Cannelton Industries, Incorporated v. District 17, United Mine Workers Of America

951 F.2d 591
CourtCourt of Appeals for the Fourth Circuit
DecidedJanuary 7, 1992
Docket91-1535
StatusPublished
Cited by9 cases

This text of 951 F.2d 591 (Cannelton Industries, Incorporated v. District 17, United Mine Workers Of America) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fourth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Cannelton Industries, Incorporated v. District 17, United Mine Workers Of America, 951 F.2d 591 (4th Cir. 1992).

Opinion

951 F.2d 591

139 L.R.R.M. (BNA) 2001, 120 Lab.Cas. P 11,056

CANNELTON INDUSTRIES, INCORPORATED, a corporation, Plaintiff-Appellee,
v.
DISTRICT 17, UNITED MINE WORKERS OF AMERICA, Local Union
8843, United Mine Workers of America,
unincorporated associations,
Defendants-Appellants.

No. 91-1535.

United States Court of Appeals,
Fourth Circuit.

Argued Oct. 28, 1991.
Decided Dec. 6, 1991.
As Amended Jan. 7, 1992.

Charles F. Donnelly, Charleston, W.Va., argued (Kevin F. Fagan, on brief), for defendants-appellants.

Gene Webster Bailey, II, Jackson & Kelly, Charleston, W.Va., argued (Daniel L. Stickler, David D. Johnson, on brief), for plaintiff-appellee.

Before PHILLIPS and HAMILTON, Circuit Judges, and HEANEY, Senior Circuit Judge of the United States Court of Appeals for the Eighth Circuit, sitting by designation.

OPINION

PHILLIPS, Circuit Judge:

The United Mine Workers (the Union) and employees of Cannelton Industries appeal the judgment of the district court vacating an arbitration award which found appellee Cannelton in violation of the National Bituminous Coal Wage Agreement of 1988 (NBCWA) and ordered Cannelton to pay monetary damages to its aggrieved employees. The district court ruled that because the arbitrator failed to identify any cognizable loss suffered by the employees, the award was a purely punitive measure which is not authorized by the NBCWA. On appeal, we must determine the proper judicial response to an arbitration opinion that fails to expressly consider and resolve the determinative question presented to the arbitrator. Because we believe this type of critical ambiguity in the reasoning of an arbitration opinion requires clarification by the arbitrator, we vacate the district court's judgment and remand the cause with instructions.

* The dispute concerns Cannelton's use of outside contractors for renovations in its coal preparation plant. The union contends these jobs should have been performed by union employees in accordance with the NBCWA.

Cannelton's coal processing plant was built by outside contractors in 1952, and it was substantially rebuilt by outside contractors in 1966. At one time, the company employed its own construction crew, but the crew was abolished in 1982. In 1987, Cannelton hired an engineer from Bays, Inc., to evaluate the flooring system in the plant, and Cannelton contracted with Bays to construct "an entire new flooring system for the entire preparation plant." An outside contractor replaced the plant's magnetite floor in November and December of 1987.1 Cannelton maintained that this construction was merely the first phase of a complete reconstruction of the flooring system.

Cannelton employees filed Grievance No. 88017-88-1146 protesting the use of outside contractors for the 1987 floor work and arguing that hiring outside contractors violated sections (g)(2) and (i) of Article IA of the NBCWA. Section (g)(2) prohibits contracting out of "[r]epair and maintenance work of the type customarily performed by classified Employees at the mine or central shop." Section (i) provides:

All construction of mine or mine related facilities ... customarily performed by classified Employees of the Employer normally performing construction work in or about the mine in accordance with prior practice and custom, shall not be contracted out at any time unless all such Employees with necessary skills to perform the work are working no less than 5 days per week.

Article XXIII, section (c) of the NBCWA provides for the resolution of disputes through a four-step grievance procedure culminating in arbitration.

This dispute was submitted to Arbitrator I.M. Lieberman, who found that the 1987 floor work was not repair and maintenance work under (g)(2) but was construction work under section (i). However, Lieberman ruled that Cannelton had not violated section (i) because the work was not "customarily performed by classified employees of the mine" (The Lieberman Award). This decision is not itself in controversy.

Cannelton employees later filed Grievance No. 84-17-87-1057, challenging Cannelton's compliance with a 1978 voluntary grievance settlement that required Cannelton to give the union specific advance notice of its intention to hire outside contractors to perform work at the plant. In August of 1988, Arbitrator Martin M. Volz ruled that "prior to any contractor coming onto the property the company is to provide the Local Union with a 'New Project Form' or a written statement containing equivalent information regarding work being performed on the property by an outside contractor" (The Volz Award).

When Cannelton hired outside contractors to complete further work in the plant in late 1988 and early 1989, it submitted a New Project Information Form describing the work as "Removing Old Steel and Equipment from Prep Plant." On January 24, 1989, the union filed two grievances. Grievance No. 8843-989-017 complained of:

Contractors replacing flooring and removing old flooring also hand rails on operators floor. Replaceing [sic] walk way in front of the coal filter. This is work that is customarily done by Cannelton's employees. We are asking for the appropriate monetary remedy.

Grievance No. 8843-989-017 maintained:

Contractors removed tank and pipe lines in preparation plant. This is work that is customarily done by employees of Cannelton. We are asking for appropriate monarity remenedy [sic]. Also the co. is failing to notify the Union when Contractors are coming on the job.

These grievances were submitted to Arbitrator Patrick J. Basial, who found that Cannelton had not violated the NBCWA as alleged in Grievance No. 8843-989-020 because the removal of the tank and pipe lines was construction work of the type not customarily completed by union employees.

With respect to Grievance No. 8843-989-017, Basial ruled that Cannelton violated the terms of the Volz arbitration award by failing to submit a sufficiently specific project information form. Neither party disputes this portion of Basial's decision. Basial noted that he did not find it necessary "to reach and to resolve the underlying substantive issue as to whether this work was 'repair and maintenance work' or 'construction work.' " Therefore, he made no determination on the issue of whether using outside contractors for work on the floors and handrails2 violated Article IA, section (g)(2) or (i) of the NBCWA. Basial also refrained from deciding whether the Lieberman Award sanctioning outside contracts for the 1987 floor work was res judicata. However, opining that Cannelton's failure to give proper notice hindered labor relations and increased labor strife, Basial awarded the union money damages in an amount equal to 100 hours compensation under the labor contract. He determined that the work listed in both grievances required approximately 200 hours, and Basial estimated that the work on the flooring and hand rails was at least one-half of that total.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
951 F.2d 591, Counsel Stack Legal Research, https://law.counselstack.com/opinion/cannelton-industries-incorporated-v-district-17-united-mine-workers-of-ca4-1992.