Captiva Lake Investments, LLC, a Missouri Limited Liability Company, and Cypress Condominium at the Lake of the Ozarks Association v. Ameristructure, Inc., a Missouri Corporation, and Stephen J. Sacco, Defendants/Respondents.

CourtMissouri Court of Appeals
DecidedApril 22, 2014
DocketED100569
StatusPublished

This text of Captiva Lake Investments, LLC, a Missouri Limited Liability Company, and Cypress Condominium at the Lake of the Ozarks Association v. Ameristructure, Inc., a Missouri Corporation, and Stephen J. Sacco, Defendants/Respondents. (Captiva Lake Investments, LLC, a Missouri Limited Liability Company, and Cypress Condominium at the Lake of the Ozarks Association v. Ameristructure, Inc., a Missouri Corporation, and Stephen J. Sacco, Defendants/Respondents.) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Captiva Lake Investments, LLC, a Missouri Limited Liability Company, and Cypress Condominium at the Lake of the Ozarks Association v. Ameristructure, Inc., a Missouri Corporation, and Stephen J. Sacco, Defendants/Respondents., (Mo. Ct. App. 2014).

Opinion

In the Missouri Court of Appeals Eastern District DIVISION TWO

CAPTIVA LAKE INVESTMENTS, LLC, ) No. ED100569 a Missouri Limited Liability Company, ) ) and ) ) CYPRESS CONDOMINIUM AT THE ) Appeal from the Circuit Court LAKE OF THE OZARKS ASSOCIATION, ) of St. Louis County ) Plaintiffs/Appellants, ) ) v. ) Honorable David Lee Vincent, III ) AMERISTRUCTURE, INC., ) a Missouri Corporation, ) ) and ) ) STEPHEN J. SACCO, ) Filed: April 22, 2014 ) Defendants/Respondents. )

Introduction

Captiva Lake Investments, LLC, a Missouri Limited Liability Company

(Captiva), and Cypress Condominium At The Lake Of The Ozarks Association (Cypress)

(collectively Appellants) appeal from the trial court’s judgment granting the Amended

Motion for Summary Judgment of Ameristructure, Inc. (Ameristructure) and

Ameristructure’s president and professional engineer Stephen J. Sacco (Mr. Sacco)

(collectively Respondents) and entering judgment in favor of Respondents and dismissing with prejudice Counts I, IV, V and VII of Appellants’ Second Amended Petition. We

affirm.

Factual and Procedural Background

In 2005, Majestic Pointe Development Company, LLC (MPDC) was endeavoring

to construct the Majestic Pointe Condominiums (Project) on some land MPDC owned in

the Lake of the Ozarks. On August 8, 2005,1 MPDC, as owner of the Project, contracted

with Kidwell Construction, Inc. (Kidwell) as general contractor for the construction of

two condominium complexes known as Building No. 4 and Building No. 5 in furtherance

of the Project (General Contract). Building No. 5 was completed; Building No. 4 was

not.

On September 9, 2005, and then as amended on October 27, 2005, to convert an

hourly pay structure to a fixed fee of $129,000.00, Kidwell and Ameristructure

contracted (Subcontract) for Ameristructure to provide architectural and engineering

services with regard to Building No. 4, with a clause specifically limiting

Ameristructure’s liability on the Project to the agreed-upon fixed fee. The Subcontract

provided for eight site visits during construction, but contained no provision regarding

construction supervision.

On December 2, 2005, Ameristructure signed an Architect’s Consent Agreement

at the request of National City Bank (Bank) that either purported to consent to MPDC’s

collateral assignment of the General Contract it had with Kidwell to Bank or consent to

1 Supplemented on April 17, 2006.

2 MPDC’s collateral assignment of the Subcontract between Ameristructure and Kidwell to

Bank.2

On March 13, 2006, MPDC, in order to obtain additional funding for the Project,

in particular the completion of Building No. 4, signed two promissory notes in favor of

Bank in the amounts of $20,080,000.00 and $1,200,000.00 and agreed as security for said

notes (collectively “Note” or “Loan”) to an “Assignment of Plans, Specifications,

Construction and Service Contracts, Licenses, and Permits” (Construction Deed of Trust

or Collateral Assignment) whereby MPDC collaterally assigned to Bank any and all of its

right, title, and interest in certain contracts for construction and other services issued for

Building No. 4. On this same date, Kidwell executed a Contractor’s Consent Agreement

2 Appellants maintain that under the terms of the Architect’s Consent Agreement, Ameristructure represented to Bank that the contract it had with Kidwell was actually with MPDC, and therefore Ameristructure is collaterally estopped from asserting the lack of privity of contract between it and MPDC and thus Bank and then Captiva. Appellants maintain that because they are now successors in interest of Bank’s rights, they have privity of contract with Ameristructure and thus summary judgment was improvidently granted to Ameristructure. However, in a July 17, 2008 letter written by Ameristructure attorney Frank Keefe to Bank’s Scott Dallman regarding the Architect’s Consent Agreement, he states that “although the agreement states in the RECITALS Section C that ‘[t]he Borrower … has entered into a written agreement with the Architect dated Sept. 9, 2005 …’ the agreement for architectural services is actually between Ameristructure, Inc. and Kidwell Construction, not Majestic Pointe Development, L.L.C.” The letter goes on to inform Bank of Kidwell’s default in payment to Ameristructure for its services pursuant to the Subcontract. Additionally, the only contract dated September 9, 2005 in the record is the Subcontract between Ameristructure and Kidwell. Accordingly, Captiva was aware of the misnomer in the Architect’s Consent Agreement when it took over the Project from Bank in July 2009. Ameristructure had no contractual relationship with MPDC, rather only with Kidwell. As such, MPDC had no ability or right to collaterally assign the Subcontract between Ameristructure and Kidwell, so the “Contract” referred to as being collaterally assigned in the Architect’s Consent Agreement must be the General Contract. However, the agreement specifically defines the “Contract” being assigned as the one dated September 9, 2005, between Kidwell and Ameristructure for architectural services to be performed on the Project by Ameristructure for a fixed fee to be paid by Kidwell of $129,000.00, so it cannot be the General Contract, but the Subcontract. “If language which appears plain considered alone conflicts with other language in the contract, or if giving effect to it would render other parts of the contract a nullity, then we will find the contract to be ambiguous.” Tuttle v. Muenks, 21 S.W.3d 6, 9 (Mo.App. W.D. 2000). Furthermore, the record contains no response to Mr. Keefe’s letter to Bank with regard to the incorrect language. Therefore, this issue has clearly not been resolved by the parties and they are thus free to argue the interpretation of the discrepancies favorable to their respective positions, prohibiting our discernment of the parties’ intent. The impossibility of either outcome is created by a patent ambiguity in the language which creates an irreconcilable conflict in the in the Architect’s Consent Agreement. Even though the face of the Architect’s Consent Agreement contains a patent ambiguity as herein described, we find that its resolution is not necessary to decide this case.

3 and acknowledged or consented to the Construction Deed of Trust or Collateral

Assignment between MPDC and Bank for the purpose of procuring additional funds in

furtherance of the Project.

In June 2008, Bank commissioned an engineering firm, EDM, Inc. (EDM), to

review certain construction documents and building elements to prepare a Building

Analysis Report of Building No. 4 (EDM Report). On June 25, 2008, the EDM Report

was created outlining certain deficiencies in Building No. 4.

MPDC defaulted on its obligations to Bank.

On June 16, 2009, Captiva was created. On July 22, 2009, Bank and Captiva

entered into an agreement whereby Bank transferred its interest in the Loan and

Construction Deed of Trust to Captiva (Loan Assignment). The Loan Assignment

provides “this Assignment is given without recourse, warranty or representation, express

or implied.” Captiva then foreclosed on the property. On August 11, 2009, Captiva

delivered to Ameristructure a notice titled “Notification of Disposition of Collateral and

Notification of Foreclosure of Real Property.” On September 1, 2009, Captiva purchased

the Project condominium property, including Building No. 4, from itself as the holder of

the Note, in “as is where is” condition.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Owens v. Unified Investigations & Sciences, Inc.
166 S.W.3d 89 (Missouri Court of Appeals, 2005)
Comp & Soft, Inc. v. AT & T CORP.
252 S.W.3d 189 (Missouri Court of Appeals, 2008)
Fleischer v. Hellmuth, Obata & Kassabaum, Inc.
870 S.W.2d 832 (Missouri Court of Appeals, 1993)
Sharp Bros. Contracting Co. v. American Hoist & Derrick Co.
703 S.W.2d 901 (Supreme Court of Missouri, 1986)
Burns v. Smith
303 S.W.3d 505 (Supreme Court of Missouri, 2010)
ITT Commercial Finance Corp. v. Mid-America Marine Supply Corp.
854 S.W.2d 371 (Supreme Court of Missouri, 1993)
Westerhold v. Carroll
419 S.W.2d 73 (Supreme Court of Missouri, 1967)
Korte Construction Co. v. Deaconess Manor Ass'n
927 S.W.2d 395 (Missouri Court of Appeals, 1996)
Sympson v. Rogers
406 S.W.2d 26 (Supreme Court of Missouri, 1966)
Smith v. Old Warson Development Company
479 S.W.2d 795 (Supreme Court of Missouri, 1972)
MacKe Laundry Service Ltd. Partnership v. Jetz Service Co.
931 S.W.2d 166 (Missouri Court of Appeals, 1996)
Tuttle v. Muenks
21 S.W.3d 6 (Missouri Court of Appeals, 2000)
Autry Morlan Chevrolet, Cadillac, Inc. v. RJF Agencies, Inc.
332 S.W.3d 184 (Missouri Court of Appeals, 2010)
Renaissance Leasing, LLC v. Vermeer Manufacturing Co.
322 S.W.3d 112 (Supreme Court of Missouri, 2010)
L.A.C. Ex Rel. D.C. v. Ward Parkway Shopping Center Co.
75 S.W.3d 247 (Supreme Court of Missouri, 2002)
G.H.H. Investments, L.L.C. v. Chesterfield Management Associates, L.P.
262 S.W.3d 687 (Missouri Court of Appeals, 2008)
Crowder v. Vandendeale
564 S.W.2d 879 (Supreme Court of Missouri, 1978)
San Luis Trails Ass'n v. E.M. Harris Building Co.
706 S.W.2d 65 (Missouri Court of Appeals, 1986)

Cite This Page — Counsel Stack

Bluebook (online)
Captiva Lake Investments, LLC, a Missouri Limited Liability Company, and Cypress Condominium at the Lake of the Ozarks Association v. Ameristructure, Inc., a Missouri Corporation, and Stephen J. Sacco, Defendants/Respondents., Counsel Stack Legal Research, https://law.counselstack.com/opinion/captiva-lake-investments-llc-a-missouri-limited-liability-company-and-moctapp-2014.