Campbell v. Davidson-Martin Manufacturing Co.

85 N.W. 1093, 126 Mich. 468, 1901 Mich. LEXIS 759
CourtMichigan Supreme Court
DecidedMay 7, 1901
StatusPublished
Cited by1 cases

This text of 85 N.W. 1093 (Campbell v. Davidson-Martin Manufacturing Co.) is published on Counsel Stack Legal Research, covering Michigan Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Campbell v. Davidson-Martin Manufacturing Co., 85 N.W. 1093, 126 Mich. 468, 1901 Mich. LEXIS 759 (Mich. 1901).

Opinion

Moore, J.

The plaintiff recovered a judgment against the defendant for $1,210. The defendant has brought the case here by writ of error. I cannot state the questions involved in the case better than to quote from the language of the trial judge, the late Judge Vance, in his* charge to the .jury, which is as follows:

“The plaintiff claims that on or about April 6, 1894, the defendant, through its president, A. S. Martin, gave the plaintiff an order to manufacture for it twelve 15-inch Wizard purifiers of whitewood; that the defendant gave plaintiff about the same time an order to manufacture five small machines for agents’ samples; that no written contract or specifications were made, but that plaintiff had a model machine to work from on these orders, furnished by the defendant; that plaintiff made the above machines, and finished these orders some time in June, 1894.
“That during the month of April, 1894, or early in May, 1894, meetings of the directors of the defendant [469]*469company were held, and the matter of using elm in the manufacture of these machines was talked over, and that •at one or more of these meetings plaintiff was present; that one Webster advocated the use of elm at one of these meetings, and that the defendant ordered plaintiff to make a 24-inch elm machine; that plaintiff began work on this machine prior to May 14, 1894, and that said machine was set up by Charles Keyes, and was completed, or nearly completed, so far as the woodwork was concerned, on May 25, 1894, and that at that date it stood on the second floor of plaintiff’s factory. This is the high 24-inch machine spoken of in plaintiff’s declaration. The officers and directors of defendant saw this machine, and approved it, prior to May 25, 1894. That on May 25, 1894, Abram S. Martin, the president of the defendant company, came to plaintiff’s office, and gave plaintiff an order for fifty 15-inch, forty 24-inch, and ten 30-inch elm machines; and one Wallace was present. They all ■examined the 24-inch sample machine then on the floor of the factory. The new machines to be manufactured under the order were to be like the 24-inch sample in timber and workmanship, but the new 24-inch machines were to be about four inches lower. That the plaintiff immediately caused the order to be entered in his book, and proceeded to purchase elm lumber, as he did not have enough in his factory to fill the order. He at once proceeded to cut up lumber for the order, as A. S. Martin .had said to him the defendant was in a hurry for the machines.
“That on June 6, 1894, the board of directors of the ■defendant company held a meeting, at which plaintiff was present, and an attempt was made to embody in writing, specifications and in a written contract, the agreement made with the president, A. S. Martin, on May 25, 1894. This attempt failed for the reason that plaintiff objected to some of the details of specifications as too stringent. That at this time the officers and directors present ratified the contract entered into with the president, Abram S. Martin, on May- 25, 1894, and supplemented it with the further provision that plaintiff should ■complete one 24-inch machine of the lower design, being ■one of the order of May 25, 1894, which was well under way on June 6, 1894, and that this machine should stand on the floor of plaintiff’s factory as a model as to finish •and minor details, but that plaintiff should finish work on [470]*470the whole order as he had done between May 35, 1894, and June 6, 1894.
“The plaintiff claims that after May 35, 1894, and after he had begun work on the order of that date, the different officers and directors of the defendant were constantly coming to the factory and watching the progress-of the work on the order; that David J. Davidson personally supervised the work, and was there once or more every day; that other officers and directors gave orders about the work, and that on June 6, 1894, they were all aware of the work he had been doing on this order; that plaintiff proceeded with the work during the months of June and July, 1894, and that it was-supervised and overlooked nearly every day by the officers and directors of the defendant; that defendant agreed to furnish ironwork, as plaintiff did not want to furnish money, and wait for them to take the machines, and the defendant did furnish ironwork for three machines; that on July 19, 1894, the defendant accepted two 34-inch elm machines, one of which went to Davison, Michigan, and one to McMorran’s mill, in this city; that on August 34th the defendant accepted a 15-inch elm machine, shipped to Metzgar, at Waterfield, Ohio.
“That on or about August 34, 1894, the defendant repudiated this contract with plaintiff, through its president, Abram S. Martin, and ordered plaintiff to cease making machines under the order, as they had found elm to be unsuitable, and would tako no more machines; that on February 19, 1895, the defendant paid $93.03 on this account of machines which plaintiff had in progress of manufacture at his factory, by allowing him to take a lot of lumber which was worth this amount; that negotiations, have been had at different times for a settlement of the claim sued upon. On April 35, 1895, the plaintiff attended a meeting of the directors of the defendant, and they then and there directed him to furnish them with a. list of the machines in progress of manufacture at his factory, and that the defendant would furnish irons, and have him complete the machines, and take and pay for them under the contract. That plaintiff furnished such lists, but defendant never furnished irons as it had agreed to do, and he claims to recover upon that theory of the case.
“The defendant claims as its theory of the case as follows : That it never made any such contract as is claimed [471]*471by the plaintiff; that, about the 28th day of May, defendant’s president, A. S. Martin, went to plaintiff’s mill to obtain prices from plaintiff of what he would manufacture whitewood purifiers of different sizes for; that said Martin obtained plaintiff’s prices on the basis of an order for 100 whitewood machines; that it was understood at that time by Mr. Campbell and Mr. Martin and Mr.' Chadwick, who were present, that a written contract', with complete specifications, was to be prepared, agreed to, and signed by the parties, before there would be any contract between them; that the terms and conditions of said contract would have to be approved by the board of directors of the defendant company; and that Mr. Chadwick was then and there requested to proceed with the preparation of the contract and specifications; that said contract and specifications were prepared in writing, and a meeting of the board of directors called on or about the 1st of June, 1894, at which Mr. Campbell was present; that the object and purpose of the meeting was to see-if a satisfactory contract could be made with Mr. Campbell for the manufacture of whitewood machines on the line of the prices obtained from him; that defendant did not desire to bind itself to take 100 machines in any one order, but desired the right to elect to take a less number; that the parties failed to agree upon the terms of the contract and specifications for the building of whitewood machines, and Mr.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Ebert v. Cullen
130 N.W. 185 (Michigan Supreme Court, 1911)

Cite This Page — Counsel Stack

Bluebook (online)
85 N.W. 1093, 126 Mich. 468, 1901 Mich. LEXIS 759, Counsel Stack Legal Research, https://law.counselstack.com/opinion/campbell-v-davidson-martin-manufacturing-co-mich-1901.