Canvasser Custom Builders, Inc. v. Seskin

171 N.W.2d 654, 18 Mich. App. 606
CourtMichigan Court of Appeals
DecidedNovember 5, 1969
DocketDocket 3,048
StatusPublished
Cited by7 cases

This text of 171 N.W.2d 654 (Canvasser Custom Builders, Inc. v. Seskin) is published on Counsel Stack Legal Research, covering Michigan Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Canvasser Custom Builders, Inc. v. Seskin, 171 N.W.2d 654, 18 Mich. App. 606 (Mich. Ct. App. 1969).

Opinion

Fitzgerald, P. J.

This appeal is based on an equitable action to foreclose a mechanic’s lien filed by the plaintiff and general contractor, Canvasser Custom Builders, against defendants Alex Seskin, Muriel Seskin and Service Investment Company. Defendant Alex Seskin is the sole stockholder of *608 Service Investment Company, which is the owner of record of the property involved in this action. Muriel Seskin is the wife of defendant Alex Seskin.

The dispute is contractual in nature and arose over the construction of the Abbey Convalescent and Nursing Home in Warren, Michigan. The principal witnesses on matters relating to the disputed agreements for construction of the nursing home are Robert Canvasser for plaintiff and Alex Seskin for defendant.

The long chain of events which culminated in litigation between the parties began at a meeting in the offices of architects Tobocman & Lawrence, who had been engaged by defendants Seskin to draw the plans and specifications for the Abbey Convalescent and Nursing Home. During this meeting in April, 1962, Mr. Seskin met Marvin Canvasser, an officer of plaintiff corporation. Several meetings were held between the parties and on July 27, 1962, a document entitled “Preliminary Notes” was drafted by the parties and later admitted into evidence during the trial as Exhibit D, the alleged written agreement between the parties regarding construction of the nursing home. Under defendants’ interpretation of Exhibit D, plaintiff was to be paid a fixed fee of $25,000 for supervision of construction and an amount for “unique contributions”, determination of the amount being left to the sole discretion of defendants.

It is alleged by plaintiff that the only contract between the parties was oral in nature, the product of a telephone conversation between Robert Canvasser and Alex Seskin on July 27, 1962, and confirmed by a handshake the following day. It is alleged further that no final written contract was ever executed although they repeatedly requested such an agreement. Plaintiff avers that Exhibit D was *609 never intended by the parties to express the full understanding between them as it was clearly marked “Preliminary Notes” and “to be reduced to A.I.A. contract”. Under the aforementioned oral agreement plaintiff was to be paid:

A. Base fee of $25,000 to be paid within 2 years. No interest was to be charged if paid within one year from date of closing and interest at 7% if not so paid within one year;

B. 40% of any savings if construction costs were less than $240,000;

C. 10% for extras;

D. $1,000 per week for each week completion was achieved prior to February 1, 1963; and

E. Reasonable compensation for so-called unique services which were apparently defined as those that are not normal contractor services.

The defendants deny the existence of items B, C and D of the alleged oral agreement. After July 27, 1962, the date of the two disputed agreements, construction commenced in accordance with the plans and specifications.

On January 29, 1963, the city of Warren, Michigan, issued a conditional certificate of occupancy, and on February 7, 1963, Robert Canvasser presented a “special bill” to defendant Alex Seskin who refused to pay, stating that it was contrary to their prior written agreement of July 27, 1962. On February 15, 1963, defendants delivered a check for $3,000 as payment in full for “unique contributions” although, as indicated in the record, they felt there was nothing due plaintiff: in that connection and payment was made under protest to avoid interference with defendants’ mortgage.

On March 6, 1963, plaintiff took steps to perfect a mechanic’s lien and on June 4, 1963, action was begun. Defendants answered, denying the existence *610 of the oral agreement and contending that the only-agreement was in writing and was contained in the preliminary agreement of July 27, 1962 (Exhibit D). Defendants also counterclaimed, denying completion in accordance with plans and specifications and charging faulty construction, stating that $32,-950 would be required to correct the defects. Fifteen thousand dollars had been paid plaintiff on sums due before completion of the building and as mentioned above, an additional $3,000 thereafter for “unique services”.

It was the holding of the lower court that the contract between the parties was evidenced by the oral agreement of July 27, 1962, and the written notations of the same date were not the final intentions of the parties and, hence, not binding upon them. The judgment provided that there was a lien on the premises in the amount of $23,585, taxation of $793.50 in costs, witness subpoena fees of $60, attorney fees in the amount of $4,900, and interest of $5,159.42 to the date of judgment; statutory interest on the judgment to commence running with the judgment and a sheriff’s sale to be made within 30 days of judgment.

Motion for a new trial was made by defendants and subsequently denied by an order dated November 28, 1966. A judgment was entered on November 28, 1966, from which this appeal was brought.

The main issue with which we are faced on this appeal is whether the trial court erred in its determination that the alleged written agreement entitled “Preliminary Notes” signed and dated on July 27, 1962, was superseded by the alleged oral agreement of the same date.

It is the contention of the plaintiff that a construction contract may be orally agreed upon after the signing of a series of preliminary notes of con *611 versations which were never reduced to a formal A.I.A. contract as originally intended. Plaintiff also asserts that defendants’ Exhibit D was not so complete in its terms as to preclude oral evidence which was contradictory. The defendants’ position is that the written agreement was the only contract between the parties and the trial court erred in admitting parol evidence to contradict a written instrument which stated the basic terms of an understanding and was dated and signed by the parties to be bound.

In the case at bar, the trial court was faced with the difficult task of determining which of the two alleged agreements was to stand as a final monument to the thoughts and understandings of the parties. It is a universal rule of law that an instrument which is complete upon its face, unambiguous in its terms, intended by the parties to be a complete integration of their agreement and signed by the parties to be bound cannot be varied or contradicted by parol evidence in the absence of fraud, duress or mistake. However, it is an equally well entrenched rule that parol evidence may be introduced for purposes of proving to the court which of two alleged agreements was the actual contract of the parties. This seemingly paradoxical situation is explained in 3 Corbin on Contracts, § 582, p 450, which states:

“The very testimony that the ‘parol evidence rule’ is supposed to exclude is frequently, if not always, necessary before the court can determine that the parties have agreed upon the writing as a complete and accurate statement of terms.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

20240229_C365939_43_365939.Opn.Pdf
Michigan Court of Appeals, 2024
Canvasser Custom Builders, Inc. v. Seskin
196 N.W.2d 859 (Michigan Court of Appeals, 1972)
Ensign Painting Co. v. Alfred A. Smith, Inc.
188 N.W.2d 534 (Michigan Supreme Court, 1971)
Cushman v. Avis
184 N.W.2d 294 (Michigan Court of Appeals, 1970)
Ensign Painting Co. v. Alfred A. Smith, Inc.
175 N.W.2d 789 (Michigan Court of Appeals, 1970)
Tuuk v. Andersen
175 N.W.2d 322 (Michigan Court of Appeals, 1969)

Cite This Page — Counsel Stack

Bluebook (online)
171 N.W.2d 654, 18 Mich. App. 606, Counsel Stack Legal Research, https://law.counselstack.com/opinion/canvasser-custom-builders-inc-v-seskin-michctapp-1969.