Carl Heck Engineers, Inc. v. Haselden & Associates, Inc.

316 So. 2d 890
CourtLouisiana Court of Appeal
DecidedOctober 24, 1975
Docket10365
StatusPublished
Cited by6 cases

This text of 316 So. 2d 890 (Carl Heck Engineers, Inc. v. Haselden & Associates, Inc.) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Carl Heck Engineers, Inc. v. Haselden & Associates, Inc., 316 So. 2d 890 (La. Ct. App. 1975).

Opinion

316 So.2d 890 (1975)

CARL HECK ENGINEERS, INC.
v.
HASELDEN & ASSOCIATES, INC., now Warren Engineers and Construction Co., Inc.

No. 10365.

Court of Appeal of Louisiana, First Circuit.

July 8, 1975.
Rehearing Denied August 26, 1975.
Writ Refused October 24, 1975.

*891 Stanwood R. Duval, Jr., Houma, for appellant.

Donald L. Peltier, Thibodaux, for appellee.

Before LANDRY, BLANCHE and YELVERTON, JJ.

LANDRY, Judge.

Plaintiff, (Engineer), appeals from a judgment dismissing Engineer's claim against defendant (Contractor) for liquidated damages as provided for Engineer's benefit by virtue of a stipulation pour autrui contained in a subdivision development contract between Contractor and Elmo Authement, (Owner). The trial court rejected Engineer's demands upon finding that the stipulation pour autrui relied upon by Engineer is penal in nature and, as such, invalid and unenforceable as a matter of law. We reverse and remand for trial on the merits.

On November 28, 1969, Owner and Contractor entered into a detailed written contract in which Contractor undertook to construct for Owner a sanitary sewer system for a subdivision known as Addendum No. 1 to Acadia Woods. The agreement (which refers to Contractor as Party of the First Part) expressly designates Engineer as the Engineer in charge of the project. It also provides that the work shall commence within 10 days of a written work order issued by Owner and be completed within 100 consecutive calendar days of commencement. Time is expressly stated to be of the essence of the agreement. Owner reserves the right to make changes and modifications mutually agreed upon with Contractor in writing and approved by Engineer. Should agreed changes increase or decrease the amount of the work or time required, the written agreement for the change is declared to be the evidence of the change. Any adjustment desired by Contractor in connection with a change must be asserted within 10 days from date the change is ordered unless the time is extended by Owner. The contract specifications admonish Contractor to examine the construction site carefully and places on Contractor responsibility for conditions found at the work site. Engineer is given full charge of the work, his opinion being made final as to all disputes concerning the amount and character of work performed. Engineer is further given authority to make changes which are adjustable on the basis of additional or decreased work involved.

The contract and attached "Instructions to Bidders" pertinently provide:

"6. It is mutually agreed between the parties hereto that time is the essence of this contract, and in event the construction of the work is not completed within the time specified, it is agreed that from the compensation otherwise to be paid to the Contractor, the second party may retain the sum of Fifty Dollars ($50.00) per day for each day thereafter, Sundays and holidays included, that the work remains incompleted, which sum shall represent the actual damage which the Owner will have sustained per day by failure of the Contractor to complete the work within the time stipulated; and this sum is not a penalty, being the stipulated damage the second party will have sustained in event of such default by the first party. The Contractor shall also pay the Engineer the sum of Fifty Dollars ($50.00) per day as hereinbefore stipulated, for actual additional expense incurred by reason of such delay."

*892 "14. CHANGES IN PLANS AND SPECIFICATIONS:

The Owner reserves the right to make such changes or modifications as it deems advisable * * *. Changes made after the execution of the Contract will be paid for at a price mutually agreed upon in writing by the Owner and the Contractor and approved by the Engineers prior to the performance of said work. * * * if the changes made cause an increase or decrease in the amount due under the Contract, or in the time required for its completion, the aforementioned written agreement shall be evidence of such changes. Any claim for adjustment under this paragraph must be asserted within ten (10) days from the date such change is ordered, unless the Owner shall extend such time, and nothing provided in this paragraph shall excuse the Contractor from proceeding with the prosecution of the work so changed. * * *"

"19. DETERMINATION AND EXTENSION OF CONTRACT TIME:

The time within which the work is to be completed is of the essence of the contract.
The Contract Time shall consist of the calendar days elapsed during the period beginning ten (10) days after the date of the official written order of the Owner to begin work and ending with the Engineer's acceptance of the Work.
At any time before the payment of the Final Estimate, the Contractor may submit to the Engineer an application for the extension of the Contract time. In support of the application the Contractor shall allege delay in the performance of the work only by either or both of the following causes:

(a) An Act of State.

(b) `Fortuitous Events' or `events beyond the control of' as defined in Louisiana Jurisprudence.
In the event of the Contractor's failure to complete the work within the time specified, except as provided above, he shall pay the Owner for liquidated damages an amount, which due to the difficulty of estimating such damages with exactness is hereby affixed, determined and agreed upon, of Fifty ($50.00) Dollars per calendar day for each and every day he is in default of completion. The money will be deducted by the Owner from monies that are due or will be due the Contractor under the Contract terms.
In addition to the above, the Owner will deduct from the monies due or to become due the Contractor under the Contract terms and will pay the Engineers by reason of this delay in completion of the work a sum which in view of the difficulty in estimating with exactness, is hereby affixed, determined and agreed to be Fifty ($50.00) Dollars per calendar day.
If they so chose, either the Owner or the Engineers may agree to waive its or their rights under the above mentioned conditions, but it is understood and agreed upon by the Contractor that this action on the part of either the Owner or the Engineers will not cancel the rights of the other to impose and collect damages in accordance with the above schedule.

"20. DUTIES OF THE CONTRACTOR:

The Contractor shall give the work his constant attention to facilitate the progress thereof and shall cooperate with the Engineer in every way possible.
* * * * * *
He (Contractor) shall bear all losses resulting to him on account of the *893 amount or character of the work, or on account of the nature of the land in or on which the work is done being different from what was estimated or expected, or on account of the weather, climate, elements or other causes."
* * * * * *

"28. DEFAULT OF CONTRACT:

* * * * * *
Permitting the Contractor to continue the Work after the time for its completion has expired or after the date for which the contract time may have been extended shall in no way be considered as a waiver of the Owner's rights under the terms of this Contract.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Brooks v. Shipp
481 So. 2d 655 (Louisiana Court of Appeal, 1985)
Jackson v. Tenneco Oil Co.
623 F. Supp. 1452 (E.D. Louisiana, 1985)
Reed v. Allstate Insurance Co.
376 So. 2d 1303 (Louisiana Court of Appeal, 1979)
Berry v. Berry
371 So. 2d 1346 (Louisiana Court of Appeal, 1979)
Carl Heck Engineering, Inc. v. Haselden & Associates, Inc.
320 So. 2d 912 (Supreme Court of Louisiana, 1975)

Cite This Page — Counsel Stack

Bluebook (online)
316 So. 2d 890, Counsel Stack Legal Research, https://law.counselstack.com/opinion/carl-heck-engineers-inc-v-haselden-associates-inc-lactapp-1975.