Cantrell v. Department of Highways

11 Ct. Cl. 110
CourtWest Virginia Court of Claims
DecidedMay 28, 1976
DocketNo. D-240; No. D-268o
StatusPublished

This text of 11 Ct. Cl. 110 (Cantrell v. Department of Highways) is published on Counsel Stack Legal Research, covering West Virginia Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Cantrell v. Department of Highways, 11 Ct. Cl. 110 (W. Va. Super. Ct. 1976).

Opinion

GARDEN, JUDGE:

On December 15, Í967, at approximately 5:00 p.m., the Silver Bridge, which spanned the Ohio River from Point Pleasant, West [111]*111Virginia, to a point on the Ohio shore a few miles north of Gallipolis, Ohio, collapsed, constituting one of the worst disasters, if not the worst, in the history of the State of West Virginia. At the time of collapse, there were 37 vehicles on the bridge, 29 vehicles in the westbound lane and the remaining 8 vehicles (six cars and two heavily laden gravel trucks) in the eastbound lane. Six vehicles were on the approach span and not affected by the collapse. Seven vehicles fell to the ground below the Ohio side span and the remaining vehicles, 24 in number, fell into the river. Of the 64 persons in the 31 vehicles that fell with the bridge, 46 died and 9 of the 18 survivors were injured.

As a result of this disaster, 56 claims for wrongful death, personal injury and property damage were filed in this Court, and two additional wrongful death claims were filed just prior to December 15, 1974, seeking recovery for the wrongful death of two persons whose bodies were never recovered from the Ohio River. At the initial stages of this litigation, it was stipulated that in Claim Nos. D-240 and D-268o, Margaret Mae Cantrell, Administratrix, and William Frederick White, Executor, were the legal representatives of two of the persons who died as a result of this tragedy. It was further stipulated that a determination of respondent’s liability in the above-mentioned claims would be dispositive of all other claims pending in this court as a result of the bridge collapse. It was further understood that only the issue of liability would be decided at this time, and that should it be determined that liability rested with respondent, additional testimony would be presented for the purpose of determining the proper amount of awards in each case.

On May 13, 1926, Congress authorized the construction of the Silver Bridge by the Gallia County Ohio River Bridge Company, an Ohio corporation, which had been formed prior thereto for the purpose of constructing a toll bridge across the Ohio River between Gallipolis, Ohio, and Point Pleasant, West Virginia. Initial plans for the bridge were submitted to the United States Engineers’ office in December of 1926. Ih j&áy of 1927; JrE. Grenier Company, as consulting engineer, prepared plans and specifications for the new bridge using parallel wire cables with two alternative methods of suspension, including eyebars. The contract for the construction of the bridge was awarded to the General Contracting Company of Pittsburgh, Pa., and American Bridge Company (a division of United States Steel Corporation) was awarded the sub-contract for the construction of the [112]*112superstructure. On July 1, 1927, American Bridge Company entered into a contract with General Contracting Company to build the superstructure using eyebars as the suspension method in lieu of parallel wire cables. The consulting engineer, J. E. Greiner Company, approved these plans in June of 1927. The bridge was completed in late June of 1928, and on June 29, 1928, the United States District Engineer reported that the conditions of the permit issued to the owner of the bridge, “had been fully complied with and the work completed in substantial accordance” with the approved plans. The total cost of the bridge was $898,096.44, of which $862,341.44 was attributed to construction. After construction, the bridge was operated as'a" toll bridge by its owiier until December 24, 1941, when it was sold to the State of West Virginia.

As constructed, the Silver Bridge was a heat-treated eyebar chain suspension bridge. It had a total of seven spans or sections, two 75' 3" spans (one on each end); two 75-foot spans (one on each side); two 380-foot spans (one on each side); and a center span of 700 feet. The two 380-foot spans and the 700-foot span were in suspension, and the eyebar chain also operated as a portion of the upper chord of the stiffening truss in the 700-foot and the two 380-foot spans. The bridge and approaches were supported by six concrete piers (number 1 through 6, west to east), and the chain was affixed to two rocker towers (located on piers 3 and 4) each of which towers was 130' 1014" high, extending approximately 95 feet above the deck or roadway. The roadway was 21 feet wide, and there was a 5' 6" wide sidewalk inside the stiffening truss on the upstream or north side of the bridge. Although the roadway, as originally designed, was to accommodate three lanes of traffic, it was ultimately constructed with only two lanes for movingAraffic,,., The chain suspension system was anchored on each side of theriver by almost identical anchorage chambers each of which was 44 feet across the front, 34 feet across the back and 200 feet long. The anchorages were filled with steel reinforced concrete and earth, each of which weighed approximately 10,000,000 pounds, and under each was embedded 405 steel reinforced concrete piles 15 feet long.

The chain suspension system contained a total of 148 eyebars, varying in length from 34' 8V2" to 65' 14", the lightest weighing 2,560 pounds and the heaviest 5,306 pounds. Eyebar 330 (the origin of the ultimate collapse) was 63' 11" in length and weighed 5,053 pounds. The head of the eyebar was 28 inches in diameter, 1 and 15/16 inches thick and 12 inches wide. It was connected to other eyebars [113]*113at what will later be referred to as joint C-13 by a pin which was 1114 inches in diameter, 13 inches in length and weighing in excess of 300 pounds.

As earlier mentioned, the bridge was constructed on six concrete piers. Piers 3, 4 and 5, as constructed, were erected in the river, resting on steel reinforced concrete caissons which in turn were resting on bedrock. Piers 1 and 6, so-called land piers and being tlie most westerly and easterly piers of the bridge, supported only the approaches and were completely independent of any support for the spans in suspension. Pier 2, on the Ohio side, was also constructed on land. For vehicular traffic, the roadway of the bridge had a vertical clearance of 16 feet, and the height of the roadway above the water at normal pool stage was in excess of 100 feet.

Two other events took place after the bridge was completed in 1928, both of which the claimants vigorously contended led to or contributed to the ultimate collapse of the bridge. In 1937, the Gallipolis Lock and Dam was completed some 14 miles down-stream from the Silver Bridge. This dam raised the elevation of the river 1814 feet above the normal pool stage at the Silver Bridge. Then again between 1949 and 1952, a floodwall was constructed on the West Virginia side of the Ohio River at Point Pleasant. It was so constructed that the base of the floodwall was 2614 vertical feet and 100 feet horizontally from, the normal pool stage and the edge of the river.

Respondent’s first concern immediately after the collapse was to rescue any survivors who might have been trapped in submerged vehicles. Thereafter, its attention was directed to the recovery of the bodies of the victims, and then to the removal from the water, those portions of the bridge which had collapsed in the river with the ultimate purpose of opening the channel for river traffic.

Prior to the collapse, the U. S. Corps of Engineers had contractors working upstream on one of their projects and within hours after the collapse, they were able to move very heavy barge-mounted cranes onto the site. These contractors obtained a crew of divers who came in and assisted in the salvage operation.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hartley v. Crede
82 S.E.2d 672 (West Virginia Supreme Court, 1954)
Puffer v. Hub Cigar Store, Inc.
84 S.E.2d 145 (West Virginia Supreme Court, 1954)
State Ex Rel. Cox v. Sims
77 S.E.2d 151 (West Virginia Supreme Court, 1953)
McCoy v. Cohen
140 S.E.2d 427 (West Virginia Supreme Court, 1965)
Southern Ry. Co. v. Bell
114 F.2d 341 (Fourth Circuit, 1940)
Gerdes v. Booth & Flinn, Ltd.
151 A. 485 (Supreme Court of Pennsylvania, 1930)
Barbee v. Amory
146 S.E. 59 (West Virginia Supreme Court, 1928)
Fowlkes v. Southern Railway Co.
32 S.E. 464 (Supreme Court of Virginia, 1899)
Consumers' Brewing Co. v. Doyle's Administratrix
46 S.E. 390 (Supreme Court of Virginia, 1904)
Virginia Iron, Coal & Coke Co. v. Hughes' Administrator
88 S.E. 88 (Supreme Court of Virginia, 1916)
Washington & Old Dominion Railway v. Weakley
125 S.E. 672 (Court of Appeals of Virginia, 1924)
Cleveland v. Danville Traction & Power Co.
18 S.E.2d 913 (Supreme Court of Virginia, 1942)
Dennis v. Odend'Hal-Monks Corp.
28 S.E.2d 4 (Supreme Court of Virginia, 1943)
Anderson v. Baltimore & Ohio Railroad
81 S.E. 579 (West Virginia Supreme Court, 1914)
Donald v. Long Branch Coal Co.
103 S.E. 55 (West Virginia Supreme Court, 1920)
Hartley v. Crede
82 S.E.2d 672 (West Virginia Supreme Court, 1954)
Koehler v. Waukesha Milk Co.
208 N.W. 901 (Wisconsin Supreme Court, 1926)

Cite This Page — Counsel Stack

Bluebook (online)
11 Ct. Cl. 110, Counsel Stack Legal Research, https://law.counselstack.com/opinion/cantrell-v-department-of-highways-wvctcl-1976.