Campbell v. George J. Igel & Co., Inc.

2013 Ohio 3584
Ohio Court of Appeals·Decided August 14, 2013·No. 13CA4·Published·Cited by 6 cases

Opinion

IN THE COURT OF APPEALS OF OHIO FOURTH APPELLATE DISTRICT HOCKING COUNTY

WILLIAM M. CAMPBELL, :

Plaintiff-Appellant, :

Case No. 13CA4

vs. :

DECISION AND

GEORGE J. IGEL & CO., INC., : JUDGMENT ENTRY

Defendant-Appellee. : RELEASED 08/14/2013

APPEARANCES:

Abigail M. Saving, Lilley & Saving Co., L.P.A., Logan, Ohio, for Plaintiff-Appellant.

Christopher J. Weber, Kegler, Brown, Hill & Ritter, LPA, Columbus, Ohio, for Defendant- Appellee.

Hoover, J.

{¶ 1} Plaintiff-appellant, William M. Campbell (“appellant”), appeals from the judgment of the Hocking County Court of Common Pleas that granted the motion for summary judgment of defendant-appellee, George J. Igel & Co., Inc. (“appellee”), as to the appellant’s claim for breach of contract. For the reasons set forth below, we reverse the judgment of the trial court and remand for further proceedings.

{¶ 2} Appellant raises two assignments of error for review.

First Assignment of Error:

THE TRIAL COURT ERRED AS A MATTER OF LAW WHEN IT GRANTED DEFENDANT’S MOTION FOR SUMMARY JUDGMENT.

Second Assignment of Error:

Hocking App. No. 13CA4 2

THE TRIAL COURT ERRED AS A MATTER OF LAW WHEN IT DENIED PLAINTIFF’S MOTION FOR SUMMARY JUDGMENT.

{¶ 3} The record reveals the following facts and procedural history. Appellant owns real

property at 19577 State Route 664, Logan, Ohio (the “Property”). In the summer of 2011, the Ohio Department of Transportation (“ODOT”) was preparing a construction project to realign State Route 664 adjacent to Old Man’s Cave State Park (the “Project”). On June 20, 2011, a representative of appellee, Jon Pulcheon, met with appellant to inform him that appellee intended to submit a bid on the Project. That same day, appellant and appellee executed a Construction Site Agreement (the “Agreement”). Mr. Pulcheon presented the Agreement, which appears to be a pre-printed form contract with certain additional handwritten terms, to appellant.

{¶ 4} Under the terms of the Agreement, appellant gave appellee “permission to establish a staging area [on the Property] for basing operations associated with the construction project including storage of materials, equipment and other pertinent items of work.” The Agreement also gave appellee “the right of ingress and egress to the [P]roperty in locations selected by the [appellee] for all purposes necessary to complete the fulfillment of this agreement.”

{¶ 5} In exchange for the permission to use the Property, appellee agreed to “place [an]

embankment [of] approx. 120,000 cy [cubic yards],” to “strip and replace topsoil,” to “grade and seed all disturbed areas,” to “provide positive drainage as needed,” and to “place aggregate up to the building site.” The Agreement also contains a provision labeled “Lump Sum Payment $50,000.00,” requiring appellee to pay appellant Twenty-Five Thousand Dollars ($25,000.00) “at start,” and Twenty-Five Thousand Dollars ($25,000.00) “upon completion and acceptance.”

Hocking App. No. 13CA4 3

{¶ 6} After the parties executed the Agreement, appellee submitted its bid to ODOT and was awarded the Project in July 2011. In January 2012, appellee notified appellant that it would not be using the Property to stage its operations on the Project or to dump fill dirt excavated from the Project site. Appellee then proceeded to dump fill dirt from the Project on property owned by the State of Ohio. The Property was never used, nor was it ever disturbed during appellee’s completion of the Project. Appellee never paid the Fifty Thousand Dollars ($50,000.00) to appellant.

{¶ 7} Appellant filed a complaint in the Hocking County Court of Common Pleas against appellee for breach of contract alleging damages of Fifty Thousand Dollars ($50,000.00), plus interest and costs. Appellee filed a motion for judgment on the pleadings. Appellant responded with a memorandum contra and a motion for summary judgment. The trial court converted appellee’s motion for judgment on the pleadings to a motion for summary judgment. The trial court ultimately entered judgment on January 4, 2013, overruling appellant’s motion for summary judgment and sustaining appellee’s motion for summary judgment. The trial court found, inter alia, that a “review of the language of the contract leads to the conclusion that the intent of the parties was that the $50,000.00 was not due until and unless the property was used.” Appellant timely appealed the judgment of the trial court.

{¶ 8} Because appellant’s two assignments of error are interrelated, we will address them together.

{¶ 9} Both assignments of error challenge the trial court’s rulings on the parties’ motions for summary judgment. We review the trial court’s decision on a motion for summary judgment de novo. Smith v. McBride, 130 Ohio St.3d 51, 2011-Ohio-4674, 955 N.E.2d 954, ¶ 12.

Hocking App. No. 13CA4 4

Accordingly, we afford no deference to the trial court’s decision and independently review the record and the inferences that can be drawn from it to determine whether summary judgment is appropriate. Harter v. Chillicothe Long-Term Care, Inc., 4th Dist. No. 11CA3277, 2012-Ohio- 2464, ¶ 12; Grimes v. Grimes, 4th Dist. No. 08CA35, 2009-Ohio-3126, ¶ 16.

{¶ 10} Summary judgment is appropriate only when the following have been established: (1) that there is no genuine issue as to any material fact; (2) that the moving party is entitled to judgment as a matter of law; and (3) that reasonable minds can come to only one conclusion, and that conclusion is adverse to the nonmoving party. Civ.R. 56(C); DIRECTV, Inc. v. Levin, 128 Ohio St.3d 68, 2010-Ohio-6279, 941 N.E.2d 1187, ¶ 15. In ruling on a motion for summary judgment, the court must construe the record and all inferences therefrom in the nonmoving party’s favor. Civ.R. 56(C). The party moving for summary judgment bears the initial burden to demonstrate that no genuine issues of material fact exist and that they are entitled to judgment in their favor as a matter of law. Dresher v. Burt, 75 Ohio St.3d 280, 293, 662 N.E.2d 264 (1996). Once that burden is met, the nonmoving party then has a reciprocal burden to set forth specific facts to show that there is a genuine issue for trial. Id.

{¶ 11} Furthermore, in order to succeed on a breach of contract claim, the plaintiff must demonstrate that: (1) a contract existed; (2) the plaintiff fulfilled his obligations; (3) the defendant breached his obligations; and (4) damages resulted from this breach. Chaney v. Ramsey, 4th Dist. No. 98CA614, 1999 WL 217656, *5 (Apr. 7, 1999), citing Doner v. Snapp, 98 Ohio App.3d 597, 600, 649 N.E.2d 42 (2nd Dist.1994). “ ‘[B]reach,’ as applied to contracts is defined as a failure without legal excuse to perform any promise which forms a whole or part of a contract, including the refusal of a party to recognize the existence of the contract or the doing of something inconsistent with its existence.” Natl. City Bank of Cleveland v. Erskine & Sons,

Hocking App. No. 13CA4 5

Inc., 158 Ohio St. 450, 110 N.E.2d 598 (1953), paragraph one of the syllabus. “ ‘When the facts presented are undisputed, whether they constitute a performance or a breach of a written contract, is a question of law for the court.’ ” Koon v. Hoskins, 4th Dist. No. 95CA497, 1996 WL 30018, *7 (Jan. 24, 1996), fn. 5, quoting Luntz v. Stern, 135 Ohio St. 225, 20 N.E.2d 241 (1939), paragraph five of the syllabus.

{¶ 12} Here, both parties agree that the Agreement is clear and unambiguous. It is further undisputed that appellee did not utilize appellant’s land in the performance of its Project duties despite appellant having made the Property available for use. Thus, whether appellant may enforce the payment obligation (“Lump Sum Payment” provision) through this breach of contract action rests upon a determination of whether, as a matter of law, the language of the Agreement contained a condition precedent to performance, or alternatively, a mutual exchange of promises.1

Free access — add to your briefcase to read the full text and ask questions with AI

Campbell v. George J. Igel & Co., Inc., 2013 Ohio 3584 (Ohio Ct. App. 2013).

2013 Ohio 3584 (Campbell v. George J. Igel & Co., Inc.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Eagle Realty Invests., Inc. v. Dumon
2022 Ohio 4106 (Ohio Court of Appeals, 2022)
Retirement Corp. of Am. v. Henning
2019 Ohio 4589 (Ohio Court of Appeals, 2019)
Grigoryan v. MaxOut Sports, L.L.C.
2017 Ohio 6982 (Ohio Court of Appeals, 2017)
Marine Max of Ohio, Inc. v. Moore
2016 Ohio 3202 (Ohio Court of Appeals, 2016)
Meeker R&D, Inc. v. Evenflo Co., Inc
2016 Ohio 2688 (Ohio Court of Appeals, 2016)
Westlake v. VWS, Inc.
2014 Ohio 1833 (Ohio Court of Appeals, 2014)