Capolupo v. Massachusetts Department of Environmental Protection

17 Mass. L. Rptr. 190
CourtMassachusetts Superior Court
DecidedDecember 1, 2003
DocketNo. 031556
StatusPublished

This text of 17 Mass. L. Rptr. 190 (Capolupo v. Massachusetts Department of Environmental Protection) is published on Counsel Stack Legal Research, covering Massachusetts Superior Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Capolupo v. Massachusetts Department of Environmental Protection, 17 Mass. L. Rptr. 190 (Mass. Ct. App. 2003).

Opinion

Billings, A. J.

The facts of this case, and particularly the lengthy procedural history of the plaintiffs dealings with the defendant Department of Environmental Protection (“DEP”), are detailed in the Complaint and in the parties’ excellent written submissions, and will not be repeated at any great length here. In brief: the plaintiff seeks to build to build a single-family home on a 27-acre parcel fronting on the Merrimack River in Salisbury. Because his proposed drive would involve two wetlands crossings, the plaintiff was required to, and did, file a Notice of Intent with the Salisbury Conservation Commission. A copy of the NOI went to the Division of Fisheries and Wildlife Natural Heritage and Endangered Species Project (“NHESP”). On December 29, 1999 the Commission, not having heard from NHESP, issued an Order of Conditions, permitting the project.

Three days later, NHESP weighed in, expressing concern that the project would result in loss and disruption of actual habitat of the bald eagle, a species classified as “endangered” (the classification receiving maximum protection) under the Massachusetts Endangered Species Act (“MESA”) and regulations thereunder. See G.L.c. 131A and 321 C.M.R. 10.60. The DEP, on the basis of NHESP’s input, appealed the Order of Conditions and required the plaintiff to obtain a Superseding Order of Conditions from the DEP. This was issued on June 27, 2000 but the plaintiff, unhappy with one of the conditions imposed, appealed it to the DEP’s Office of Administrative Appeals.

Now, the Department advanced the view that the project’s location within actual eagle habitat meant that it needed to be reviewed under the Massachusetts Environmental Policy Act (“MEPA”). Further skirmishing before an administrative law judge resulted in a ruling that the DEP’s new position stemmed from a bona fide change in opinion as to the ability of the project to meet applicable regulatory standards, and so could be advanced. The same ALJ later found, after an evidentiary hearing, that the wetlands crossings lay within actual eagle habitat, and that MEPA review was therefore required. He stayed the DEP’s proceedings pending the conclusion of that review.

As more fully detailed below, MEPA review commences with the project proponent’s filing of an environmental notification form (“ENF”), following which the Secretary of the Executive Office of Environmental Affairs determines whether an environmental impact report (“EIR”) is required. Rather than file an ENF, however, the plaintiff commenced this action.

The plaintiffs three-count complaint seeks (a) review of the stay order under G.L.c. 30A, §14; (b) a declaratory judgment that MEPA review is not required; and (c) relief in the nature of certiorari. It prays both for preliminary injunctive relief, and for a final judgment remanding the case to the Department and ordering it to approve the project without MEPA review. The DEP has moved to dismiss the action under Rule 12(b)(6), on the ground that interlocutory review of the ALJ’s decision is unavailable, and the Complaint therefore falls to state a claim.

For the reasons that follow, the DEP’s Motion to Dismiss is ALLOWED.

DISCUSSION

A. The Regulatory and Administrative Scheme

The plaintiffs project, because of its location (riverfront, containing bordering vegetated wetlands and perhaps habitat of an endangered species), lies at the crossroads of several state environmental statutes and the regulations implementing them. The aspects of the statutory and regulatory schemes directly pertinent to the present motion are as follows.

The Wetlands Protection Act, G.L.c. 131, §40, regulates alteration of bordering vegetated wetlands and other wetland resource areas. The Act is administered by local conservation commissions, subject to review in the DEP.

As noted above, the heart of the present dispute is the DEP’s determination, with which the ALJ agreed, that the project is subject to the review process under MEPA. The SJC has summarized MEPA’s overall “legislative purpose and administrative scheme” as follows:

MEPA consists of two complementaiy provisions. General Laws c. 30, §61, establishes an official policy of environmental protection in the Commonwealth by directing that all State agencies “review, evaluate, and determine the impact on the natural environment of all works, projects or activities con[262]*262ducted by them and . . . use all practicable means measures to minimize damage to the environment.” Section 61 directs that an agency, before taking any action on a project, make substantive findings “describing the environmental impact, if any, of the project and [certifying] that all feasible measures have been taken to avoid or minimize said impact.” In aid of this directive, G.L.c. 30, §§62-62H establishes a process, supervised by the Secretary, thorough consideration of the potential environmental impact of certain projects through preparation of draft and final environmental impact reports (EIRs), and submission of these EIRs to interested State agencies and to the public.
MEPA review begins when the proponent of the project files an environmental notification form (ENF), to advise the Secretary of the nature of the project. G.L.c. 30, §62A. After a thirty-day review period, during which the Secretary consults with the agency and other interested parties, the Secretary issues a written certificate stating whether an environmental impact report (EIR) is required and, if so, the form, scope, content, and level of detail of the EIR. Id. The statute directs that an EIR must describe the nature and extent of the proposed project and its environmental impact; all measures being utilized to minimize environmental damage; any adverse short-term and long-term environmental consequences which cannot be avoided should the project be undertaken; and reasonable alternatives to the proposed project and their environmental consequences. G.L.c. 30, §62B. When an EIR, in draft or final form, is filed, the Secretary issues public notice of the availability of the report, which initiates a thirty-day public and agency review period. G.L.c. 30, §62C. During this time, any reviewing agency or person (or any agency with jurisdiction or with special expertise with respect to any environmental impact involved), may submit written comments to the Secretary, which then become part of the public record. Id.
Within seven days of the completion of the public comment period, the Secretary issues a final statement, indicating whether the EIR “in his judgment . .. adequately and properly complies with the provisions of sections sixty-two to sixty-two H, inclusive [the review procedures of MEPA].” Id. This certification completes the MEPA process. The record created during MEPA review (any draft and final EIRs, all public and agency comments, and the Secretary’s certification or, presumably, failure to certify) provides the information for the agency’s evaluation and subsequent §61 findings review, evaluate, and determine the impact on the natural environment of all works, projects or activities conducted by them and shall use all practicable means and measures to minimize damage to the environment.

Enos v. Secretary of Environmental Affairs, 432 Mass. 132, 136-37 (2000). Significantly for the present case, an agency’s “projects” includeand MEPA jurisdiction therefore extends tonot only the agency’s own activities, but activities by private parties which require a permit from that agency. G.L.c.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

East Chop Tennis Club v. Massachusetts Commission Against Discrimination
305 N.E.2d 507 (Massachusetts Supreme Judicial Court, 1973)
McKenney v. Commission on Judicial Conduct
402 N.E.2d 1356 (Massachusetts Supreme Judicial Court, 1980)
Boston Edison Co. v. Board of Selectmen of Concord
242 N.E.2d 868 (Massachusetts Supreme Judicial Court, 1968)
Boston Edison Co. v. Brookline Realty & Investment Corp.
405 N.E.2d 995 (Massachusetts Appeals Court, 1980)
Borman v. Borman
393 N.E.2d 847 (Massachusetts Supreme Judicial Court, 1979)
Assuncao's Case
359 N.E.2d 1304 (Massachusetts Supreme Judicial Court, 1977)
Saint Luke's Hospital v. Labor Relations Commission
70 N.E.2d 10 (Massachusetts Supreme Judicial Court, 1946)
First Federal Savings & Loan Ass'n v. State Tax Commission
363 N.E.2d 474 (Massachusetts Supreme Judicial Court, 1977)
Douglas Environmental Associates, Inc. v. Department of Environmental Protection
429 Mass. 71 (Massachusetts Supreme Judicial Court, 1999)
Enos v. Secretary of Environmental Affairs
432 Mass. 132 (Massachusetts Supreme Judicial Court, 2000)
Ciardi v. F. Hoffmann-La Roche, Ltd.
436 Mass. 53 (Massachusetts Supreme Judicial Court, 2002)
Fabre v. Walton
781 N.E.2d 780 (Massachusetts Supreme Judicial Court, 2002)
Retirement Board of Taunton v. Contributory Retirement Appeal Board
778 N.E.2d 536 (Massachusetts Appeals Court, 2002)

Cite This Page — Counsel Stack

Bluebook (online)
17 Mass. L. Rptr. 190, Counsel Stack Legal Research, https://law.counselstack.com/opinion/capolupo-v-massachusetts-department-of-environmental-protection-masssuperct-2003.