Carl Construction Company v. Miller

29 S.W.2d 545, 234 Ky. 794, 1930 Ky. LEXIS 273
CourtCourt of Appeals of Kentucky (pre-1976)
DecidedJune 17, 1930
StatusPublished
Cited by1 cases

This text of 29 S.W.2d 545 (Carl Construction Company v. Miller) is published on Counsel Stack Legal Research, covering Court of Appeals of Kentucky (pre-1976) primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Carl Construction Company v. Miller, 29 S.W.2d 545, 234 Ky. 794, 1930 Ky. LEXIS 273 (Ky. 1930).

Opinion

Opinion of the Court by

Judge Logan

Reversing.

Appellees brought suit against appellant in the Kenton circuit court seeking to recover $1,690, that is, $1,489, which they claimed was due for work performed under a contract, and $201 damages for breach of the contract. The basis of the recovery, as alleged in the petition, was that in July, 1926, they entered into a verbal contract with appellant by the terms of which they were to do all the excavating and back filling necessary in the erection and construction of the junior high school building adjoining the Holmesdale High School in the city of Covington, for which work they were to receive 50 cents per cubic yard for all material removed and back filled; that the excavating amounted to 9,100 cubic yards and the back filling 500 cubic yards; that they began the work in accordance with the contract, and that they had been paid for the work done $2,641; that on or about the latter part of October, 1926, the appellant wrongfully and in violation of the contract placed a steam shovel and workmen on said undertaking, and began excavating, and that about the first of November, 1926, appellees received a written order from appellant to remove their equipment and cease work; that at the time they were directed to cease work they had excavated 8,260 cubic yards, and had been paid the sum of $2,641, leaving a balance due them of $1,489; that, if they had been allowed to complete the work, they would have been entitled to receive 50 cents per cubic yard for 1,340 yards; and that their profit would have been $201 on that yardage.

Appellant filed an answer and counterclaim, denying some of the allegations in the petition and admitting others. It admitted the making of a contract, but denied that there were only 9,100 cubic yards of excavating, or 500 cubic yards of back filling to be done; it admitted the payment of $2,641 to appellees, but denied that, at any time, it wrongfully, or in violation of its contract, placed the steam shovel and workmen, or either, on the job and began the excavating work, but it admits that about November 1, 1926, it notified appellees to remove their *796 equipment and to cease work.' It denied that it was indebted to appellees in the sum of $1,489, or any sum, by reason of the work which was done by them, "or that they had been damaged $201, or any sum, by the notice to them to cease work. By way of counterclaim it was alleged by appellant that appellees failed to do the work in a proper and expeditious manner, and that they abandoned the work, resulting in the forced necessity of its notifying them to remove their, equipment so that it might complete the work; that it .did complete the work, and. to do so it was necessary for it to engage a steam shovel at a cost of $933.20, a reasonable and proper cost, and that it was necessary for it to employ men at a cost of $4,074.76, and that the work was still uncompleted. The'prayer of'the appellant was for a dismissal of the petition and'that it recover $5,007.96, subject'to a credit of $1,489, the amount claimed by' appellees. A reply was filed making an issue on the' counterclaim'. An amended answer and cduilterclaim was filed which served no purpose, in the main, other than to. make the'original counterclaim more-specific, and to allege'moré definitely the work which'-appellant was' compelled to do,- and the necessity for 'an early completion -of the work after the contract with appellees was made in'July. ' ' ' ' ' - •

Appellant alleged, in .its. .amended counterclaim, 'that appellees had excavated no more than, 5,500 cubic .yards, for which they viere entitled to receive $2,750,. and they had actually been', paid $2,641;'consequently, the credit to which appellees weie entitled pn'.'the amount expended by appellant' after it completed’ the work was .not what was admitted in the prayer of' the; counterclaim. ' The counterclaim, after making deductions' and'adjustments, alleged that there was due appellant" á net sum of $2,-450.94, and that notliing-was due appellees. There was a motion to strike certain parts of the amended counterclaim', but there is nothing to'indicate-any ruling on that motion!,' and'it"appears that no-reply'was filed to the amended answer and counterclaim.

A trial before a jury resulted in .a'judgment in faybr of appellees for $579,50. A motion.for. a. nev^ trial, was based upon' errors concerning ' instructions-,, 'but. ,an amended motion was filed relying oh other grounds',’ one of which was newly discovered evidence, and another that the verdict was against the weight of the evidence. The motion and supplemental motion for a new trial were overruled.

*797 The case is one of complicated facts, and the record is such as to require careful attention, but we are without the benefit of a brief filed in behalf of appellees. Although this might be considered as a tacit admission that there were errors in the record requiring reversal, yet we cannot so treat it, and must, with the aid of brief for appellant, go through the record and find out, if we can, whether there are reasons for upholding the judgment which appellees do not attempt to support, in this court by a brief filed in their behalf.

The evidence discloses that Northcutt Bros, had the contract for the erection of the school building mentioned above and they sublet to appellant the excaváting and back filling work, who, in turn, sublet it to appellees. By the terms of the contract that appellant had with Northcutt Bros, they were to complete the work within a certain time, else pay a penalty for each day the work remained uncompleted thereafter. It was testified by Mr. Carl that this fact was well known to appellees at the time they made the contract, and that he was assured by them that they would complete the work in about eighteen days. As alleged in the petition, the contract was verbal but it was reduced to writing for the purpose of signing, but for some unexplained reason it never was signed. It is alleged in the petition, and also proven by Mr. Carl, representing appellant, that appellees were to do all of the excavating and back filling, that is, they were to excavate the cellar, dig trenches, do the back filling and grading. The trenches were the footings for -the foundation, and all of this work was shown on the plans furnished to appellees when they commenced the work. It is not entirely certain from the evidence the amount of excavating which was required. It may have been slightly less than alleged in the petition. The work was commenced by appellees immediately after the maldng of the contract, but it was not pursued with diligence, according to the evidence for appellant. Instead of its being completed in eighteen days,- it had not been completed by the latter, part of October. The partners, Miller and Parish, from the evidence offered by appellant, seemed to have disagreed about matters, and thereby delayed the work. Appellant was compelled to pursue its work with diligence; consequently they were handicapped by the failure of appellees to do the excavating. It is made to appear by the evidence for appellant that appellees had substantially abandoned all work *798 at the time it was taken over by appellant. Appellant furnished money for the work, although not required to do so, and Mr. Carl testified that on one occasion, when he advanced money to Parish, Miller forbade his doing so again.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Steffen v. United States
213 F.2d 266 (Sixth Circuit, 1954)

Cite This Page — Counsel Stack

Bluebook (online)
29 S.W.2d 545, 234 Ky. 794, 1930 Ky. LEXIS 273, Counsel Stack Legal Research, https://law.counselstack.com/opinion/carl-construction-company-v-miller-kyctapphigh-1930.