Carey

Superior Court of Delaware·Decided July 1, 2015·No. 11C-10-029·Published

Opinion

IN THE SUPERIOR COURT OF THE STATE OF DELAWARE IN AND FOR SUSSEX COUNTY

RICHARD B. CAREY and ) CAREY’S HOME ) CONSTRUCTION, LLC )

)

Plaintiffs, )

)

v. ) C.A. No. S11C-10-029 MJB )

THE ESTATE OF DAVID L. MYERS ) and ARLENE J. MYERS )

)

Defendants. )

Submitted: April 15, 2015 Decided: July 1, 2015

DECISION AFTER TRIAL

Tasha M. Stevens, Esq., Fuqua, Yori and Willard, 26 The Circle, P.O. Box 250, Georgetown, Delaware 19947, Attorney for Plaintiff

Dean A. Campbell, Esq., Law Office of Dean A. Campbell, LLC, 401 North Bedford Street, P.O. Box 568, Georgetown, Delaware 19947, Attorney for Defendant

BRADY, J.

I. INTRODUCTION & BACKGROUND This is a contract dispute between a general contractor and his clients. Contractor Richard B. Carey (“Carey”) is the owner and sole member of Carey’s Home Construction, LLC (“Carey’s Construction,” collectively, “Plaintiffs”). In 2008, Carey entered into a contract with David and Arlene Myers (“Mr. Myers” and “Mrs. Myers,” collectively, “Defendants”) to serve as general contractor on their custom home project. Mr. Myers has since passed away. At some point during the building process, the relationship between the parties deteriorated; Defendants ceased to make payments; and Carey stopped work.

Carey filed the instant action on October 31, 2011, alleging breach of contract and unjust enrichment. Specifically, Carey alleges that Defendants breached the contract by failing to pay the seventh installment and by failing to pay for extras that Defendants allegedly requested and Carey allegedly completed. 1 Carey further alleges unjust enrichment on the grounds that he performed extra work, that Defendants were aware of the extra work, and that Defendants knew they would be charged for the extra work. 2 After the Court denied their Motion to Dismiss, Defendants filed an Answer and Counterclaim on April 20, 2012. Defendants deny that Carey performed his obligations in accordance with the contract. 3 Defendants deny that any “extra” work was performed and instead maintain that all of the work completed by Carey was work he was obligated to do under the original contract. 4 Defendants allege affirmative defenses, including that Carey breached the contract first “through non-performance and abandonment” and “by failing to

1 Complaint, Item 1, at 1-2. 2 Complaint, Item 1, at 2-3. 3 Answer, Item 13, at 2. 4 Answer, Item 13, at 3.

coordinate the job properly.” 5 Defendants further allege that Carey failed to disclose all of the subcontractors who performed work on the house and engaged in fraudulent billing for “extras” which were not authorized by signed change orders (when the contract stated that signed change orders were required). 6 Defendants counterclaimed against Carey for breach of contract and negligent supervision for allegedly failing to coordinate and supervise his subcontractors, causing damage to the property; and for ultimately abandoning the project rather than correcting the damage. 7 Specifically, Defendants allege that Carey permitted the hardwood floor and custom built cabinets to be installed before the HVAC system was installed and operational, resulting in damage to these fixtures caused by humidity. 8 Defendants allege breach of the implied warranty of good quality and workmanship on the same grounds. 9 Defendants allege consumer fraud for Carey’s alleged failure to provide the change orders in writing, as per the contract, before performing extra or different work. 10 Finally, Defendants allege that Carey deceptively used the fictitious name “Carey’s Custom Home Construction,” whereas the actual name of the business entity owned by Carey is “Carey’s Home Construction,” in violation of 6 Del. C. §3101. 11 During trial, Defendants suggested that Carey also acted in bad faith to conceal the fact that his business is an LLC rather than a sole proprietorship. 12 A three-day bench trial was held June 2-4, 2014. Plaintiffs and Defendants submitted post-trial closing statements on June 27, 2014 and July 21, 2014, respectively. The Court received a complete set of transcripts on April 15, 2015, and the Court took the matter under

5 Answer, Item 12, at 3. 6 Answer, Item 13, at 3-4. 7 Answer, Item 13, at 5-6. 8 Answer, Item 13, at 6. 9 Answer, Item 13, at 6-7. 10 Answer, Item 13, at 7. 11 Answer, Item 13, at 8. 12 Trial Transcript B at 150.

consideration. For the reasons detailed below, the Court finds that both parties breached the contract and owe damages to one-another. Offsetting the damages that Defendants owe to Plaintiff by the damages that Plaintiff owes to Defendants, the Court awards judgment to Plaintiff in the amount of $2,490.80.

II. TESTIMONY AT TRIAL

A. Carey’s Testimony for the Plaintiff Plaintiffs only called one witness at trial, Richard Carey. Carey testified that he has been a contractor in Sussex County for the past 25 years. 13 Carey testified that he has been in business for himself since 1997, originally as a sole proprietorship, which he later converted to an LLC for worker’s compensation reasons. 14 Carey testified that the trade name of his business is Carey’s Custom Home Construction, but when his accountant submitted the paperwork to create the LLC, the accountant left out the word ‘custom.’ 15 Hence, Carey testified, his LLC is named Carey’s Home Construction, although Carey says that he was unaware that ‘custom’ had been omitted until he became involved in the present litigation. 16 Carey testified that he was approached by Defendants sometime around 2007 about the possibility of Carey building a house for them. 17 Eventually, Defendants settled on a home in the Bridlewood development. Carey testified that when he asked Defendants what kind of house they were interested in, they indicated that they liked a home that Carey had built for another client, Kenny Hughes. 18 Carey said he told the defendants to contact the

13 Trial Transcript A at 21. 14 Trial Transcript A at 22-23. 15 Trial Transcript A at 22. 16 Trial Transcript A at 22, 24. 17 Trial Transcript A at 28. 18 Trial Transcript A at 28.

architect who designed Mr. Hughes’ home, M.R. Designs. 19 Carey testified that Defendants came back to him after contacting M.R. Designs and told him that they did not get the plans because they thought the price was too expensive. 20 Carey said that he spoke with the architect and the architect agreed to provide an unmodified copy of the plans for Mr. Hughes’ home at a lower price than it would have cost to draw up new plans or modify the Hughes plans. 21 These were the plans that Carey went on to use for Defendants’ home. Carey testified that he gave the plans to Defendants, and that Defendants took the plans home to review them and make changes. 22 After Defendants had a chance to review the plans, the parties met to discuss the desired changes. The changes described by Carey include the house being “flip-flopped,” meaning that the positions of the kitchen and dining room were switched with the master bedroom and bath. 23 Other changes included changing a screened-in porch into a closed-in room; dividing what was originally a sunroom into a closed-in room and a closet; and turning an office into a bedroom. 24 Carey testified that before construction began he had additional discussions with Defendants regarding what they wanted in the house and that some of the content of these conversations was memorialized in Carey’s notes. 25 Carey testified that he originally quoted Defendants $289,000 for the house they wanted. 26 Carey testified that Defendants told him that $289,000 was too high and indicated that they needed to get down to a certain number, but did not indicate what this number was. 27 Carey indicated several changes to which Defendants allegedly agreed for the purpose of

Free access — add to your briefcase to read the full text and ask questions with AI

Carey, (Del. Ct. App. 2015).

Carey (Carey) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Twin City Fire Insurance v. Delaware Racing Ass'n
840 A.2d 624 (Supreme Court of Delaware, 2003)
Stephenson v. Capano Development, Inc.
462 A.2d 1069 (Supreme Court of Delaware, 1983)
BioLife Solutions, Inc. v. Endocare, Inc.
838 A.2d 268 (Court of Chancery of Delaware, 2003)
Bechtel v. Robinson
886 F.2d 644 (Third Circuit, 1989)