Campbell v. Buller

32 Mo. App. 646, 1888 Mo. App. LEXIS 427
CourtMissouri Court of Appeals
DecidedDecember 20, 1888
StatusPublished

This text of 32 Mo. App. 646 (Campbell v. Buller) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Campbell v. Buller, 32 Mo. App. 646, 1888 Mo. App. LEXIS 427 (Mo. Ct. App. 1888).

Opinion

Ramsay, J.

— Plaintiff’s petition is in words and figures following : “ Plaintiffs state that on the twenty-seventh day of November, 1885, plaintiffs were partners doing business under the firm name and style of H. E. Campbell & Co. and that on said day they sold and delivered to the defendant one number two, ten foot windmill and tower complete at the price of one hundred dollars ; one force pump air chamber threeway, cock and brass cylinder for twenty-five dollars; one reservoir tank, round, size six feet bottom, four feet square, at twenty dollars, and twenty feet well pipe and rods at twenty-five cents per foot, aggregating the sum of one hundred and fifty dollars, for which defendant, by his agreement in writing herewith filed, promised, when said mill was up and in good running order, to execute to plaintiffs by their said firm name his promissory note for the said sum of one hundred and fifty dollars, payable to plaintiffs, said firm due December 1, 1886, with eight per cent, interest payable annually; that said mill was put up and in good running order on the third day of December, 1885, and the execution and delivery of said note was demanded of defendant and refused, and defendant has ever since refused and still refuses to execute said note, and has refused and still refuses to pay said sum; that by the terms of ssid agreement it was provided that in case defendant failed to execute said note then the said sum shall then and on said failure be due ; that plaintiffs have fully performed their part of said agreement and the said sum is now due and remains wholly unpaid. Wherefore they ask judgment against defendant for the sum of one hundred and fifty dollars, with eight per cent, interest thereon from the third day of December, 1885, and for costs.” The defendant’s answer is in the following words, omitting caption and signature: £ 1 Further answering defendant says that the said windmill was expressly warranted to be well made and of good materials, and to do good work, and that plaintiffs agreed that if any part thereof proved defective within one year they would replace it upon [651]*651notice, and that the said windmill was not well put up, but on the contrary was not set perpendicularly above the pump, in consequence of which it never worked properly, and in addition to that the pump was worthless and constantly out of repair and broken, so as to be useless to defendant, and the plaintiffs wholly failed and neglected and refused to replace it, though often requested, to defendant’s damage in the sum of one hundred and fifty dollars, for which he asks judgment against plaintiffs.” Plaintiffs, replication consisted of a general denial. At the trial plaintiffs read in evidence the contract, declared on, which was as follows : “Messrs. H. E. Campbell & Co. Please ship to me on or before December 3, 1885, at your earliest convenience, to Carthage, via Missouri Pacific Railroad, the following list of articles and erect same as soon as you can at prices opposite each: 1 No. 2 10-foot windmill and tower complete, $100.00; 1 force pump air chamber 3 and brass cylinders, $25.00 ; 1 reservoir tank, round, 6 ft. bottom, 4 ft. stave. $20.00 ; 20 feet well pipe and rods, 25c. per foot, am’t used, $5.00; Total, $150.00. When the windmill is up and in good running order, I will pay H. E. Campbell & Go., or order, my note for $150.00 due on or before December 1, 1886, payable at the Bank of Carthage, Carthage, Mo., interest eight per cent., payable annually from its erection, failure to execute notes as above agreed makes whole amount due. I agree to assist machanics and board him or them while putting up work, do all digging, and I am to furnish four anchor posts and plank for well platform ; reserving, however, the benefit of the warranty hereon endorsed. R. F. Buller.” “Warranty: This windmill is warranted for one year from its erection against winds that do not unroof buildings, and any piece of the windmill proving defective during said year will be shipped to buyer free of charge by giving us notice. Failure to take proper care of said windmill renders above warranty null and void. H. E. Campbell & Co.” Also offered evidence tending to show that they put up the [652]*652windmill and pump according to the contract and left it in running order ; that a short time afterwards they were notified by defendant that it would not work and they went out and found the supply-pipe was frozen up and had bursted ; that they took out the damaged part and put in a new piece ; that some time after that they were again notified, they found the bottom of the pump broken off: and repaired it; also that plaintiffs had several times requested defendant to give plaintiffs his note, but that he refused on the ground that the pump was defective and had never worked properly. The defendant introduced evidence tending to show that the pump was so badly put up and so defective in construction that it never had worked properly ; that on two occasions notice had been given to plaintiffs’ and though plaintiffs repaired it, it soon failed and defendant was deprived of its use and expended money to get it repaired ; that it still failing to work, defendant requested plaintiffs to take it away. Also introduced evidence tending to show that a windmill pump was not properly put up unless the supply-pipe was below the frost-line, that the pipe in the one in suit had frozen, etc. Plaintiffs in rebuttal offered evidence tending to show that the supply-pipe of the pump was placed too near the surface of the ground owing to the refusal of one George Meredith, who was a servant of defendant, to dig the trenches deep enough; that plaintiffs requested said Meredith to dig the trench deeper, which he refused to do, and that the reason the pump did not work during the winter was because the supply-pipe was not placed deep enough in the ground to prevent freezing.

For plaintiffs the court instructed:

“1. The court instructs the jury that if they find from the evidence that plaintiffs composing the firm of H. E. Campbell & Co., sold and delivered to the defendant the windmill and force pump and other articles mentioned in plaintiffs’ petition under the written contract read in evidence, and placed the said mill and pump on the farm of defendant, and the same were put up in [653]*653good running order, then by the terms of said contract defendant agreed to execute his note to plaintiffs for the sum of one hundred and fifty dollars, payable December, 1886, with interest at eight per cent, per annum; and if you find from the evidence that plaintiffs complied with said contract on their part, and that defendant neglected or refused to execute said note on his part, the jury should find the issues for the plaintiffs and assess their damages at the sum of one hundred and fifty dollars, together with interest at eight per cent", from the time said mill and pump were put up in good running order by plaintiffs.

2. The court instructs the jury that if the windmill and pump were put up in good running order by plaintiffs on defendant’s farm, and after being so put tip defendant failed and neglected to use proper care in looking after such windmill and pump, then plaintiffs are not responsible for any failure of the pump or windmill to work, occasioned by such failure or negligence by defendant.

“3.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Meechum v. Judy
4 Mo. 361 (Supreme Court of Missouri, 1836)
Culbertson v. Hill
87 Mo. 553 (Supreme Court of Missouri, 1885)

Cite This Page — Counsel Stack

Bluebook (online)
32 Mo. App. 646, 1888 Mo. App. LEXIS 427, Counsel Stack Legal Research, https://law.counselstack.com/opinion/campbell-v-buller-moctapp-1888.