Capital Electric Cooperative, Inc. v. North Dakota Public Service Commission

2016 ND 73, 877 N.W.2d 304, 2016 N.D. LEXIS 73, 2016 WL 1178323
CourtNorth Dakota Supreme Court
DecidedMarch 28, 2016
Docket20150227
StatusPublished
Cited by3 cases

This text of 2016 ND 73 (Capital Electric Cooperative, Inc. v. North Dakota Public Service Commission) is published on Counsel Stack Legal Research, covering North Dakota Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Capital Electric Cooperative, Inc. v. North Dakota Public Service Commission, 2016 ND 73, 877 N.W.2d 304, 2016 N.D. LEXIS 73, 2016 WL 1178323 (N.D. 2016).

Opinion

KAPSNER, Justice.

[¶ 1] Capital Electric Cooperative, Inc. (“Capital”), appeals from a judgment affirming a Public Service Commission order granting Montana-Dakota Utilities Company (“MDU”) a certificate of public convenience and necessity to extend its electric service in Burleigh County. Because the Commission’s order is in accordance with the law, its findings of fact are supported by a preponderance of the evidence and sufficiently address the evidence presented, and those findings support the conclusions of law, we affirm the judgment.

I

[¶ 2] Menard, Inc., is ’ developing a manufacturing and distribution center near McKenzie, an unincorporated community located in Burleigh County. Capital, a rural electric cooperative, and MDU, an investor owned electric utility, are the only electric suppliers operating in the general area of the Menard site. Since 1928 MDU, through its predecessors in interest, has held a franchise and a certificate of public convenience and necessity issued by the Commission, then called the Board of Railroad Commissioners, to ' serve the McKenzie community. The certificate of public convenience and necessity allows MDU service to the- eastern boundaries of McKenzie, which is immediately northeast of and adjacent to the Menard site. Capital serves rural customers adjacent to the site. MDU serves 28 customers within a one-mile radius of the Menard site and 29 customers within a two-mile radius. Capital serves four customers within a one-mile radius of the Menard site and 11 customers within a two-mile radius.

[¶ 3] In October 2013, Menard requested estimated rates from Capital and MDU based on the anticipated load at its site of approximately 1.2 MW and an estimated annual consumption of 7 million kWh. Both MDU and Capital would néed tó construct extensions to provide three-phase electric supply ‘lines to serve the Menard site. MDU estimated the total annual estimated cost to Menard would be $513,669.84 while Capital estimated' the cost would be $575,883.84. Menard requested service from MDU based on present and’ future cost savings, reliability of service, and the Commission’s regulatory oversight over rates and services. ■

[¶ 4] In November 2013, MDU applied to the Commission to extend electric service to the Menard site. Capital filed a protest and requested a hearing. Following a public hearing, the Commission, in a two-to-one decision, decided to grant MDU a certificate of public convenience and necessity and allow the company to provide electric service to the Menard site. In a nine-page decision consisting of 34 findings of fact, the Commission explained:

34. The Commission finds that public convenience and necessity reasonably requires approval of Montana-Dakota’s application because: .
• The customer prefers electric service from Montana-Dakota as it results in more than $60,000 in annual cost savings and better meets the customer’s needs;
• Montana-Dakota has served customers in the area since 1928 and has more customers within a one-mile and two-mile radius of the location;
*306 • Montana-Dakota’s substation is located closer to the Menard Site providing less voltage drop and less line length on which a fault could occur;
• The proposed extension of Montana-Dakota’s three-phase system to serve the site is shorter than the proposed extension of Capital Electric’s three-phase system.
• Montana-Dakota will serve the Me-nard Site more economically when considering both the cost to extend service and the annual costs to the customer as reflected in rates for service;
• Montana-Dakota’s extension of ser- ■ vice would, best serve the community of McKenzie and realize significant cost savings to Menard, Inc., therefore best serving orderly and economic development of the area.

The district court affirmed the Commission’s order.

II

[¶ 5] Capital argues the Commission erred in granting MDU a certificate of public convenience and necessity to provide electric service to the Menard site.

[¶6] In North Cent. Elec. Coop., Inc. v. N.D. Pub. Serv. Comm’n, 2013 ND 158, ¶¶ 6-7, 837 N.W.2d 138, we explained:

An appeal from a Commission decision is governed by the Administrative Agencies Practice Act, N.D.C.C. ch. 28-32. Capital Elec. Coop., Inc. v. City of Bismarck, 2007 ND 128, ¶30, 736 N.W.2d 788. As relevant to this appeal, a district court must affirm a Commission order under N.D.C.C. § 28-32-46, unless:
1. The order is not in accordance with the law.
[[Image here]]
5. The findings of fact made by the agency are not supported by a preponderance of the evidence.
6. The conclusions of law and order of the agency are not supported by its findings of fact.
7. The findings of fact made by the agency do not sufficiently address the evidence presented to the agency by the appellant.
In an appeal to this Court from a district court’s decision on an appeal from a Commission decision, we review the Commission’s order in the same manner as the district court. See N.D.C.C. § 28-32-49. The' Commission’s decision on questions of law is fully reviewable. Capital Elec. Coop., 2007 ND 128, ¶ 31, 736 N.W.2d 788. In reviewing the Commission’s findings of fact, however, we do not substitute our judgment for that of the Commission or make independent findings. Id. See Power Fuels, Inc. v. Elkin, 283 N.W.2d 214, 220 (N.D.1979). Rather, in reviewing the Commission’s findings of fact, “ ‘[w]e determine only whether a reasoning mind reasonably could have determined that the factual conclusions reached were proved by the weight of the evidence from the entire record.’ ” Capital Elec. Coop., at ¶31 (quoting Power Fuels, at 220).

“Agency expertise is entitled to appreciable deference if the subject matter is highly technical.” Cass Cty. Elec. Coop., Inc. v. N. States Power Co., 518 N.W.2d 216, 220 (N.D.1994).

[¶ 7] Under the Territorial Integrity Act-,- an electric public utility, unlike a rural electric cooperative, must secure a certificate of public convenience and necessity before extending service to a new customer outside the corporate limits of a municipality. See N.D.C.C. §§ 49-03-01 and 49-03-01.1; Capital Elec. Coop., Inc. *307 v. Pub. Serv. Comm’n, 534 N.W.2d 587, 590 (N.D.1995). The criteria for the Commission to consider in deciding whether a certificate of public convenience and-necessity should be issued are:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Environmental Law & Policy Center v. N.D. Public Svc. Commission
2020 ND 192 (North Dakota Supreme Court, 2020)
Minn-Kota Ag Products, Inc. v. N.D. Public Service Commission
2020 ND 12 (North Dakota Supreme Court, 2020)
Voigt v. North Dakota Public Service Commission
2017 ND 76 (North Dakota Supreme Court, 2017)

Cite This Page — Counsel Stack

Bluebook (online)
2016 ND 73, 877 N.W.2d 304, 2016 N.D. LEXIS 73, 2016 WL 1178323, Counsel Stack Legal Research, https://law.counselstack.com/opinion/capital-electric-cooperative-inc-v-north-dakota-public-service-nd-2016.