Campbell v. Evens & Howard Sewer Pipe Co.

286 S.W.2d 399, 1956 Mo. App. LEXIS 24
CourtMissouri Court of Appeals
DecidedJanuary 17, 1956
DocketNo. 29295
StatusPublished
Cited by4 cases

This text of 286 S.W.2d 399 (Campbell v. Evens & Howard Sewer Pipe Co.) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Campbell v. Evens & Howard Sewer Pipe Co., 286 S.W.2d 399, 1956 Mo. App. LEXIS 24 (Mo. Ct. App. 1956).

Opinion

HOUSER, Commissioner.

This is an action by Neal J. Campbell, a professional architect, to recover the reasonable value of services rendered by him in engineering, planning, drafting plans and specifications and procuring bids and estimates for the erection and construction of a dryer building for a sewer pipe company. A trial jury awarded plaintiff $6,500 but the trial judge set aside the verdict and judgment and granted a new trial. Plaintiff has appealed from that order.

The first question is whether the trial judge committed error in granting a new trial “on the ground that the court erred in refusing Defendant’s Instruction A.” That instruction directed a verdict for defendant upon- a finding that it employed plaintiff to draw plans for a dryer building the construction of which would not cost over $200,000 but that, constructed according to plaintiff’s plans, the building would have cost substantially more than $200,000. This instruction, embodies the well established rule that where an architect is employed to prepare plans for a building to .cost not more than a certain sum the architect is not entitled to compensation unless the building can be constructed for the stipulated amount. Hellmuth v. Benoist, 144 Mo.App. 695, 129 S.W. 257; Kurfiss v. Martin, 130 Mo.App. 469, 110 S.W. 32; Hudson v. Rodgers, 121 Mo.App. 168, 98 S.W. 778; Cann v. Rector, Wardens & Vestrymen of Church of Redeemer, 111 Mo.App. 164, 85 S.W. 994; Maack v. Schneider, 57 Mo.App. 431; 6 C.J.S., Architects, § 14b, p. 310; 5 C.J., Architects, § 13, p. 262; 3 Am.Jur., Architects, § 15; Annotation 127 A.L.R. 410 et seq. Appellant claims that Instruction ‘A was properly refused because it was not supported by any evidence; that the giving of the instruction would have constituted reversible error.

The following facts were undisputed: Defendant company desired to convert from the traditional gravity flow system of drying freshly molded clay pipe to a new system of drying by forced air. Ultimately eight new dryer building units would be required. Plaintiff was commissioned by Oscar E. Buder, defendant’s duly authorized president, to draw plans for a two-unit dryer building. The contract was oral and informal. There was-no discussion of fees. Plaintiff and his associates prepared a set of plans and specifications which, from the standpoint of engineering, design and practicality for the intended use, were satisfactory to defendant. The estimated cost of construction of a building housing two dryer units, according to plaintiff’s plans and specifications, was $190,000. Upon learning of the cost estimate defendant abandoned the undertaking and did not use plaintiff’s plans.

The lack of agreement on the facts, indeed, the fact issue upon which the testimony of the parties was in diametric opposition, related to the question whether the contract included a limitation on the cost of the building. Plaintiff testified that Mr. Buder did not place any limit as to the ultimate cost of construction of the project he was employed to engineer and design, or indicate the amount of money defendant had available to spend on the proposed dry[401]*401er buildings; that at no time during any of the conversations with Mr. Buder did the latter tell him that the company had placed a limit of $200,000 on the project. In direct contradiction Mr. Buder testified that during his initial conversation with plaintiff in connection with this transaction he told plaintiff that he was allowing $200,000 for four dryers; that plaintiff knew defendant’s requirements and was told that defendant wanted the best, most economical and efficient plant possible, “provided it could be built within the $200,000, which was my limitation. * * * I told him $200,000 for four buildings * * On cross-examination Mr. Buder testified as follows:

“Q. * * * You told him then that you wanted ⅛⅞ four dryer buildings built at a cost not to exceed $200,000? A. Absolutely.
“Q. That’s right?. A. Yes.”

On redirect examination this appears:

“Q. Mr. Buder, at this first conference after you had shown Mr. Campbell this sketch and, as you have testified, told him of the limitation of funds available, what instructions did you then give him concerning the work that he was to do ? * * *. A. Well, I told him to go ahead and prepare the dryers for us in keeping with this limitation of $200,000.”

From this recital it is plain to see that there was substantial record evidence of the fixing of a cost limitation amply sufficient to support the giving of Instruction A.

. Appellant contends, however, that defendant was not entitled to Instruction A for the reason that it presented a theory of defense which had been abandoned and which is wholly inconsistent with the theory on which the case was tried. The philosophy of Instruction A is one -of complete exoneration ; that plaintiff was bound to perform the contract as made and if his plans and specifications did not come within its terms he was not entitled to recover; that, as expressed in Maack v. Schneider, supra, 57 Mo.App. loc. cit. 432, “ * * * one. who buys one thing is not thereby bound to pay for another and different thing, * * Appellant argues that defendant did not try the case on the theory that it was entitled to be completely relieved of all liability but on the theory that, while it owed plaintiff something, its liability should be restricted to the reasonable value of plaintiff’s services up to the time his investigation revealed that the building could not be constructed within the price limitation, upon the determination of which plaintiff should communicate that information to defendant and proceed further only if permitted to do so. Appellant points to the testimony of the president of the company, Mr. Buder, who, when asked on cross-examination if he took the position that plaintiff should not be paid for his services, said: “We don’t take that position. We want to pay him the reasonable value of his services.” The entire record in this connection follows:

“Q. Do you take the position, Mr. Buder¡ that Mr. Campbell is not entitled to payment for his services?
* * * ⅝ * . ‘ *
“A. I don’t take that position, although you asked me at that time a matter of law and I told you as a matter of law I didn’t think he was entitled to . anything.
“Q. I asked you whether or not you take the position he is not entitled to payment for his services? A. We don’t take that position. We want to pay him the reasonable value of his services.”

Appellant also emphasizes the statement made by counsel for defendant at the time defendant offered to prove what the company did with respect to the construction of dryer buildings after terminating its relations with plaintiff, as follows:

“My theory is that the Campbell assignment was either to design it so it could be built, or if by investigation he found he couldn’t then to drop it; that it was impossible to spend more for [402]*402building, therefore, if he had informed Mr. Buder earlier he would have paid him for his services investigating, what was done, and either drop the project and find another designer, or build one of the old type buildings, or something else; but, instead of doing that, he went on and didn’t inform us. Therefore, it is relevant to the case to show that it was important that Mr. Buder be informed, because there were other persons he could obtain.”

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Stanley Consultants, Inc. v. H. Kalicak Const. Co.
383 F. Supp. 315 (E.D. Missouri, 1974)
Carvitto v. Ryle
495 S.W.2d 109 (Missouri Court of Appeals, 1973)
Scott v. Nash
355 S.W.2d 626 (Missouri Court of Appeals, 1962)

Cite This Page — Counsel Stack

Bluebook (online)
286 S.W.2d 399, 1956 Mo. App. LEXIS 24, Counsel Stack Legal Research, https://law.counselstack.com/opinion/campbell-v-evens-howard-sewer-pipe-co-moctapp-1956.