Cargo Carriers, Incorporated v. Richmond Steel Company, Incorporated

263 F.2d 919, 1959 U.S. App. LEXIS 4367
CourtCourt of Appeals for the Fourth Circuit
DecidedFebruary 20, 1959
Docket7743
StatusPublished
Cited by1 cases

This text of 263 F.2d 919 (Cargo Carriers, Incorporated v. Richmond Steel Company, Incorporated) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fourth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Cargo Carriers, Incorporated v. Richmond Steel Company, Incorporated, 263 F.2d 919, 1959 U.S. App. LEXIS 4367 (4th Cir. 1959).

Opinion

HAYNSWORTH, Circuit Judge.

In this action for damages for breach of a contract to construct steel barges, tried to the court without a jury, the District Judge concluded that the contract had been rescinded by mutual consent. *920 There is no great disagreement among the parties as to what was done and said, the issue being whether or not all of the facts and circumstances warrant the inferences drawn and the conclusion reached by the District Court. We think they do not.

Cargo Carriers, Inc. operates a fleet of barges from points in the upper Mississippi Valley eastward through the Great Lakes to the Eastern Seaboard and southward through the Mississippi and its tributaries to ports on the Gulf of Mexico. Being in need of additional barges, in 1955 it solicited proposals from a number of shipyards. Among those received was one from Richmond Steel Company, which, after some modification during further negotiations, resulted in an agreement that Richmond Steel would construct two steel “river barges” for $77,850 each and six “coast-wise barges” for $84,850 each, deliveries to commence late in January 1956 and to be completed approximately three months later. The agreement of October 13, 1955 was confirmed by a “contract letter” from Richmond Steel to Cargo Carriers dated October 18, 1955 and accepted by Cargo Carriers on October 20, 1955.

During the negotiations which culminated in the contract, representatives of Cargo Carriers referred to the then current scarcity of steel plate for barges and pressed Houck, Richmond Steel’s sales manager, for assurance that the proposed delivery schedule could be met. Houck assured them that it would be met. He asserted that Richmond had steel on hand to begin construction of the barges and explained Richmond’s supposed ability to obtain steel barge plates, when other yards were encountering difficulty, by reference to the fact that Richmond not only operated a shipyard but was engaged in the business of steel warehousing and in fabricating structural steel and ornamental iron.

The great confidence exhibited by Houck on October 13 deteriorated to seeming hopelessness on October 28. On the latter date he called Hays, president of Cargo Carriers, and informed him that, after contacting his suppliers, he had been unable to obtain assurance of timely steel deliveries and would be unable to meet the contract’s delivery schedule. 1 Hays responded that he could not wait and would look elsewhere, but would call Houck on the following Monday, October 31, 1955. 2

*921 Though Houck tried unsuccessfully to reach Hays by telephone on November 2, there was no further conversation between the parties until November 4 when Hays called Houck. 3 During this conversation, Hays reported a fruitless search for another shipyard which could promise a delivery schedule approaching his need, and Houck said his steel situation remained unchanged and he did not know when he could construct the barges. Houck suggested that Hays accept a proposal of another shipyard which, according to Hays, would undertake to construct the barges for delivery in June.

After talking to Hays on November 4, Houck wrote to him:

“November 4, 1955.
“Cargo Carriers, Inc. Grain Exchange Building Minneapolis, Minnesota
Attention: Mr. F. J. Hays, President.
“Dear Mr. Hays:
“This will confirm the writer’s conversation with you on Friday, October the 28th, 1955 and today, November 4, 1955. On Friday, October the 28th, the Richmond Steel Company called you to inform you that the plate situation had changed almost overnight, and that the mills would not live up to the promises which they made to us several weeks before. Our vice president, Mr. Charles Williams and myself, made a trip the week of October the 23rd and personally visited all of our plate suppliers and returned to Richmond on Friday, October the 28th. Our findings were that we could get no promise at all for steel plate in time to complete your order, as we had scheduled. We notified you of this in our telephone conversation on Friday, October the 28th and it was agreed at that time that you could not wait for us to give a delivery date, and that you would see about placing the order elsewhere, and that you would contact us on Monday, October the 31st.
“We explained to you that we had spent a considerable amount of time and money on this order, but in view of the fact that we knew you wanted your barges in the early spring of next year, and that we found that we were not in a position to make this delivery, we felt that the right thing to do was to notify you rather than delay your program. When we did not hear from you on Monday, we assumed that you had placed the order elsewhere, however, according to your conversation today you have not placed the order with another supplier.
“We appreciate your kindness and sincerely regret that we are unable, at this time to give you any delivery promises close to your requirements. As explained to you again today, we have made a thorough investigation of the steel plate situation with all of our plate suppliers, the supply situation could not be worse and it does not appear to us that it will improve. Under these circumstances you can readily see that we can make no delivery promise, and knowing your desire for delivery early next year we can only say that such a delivery would be impossible. Such being the situation and realizing your need for prompt delivery we would be willing, as we have already stated, to relieve you of any obligation so that you may make other arrangements. We regret very much that the supply situation prevents our giving the delivery desired, however, if the situation should improve we will contact you at that time. Thanking you again, for the courtesies extended we remain,
“Very truly yours,
Richmond Steel Company, Inc.
J. R. Houck, Sales Manager.”

*922 Though he was then uninformed of Richmond Steel’s Trap Rock contract, 4 upon receipt of Houck’s letter of November 4, Hays became suspicious that Richmond Steel’s difficulty might be want of potential profit in performance of the contract rather than want of steel. In an effort to discover whether Richmond Steel was honestly representing its steel supply situation, he sent to Richmond a Captain Wright, who was Cargo’s marine superintendent. By telephone to Houck, Wright arranged a meeting in Richmond on November 11th. At that meeting Houck told Wright the contract had been terminated, this being the first occasion a word of such import had been used. Wright, nevertheless, persisted in his inquiry into the situation and, ignorant of the Trap Rock contract, became convinced that Richmond Steel was having difficulty obtaining steel and would be happy to proceed with the contract if it could procure steel plates.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
263 F.2d 919, 1959 U.S. App. LEXIS 4367, Counsel Stack Legal Research, https://law.counselstack.com/opinion/cargo-carriers-incorporated-v-richmond-steel-company-incorporated-ca4-1959.