Camosy, Inc. v. River Steel, Inc.

624 N.E.2d 894, 253 Ill. App. 3d 670, 191 Ill. Dec. 706, 1993 Ill. App. LEXIS 1805
CourtAppellate Court of Illinois
DecidedDecember 9, 1993
Docket2-92-1445
StatusPublished
Cited by4 cases

This text of 624 N.E.2d 894 (Camosy, Inc. v. River Steel, Inc.) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Camosy, Inc. v. River Steel, Inc., 624 N.E.2d 894, 253 Ill. App. 3d 670, 191 Ill. Dec. 706, 1993 Ill. App. LEXIS 1805 (Ill. Ct. App. 1993).

Opinion

JUSTICE COLWELL

delivered the opinion of the court:

Plaintiff, Camosy, Inc., appeals from the judgment of the circuit court granting a directed finding in favor of defendant, River Steel, Inc. Plaintiff, a general contractor, had filed a one-count complaint based upon promissory estoppel, alleging injury resulting from its reliance upon defendant’s bid proposal for a construction project. Plaintiff contends that the trial court erred in directing a finding in favor of defendant at the close of plaintiff’s case because plaintiff’s prima facie case under the doctrine of promissory estoppel was supported by a preponderance of the evidence. We affirm.

Plaintiff is a general contractor that prepared a bid for general contracting services at the Grayslake Junior High School project. Defendant is a structural steel subcontractor based in Wisconsin and doing business in Lake County, Illinois.

The deadline for submitting proposals to the school district was 3 p.m. on January 9, 1991. At approximately 2:19 p.m., plaintiff received a written proposal from defendant. The proposal stated in part:

“[W]e propose to furnish materials and labor at the prices and terms as stipulated below:
Furnish and erect per plans & specs: No addendums.”

There followed a listing of tonnage for the structural metal framing and metal fabrications involved in defendant’s proposal and a total price figure of $94,500.

On the same page of the proposal, the following was stated:

“EXCLUDE: Drawings under supervision of professional registered Engineer, Rough hardware for other trades, Aluminum expansion joint covers, Stainless steel table tops/legs, Grouting, Touch-up paint, Metal access panels, Abrasive stair inserts, Ladder, 05510 (metal stairs) 05521 (pipe & tubing) Railings, Cutting & welding of steel for P.C., Erection, Demolition.”

Plaintiff evidently received 13 other bids from subcontractors. One of them excluded the erection of the structural steel, although it did include, unlike defendant’s proposal, the supply and the erection of the stairs, ladders, and railings. The amount of this bid was $82,836. The remaining proposals included both the fabrication and the erection of the structural steel, as well as the supply and the erection of the stairs, ladders, and railings. These bids ranged from $147,421 to $236,000, with an average bid amount of $176,619.39.

At approximately 2:25 p.m. on January 9, 1991, Richard Grabowski, the chief estimator for Camosy, Inc., called River Steel, Inc., and spoke with Ron Mussa, an estimator employed by River Steel, Inc. Grabowski informed Mussa that defendant’s proposal did not acknowledge addenda to the project’s specifications and that its price was “way low.” The two men also confirmed defendant’s exclusion of the steel for the stairs, ladders, and railings. They did not discuss whether defendant’s proposal included the erection of the structural steel. After reviewing the addenda, Mussa telephoned Grabowski and told him that the addenda did not affect defendant’s price.

Plaintiff used defendant’s bid in conjunction with another company’s proposal to fabricate and install the steel stairs, railings, and ladders for a price of $11,900 in the preparation of plaintiff’s proposal to the school district. Shortly after 3 p.m. on January 9, 1991, the bids were opened in a public meeting, and plaintiff was determined to be the low, responsive bidder for the project. On or about January 14, 1991, plaintiff was awarded a contract in the sum of $2,515,300 for the project.

On approximately January 23, 1991, Grabowski telephoned Mussa and informed him that plaintiff had been awarded a contract and had “utilized a number of $94,500.” At this time Grabowski desired to have one subcontractor do all of the structural steel work, and he asked Mussa to put together pricing for the steel stairs, ladders, and railings. Mussa said that he would get back to Grabowski.

Grabowski called River Steel, Inc., early in February and was told by Mussa that he would have to speak with the office manager, Roger Wilinski. Wilinski stated that the price including stairs, ladders, and railings would be approximately $113,000. Grabowski responded that Wilinski could “purchase” this work for around $104,000 or $106,000. Wilinski said that he would have to get back to Grabowski.

On February 3 or 4, 1991, Grabowski called Wilinski and Wilinski stated that defendant did not accept plaintiff’s offer. According to Grabowski’s testimony, Wilinski also stated that defendant had made a mistake in the original proposal in that it had left out the cost of erection of the structural steel.

Following this conversation, Grabowski sent defendant a letter of intent, dated February 4, 1991, to award defendant a subcontract per defendant’s January 9 proposal. On or about February 6, 1991, Wilinski telefaxed to plaintiff a copy of the intent letter with a handwritten note by Wilinski stating “we reject this job as proposed, see ltr Feb.4.91 herewith.” The reference was to a letter to Wilinski from Timothy Brennan, the president of River Steel, Inc., stating:

“After discussing the Grayslake Jr. High School project, and reviewing the file on that project, I have to concur that there was an error in bidding that project. We made a mistake and bid the job installed, but did not add in the erection price.
Please relate this mistake to the contractor, as we cannot perform the job as proposed. The erection would add $52,500.00 to the proposal. The proposal price should be $147,000.00, without the inclusion of $13,190.00 [for the stairs, ladders, and railings], $160,900.00 with the inclusion.”

On February 8, 1991, defendant’s counsel notified plaintiff by telefax that defendant had “inadvertently omitted” the erection costs from its bid, and on February 12,1991, defendant rescinded its bid.

On March 25, 1991, plaintiff filed a one-count complaint against defendant. Although the complaint does not mention promissory estoppel, plaintiff states in its motion for summary judgment on defendant’s affirmative defenses that the complaint as filed was based upon promissory estoppel. A bench trial was conducted on August 10, 1992, at which plaintiff presented the testimony of Richard Grabowski, various exhibits, and the evidence deposition of Ron Mussa. At the close of plaintiff’s case, defendant moved for a directed finding, which the trial court granted in favor of defendant.

On September 4, 1992, plaintiff filed a motion for reconsideration, and the trial court heard oral arguments on the motion on November 9, 1992. The trial court held that plaintiff had presented a prima facie case for promissory estoppel but, after weighing the evidence, found, inter alia, that “there is an ambiguity as far as the term erection” is concerned. The court then reaffirmed its granting of defendant’s motion for a directed finding. Plaintiff appeals both the August 10,1992, and the November 9, 1992, rulings.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Pickus Construction & Equipment v. American Overhead Door
761 N.E.2d 356 (Appellate Court of Illinois, 2001)
Straka v. Francis
867 F. Supp. 767 (N.D. Illinois, 1994)
Jeffrey M. Goldberg v. Collins Tuttle
637 N.E.2d 1103 (Appellate Court of Illinois, 1994)

Cite This Page — Counsel Stack

Bluebook (online)
624 N.E.2d 894, 253 Ill. App. 3d 670, 191 Ill. Dec. 706, 1993 Ill. App. LEXIS 1805, Counsel Stack Legal Research, https://law.counselstack.com/opinion/camosy-inc-v-river-steel-inc-illappct-1993.