
2015 Ohio 4762 (Ohio Court of Appeals, 2015)
Raymond G. Schreiber Revocable Trust v. Estate of Knievel
984 F. Supp. 2d 1099 (D. Nevada, 2013)

Cite This Page — Counsel Stack

Bluebook (online)
704 N.E.2d 39, 123 Ohio App. 3d 277, 1997 Ohio App. LEXIS 4629, Counsel Stack Legal Research, https://law.counselstack.com/opinion/carlisle-v-t-r-excavating-inc-ohioctapp-1997.