Camo Construction Co., Inc. v. Town of Vidalia
Opinion
STATE OF LOUISIANA COURT OF APPEAL, THIRD CIRCUIT
07-354
CAMO CONSTRUCTION CO., INC.
VERSUS
TOWN OF VIDALIA
**********
APPEAL FROM THE SEVENTH JUDICIAL DISTRICT COURT PARISH OF CONCORDIA, NO. 39589 HONORABLE LEO BOOTHE, DISTRICT JUDGE
ULYSSES GENE THIBODEAUX CHIEF JUDGE
Court composed of Ulysses Gene Thibodeaux, Chief Judge, Marc T. Amy, and Michael G. Sullivan, Judges.
AFFIRMED.
Ronald J. Fiorenza Provosty, Sadler, deLaunay, Fiorenza & Sobel P. O. Drawer 1791 Alexandria, LA 71309-1791 Telephone: (318) 445-3631 COUNSEL FOR: Defendant/Appellee - Town of Vidalia
Richard Brooks Easterling 450 Laurel Street - Suite 1900 Baton Rouge, LA 70801 Telephone: (225) 336-5200 COUNSEL FOR: Plaintiff/Appellant - CAMO Construction Co., Inc. THIBODEAUX, Chief Judge.
This case involves a contract dispute between the plaintiff-appellant,
CAMO Construction Company, Inc., (CAMO) and the defendant-appellee, the Town
of Vidalia (Town). In January of 2001, CAMO was awarded the contract for a street
improvement and drainage project in Vidalia, Louisiana which called for completion
in 270 days. The project was plagued with delays from the beginning and after two
extensions of time was still not complete. The Certificate of Substantial Completion
was issued 1007 days after the start date on the contract.
During construction, CAMO instituted a claim for extended overhead
and delay damages of $221,634.04, later reduced to $141,681.59. At the end of the
project, the Town rejected the claim and deducted $80,000.00 from CAMO’s last
payment as liquidated damages for 160 of the days that CAMO went beyond the last
approved extension date on the contract.
CAMO filed suit for breach of contract in April 2004 seeking to recover
the liquidated damages and the funds claimed for overhead and delay damages. After
a bench trial, the trial court found in favor of the Town and dismissed all of CAMO’s
claims. CAMO filed this appeal. For the reasons set forth below, we affirm the
judgment of the trial court.
I.
ISSUES
We must decide:
(1) whether the trial court erred in finding that CAMO Construction Company, Inc. was not entitled to additional payments for delays and extended overhead on the construction project for the Town of Vidalia; and (2) whether the trial court erred in finding that the Town was entitled to deduct from CAMO’s final payment liquidated damages for 160 days at $500.00 per day.
II.
FACTS AND PROCEDURAL HISTORY
In early January of 2001, the Town invited bids on a construction project
entitled, “Town of Vidalia 1999 Street Improvement Program, Phase II-Subsurface
Drainage.” The Town estimated that the project would require funds of
$2,445,016.00 and that the construction would take 270 days. CAMO Construction
submitted the lowest overall bid, at $2,165,976.50 and was awarded the contract. In
general, the project called for the installation of catch basins and various sizes of PVC
pipe in open ditches, and then required covering the installations with dirt and sod,
called “dressing up.” The new installations were tied into, and sometimes replaced,
existing subsurface drainage systems, at times requiring the breaking up and repair
of private driveways.
The contract documents called for “unit price” bids, not cost plus bids,
or price per hour bids. The bid forms were pre-printed with the description of each
item, the estimated quantity of that item needed for the project, and the measurement
unit for that item (linear foot, square yard, cubic yard, etc.). Blanks were provided
at the end of each line item for the contractor to write in his “unit price” bid and his
“total price” bid for that item. The contractors “unit price” bid was his price for each
item installed, that is, after installation. Therefore the “unit price” bid for each item
specifically included the cost of the material, the labor, the contractor’s overhead,
profit, taxes, insurance, bond premiums, equipment rentals, and any other contractor
costs associated with the installation.
2 For example, in one instance, 3,670 linear feet of fifteen-inch (15") inch
pipe, was bid by CAMO at $17.88 per linear foot installed. Although not shown on
the bid form, the purchase price (or unit rate) for this pipe was $5.60 per linear foot
at one time during the project. The $17.88 per unit bid by CAMO is called the “unit
price” and is then multiplied times the 3,670 linear feet indicated on the bid form, for
a “total price” bid of $65,619.60 for that item (15" pipe). The original bid form
contained eighteen (18) line items which included five sizes of corrugated PVC pipe,
catch basins, inline drains, driveway repair, asphalt street repair, sand/clay/gravel, and
other materials. Item 17 was a “utility relocation” lump sum cash allowance pre-set
on the bid form at $2,000.00. Item 18 asked for a lump sum bid for “mobilization.”
The pre-printed quantities on the bid form were estimates only. CAMO would be
paid for actual quantities installed based upon its “unit price” bid for each item.
Page two (2) of the bid packet signed by CAMO contained the following
language:
The Bidder, in compliance with your Advertisement for Bids . . . having examined the plans and specifications with related documents and the site of the proposed work, and being familiar with all of the conditions surrounding the construction of the proposed project including the availability of materials and labor, hereby proposes to furnish all labor, materials, and supplies, and to construct the project in accordance with the contract documents within the time set forth therein and at the prices stated below. These prices are to cover all expenses incurred in performing the work required under the contract documents, of which this proposal is a part.
....
BIDDER hereby agrees to commence WORK under this contract on or before a date to be specified in the written NOTICE TO PROCEED and to fully complete the PROJECT with[in] 270 consecutive calendar days thereafter. BIDDER further agrees to pay as liquidated damages, the sum of $500.00 for each consecutive calendar
3 day thereafter as provided in Section 9 of the Information for Bidders.
Bryant Hammett and Associates, the engineering firm, was responsible
for plan designs and drawings, materials lists, bid and contract documents and
specifications, and supervision and administration of the project. The only two
signatories on the two-page contract document setting forth the price, the completion
time, and the amount for liquidated damages, were the CONTRACTOR (CAMO
Construction) and the OWNER (Town of Vidalia through its Mayor, Hyram
Copeland).
The notice to proceed was issued on January 31, 2001, and provided a
construction start date of March 6, 2001. Since the construction contract required
completion of the project in 270 days, the contract between the Town and CAMO had
a completion date of December 1, 2001, which means that the project must be
“substantially complete” by the designated date. Basically, the contractor notifies the
owner that he is finished; the owner conducts a pre-final inspection, and issues a
Certificate of Substantial Completion.
In addition to the provision in the bid packet, the contract document
itself provided for liquidated damages in the form of a $500.00 per diem charge
against the contractor for every day that the project ran over the completion date on
the contract.
Free access — add to your briefcase to read the full text and ask questions with AI
STATE OF LOUISIANA COURT OF APPEAL, THIRD CIRCUIT
07-354
CAMO CONSTRUCTION CO., INC.
VERSUS
TOWN OF VIDALIA
**********
APPEAL FROM THE SEVENTH JUDICIAL DISTRICT COURT PARISH OF CONCORDIA, NO. 39589 HONORABLE LEO BOOTHE, DISTRICT JUDGE
ULYSSES GENE THIBODEAUX CHIEF JUDGE
Court composed of Ulysses Gene Thibodeaux, Chief Judge, Marc T. Amy, and Michael G. Sullivan, Judges.
AFFIRMED.
Ronald J. Fiorenza Provosty, Sadler, deLaunay, Fiorenza & Sobel P. O. Drawer 1791 Alexandria, LA 71309-1791 Telephone: (318) 445-3631 COUNSEL FOR: Defendant/Appellee - Town of Vidalia
Richard Brooks Easterling 450 Laurel Street - Suite 1900 Baton Rouge, LA 70801 Telephone: (225) 336-5200 COUNSEL FOR: Plaintiff/Appellant - CAMO Construction Co., Inc. THIBODEAUX, Chief Judge.
This case involves a contract dispute between the plaintiff-appellant,
CAMO Construction Company, Inc., (CAMO) and the defendant-appellee, the Town
of Vidalia (Town). In January of 2001, CAMO was awarded the contract for a street
improvement and drainage project in Vidalia, Louisiana which called for completion
in 270 days. The project was plagued with delays from the beginning and after two
extensions of time was still not complete. The Certificate of Substantial Completion
was issued 1007 days after the start date on the contract.
During construction, CAMO instituted a claim for extended overhead
and delay damages of $221,634.04, later reduced to $141,681.59. At the end of the
project, the Town rejected the claim and deducted $80,000.00 from CAMO’s last
payment as liquidated damages for 160 of the days that CAMO went beyond the last
approved extension date on the contract.
CAMO filed suit for breach of contract in April 2004 seeking to recover
the liquidated damages and the funds claimed for overhead and delay damages. After
a bench trial, the trial court found in favor of the Town and dismissed all of CAMO’s
claims. CAMO filed this appeal. For the reasons set forth below, we affirm the
judgment of the trial court.
I.
ISSUES
We must decide:
(1) whether the trial court erred in finding that CAMO Construction Company, Inc. was not entitled to additional payments for delays and extended overhead on the construction project for the Town of Vidalia; and (2) whether the trial court erred in finding that the Town was entitled to deduct from CAMO’s final payment liquidated damages for 160 days at $500.00 per day.
II.
FACTS AND PROCEDURAL HISTORY
In early January of 2001, the Town invited bids on a construction project
entitled, “Town of Vidalia 1999 Street Improvement Program, Phase II-Subsurface
Drainage.” The Town estimated that the project would require funds of
$2,445,016.00 and that the construction would take 270 days. CAMO Construction
submitted the lowest overall bid, at $2,165,976.50 and was awarded the contract. In
general, the project called for the installation of catch basins and various sizes of PVC
pipe in open ditches, and then required covering the installations with dirt and sod,
called “dressing up.” The new installations were tied into, and sometimes replaced,
existing subsurface drainage systems, at times requiring the breaking up and repair
of private driveways.
The contract documents called for “unit price” bids, not cost plus bids,
or price per hour bids. The bid forms were pre-printed with the description of each
item, the estimated quantity of that item needed for the project, and the measurement
unit for that item (linear foot, square yard, cubic yard, etc.). Blanks were provided
at the end of each line item for the contractor to write in his “unit price” bid and his
“total price” bid for that item. The contractors “unit price” bid was his price for each
item installed, that is, after installation. Therefore the “unit price” bid for each item
specifically included the cost of the material, the labor, the contractor’s overhead,
profit, taxes, insurance, bond premiums, equipment rentals, and any other contractor
costs associated with the installation.
2 For example, in one instance, 3,670 linear feet of fifteen-inch (15") inch
pipe, was bid by CAMO at $17.88 per linear foot installed. Although not shown on
the bid form, the purchase price (or unit rate) for this pipe was $5.60 per linear foot
at one time during the project. The $17.88 per unit bid by CAMO is called the “unit
price” and is then multiplied times the 3,670 linear feet indicated on the bid form, for
a “total price” bid of $65,619.60 for that item (15" pipe). The original bid form
contained eighteen (18) line items which included five sizes of corrugated PVC pipe,
catch basins, inline drains, driveway repair, asphalt street repair, sand/clay/gravel, and
other materials. Item 17 was a “utility relocation” lump sum cash allowance pre-set
on the bid form at $2,000.00. Item 18 asked for a lump sum bid for “mobilization.”
The pre-printed quantities on the bid form were estimates only. CAMO would be
paid for actual quantities installed based upon its “unit price” bid for each item.
Page two (2) of the bid packet signed by CAMO contained the following
language:
The Bidder, in compliance with your Advertisement for Bids . . . having examined the plans and specifications with related documents and the site of the proposed work, and being familiar with all of the conditions surrounding the construction of the proposed project including the availability of materials and labor, hereby proposes to furnish all labor, materials, and supplies, and to construct the project in accordance with the contract documents within the time set forth therein and at the prices stated below. These prices are to cover all expenses incurred in performing the work required under the contract documents, of which this proposal is a part.
....
BIDDER hereby agrees to commence WORK under this contract on or before a date to be specified in the written NOTICE TO PROCEED and to fully complete the PROJECT with[in] 270 consecutive calendar days thereafter. BIDDER further agrees to pay as liquidated damages, the sum of $500.00 for each consecutive calendar
3 day thereafter as provided in Section 9 of the Information for Bidders.
Bryant Hammett and Associates, the engineering firm, was responsible
for plan designs and drawings, materials lists, bid and contract documents and
specifications, and supervision and administration of the project. The only two
signatories on the two-page contract document setting forth the price, the completion
time, and the amount for liquidated damages, were the CONTRACTOR (CAMO
Construction) and the OWNER (Town of Vidalia through its Mayor, Hyram
Copeland).
The notice to proceed was issued on January 31, 2001, and provided a
construction start date of March 6, 2001. Since the construction contract required
completion of the project in 270 days, the contract between the Town and CAMO had
a completion date of December 1, 2001, which means that the project must be
“substantially complete” by the designated date. Basically, the contractor notifies the
owner that he is finished; the owner conducts a pre-final inspection, and issues a
Certificate of Substantial Completion.
In addition to the provision in the bid packet, the contract document
itself provided for liquidated damages in the form of a $500.00 per diem charge
against the contractor for every day that the project ran over the completion date on
the contract. However, the entire contract, which contained four parts – Contract and
Bid Documents, General Conditions, Special Conditions, and Technical
Specifications – provided specific mechanisms for adjusting the contract price and
the completion time, due to inevitable delays and unforseen costs as the project
progressed. Those mechanisms are defined under Section 1.01 on page one of the
General Conditions (GC-1) as a Change Order and a Claim, as follows:
4 9. Change Order – A document recommended by ENGINEER which is signed by CONTRACTOR and OWNER and authorizes an addition, deletion, or revision in the Work or an adjustment in the Contract Price or the Contract Times, issued on or after the Effective Date of the Agreement.
10. Claim – A demand or assertion by OWNER or CONTRACTOR seeking an adjustment of Contract Price or Contract Times, or both, or other relief with respect to the terms of the Contract. A demand for money or services by a third party is not a claim.
The project was besieged with delays from the beginning. CAMO began
ordering materials, and sent drawings for the catch basins and drain tops to the
fabricator for review when the notice to proceed was issued. It was soon discovered
that the catch basins could not be fabricated because the pipe to be installed was too
big to go in the basin elevations that had been supplied on the drawings by the
engineers. After lengthy discussions with the project engineer, CAMO was still
corresponding with the fabricator in mid-March 2001 about the various pipe sizes and
the minimum depth for the coordinating catch basins. CAMO did not begin
construction at the work site until June 11, 2001.
Once construction began, it became apparent that the eighteen-inch
(18") PVC pipe ordered pursuant to the plans and specifications was too large for the
intended ditches. Therefore, a large amount of this pipe was unusable. There were
also problems with the elevations prepared by surveyors with the engineering firm,
and CAMO could not tie the new pipe into the existing pipes and cross-drains.
CAMO began taking the elevations in the field and adjusting the pipe as it was laid.
This process is called “field engineering.” CAMO also encountered underground
gas, sewer, and water lines that were not accurately marked on the drawings,
requiring the relocation by the Town of some of the utilities, and circumvention by
CAMO of others. The project was far from completion by the original deadline of
5 December 1, 2001. On December 13, 2001, the engineering firm wrote CAMO
asking it to provide a written request for additional time to complete the project.
On December 20, 2001, with the Hammett firm’s recommendation,
Change Order No. 1 was issued granting an additional 200 days for completion of the
project, thereby extending the contract period to 470 calendar days, with a beginning
date of March 6, 2001 and a completion date of June 19, 2002. The reasons listed for
the change order were: (1) delays in material deliveries; (2) delays in material
fabrication; (3) extreme weather conditions; and, (4) conflicts with existing
underground utilities.
On January 29, 2002, Change Order No. 2 was issued due to a decision
by the Town to delete Bid Item 12 - “trench repairs with sod.” CAMO’s unit price
for that item was $87,108.00. Therefore, the contract price was reduced from
$2,165,976.50 to $2,078,868.50. CAMO had no objection to this deletion, and the
change order was approved. The contract time of 470 days remained the same, as did
the completion date of June 19, 2002.
Problems continued in 2002. CAMO met with Hammett in mid-January
to discuss the project needs. The conflicts with underground utilities, and problems
with inlets and catch basins continued. Too many catch basins had been ordered;
discussions were underway for a new design on the inlets; and CAMO suggested
modifying some of the extra basins in order to use them. At some point a switch was
made from concrete basins to plastic basins. There were continued delays due to
material fabrication. CAMO lost a month due to adverse weather conditions. The
Hammett engineering firm wrote CAMO twice in July of 2002, advising CAMO to
provide another written request for more time, since the contract had expired on June
19, 2002.
6 Change Order No. 3 was issued on September 3, 2002, two-and-a-half
months after the June 19, 2002 deadline. This change order added 320 days to the
original contract time, resulting in a contract period of 790 calendar days, from March
6, 2001 to May 5, 2003. The reasons for Change Order No. 3 were the same as those
stated on Change Order No. 1 - delays in material deliveries and material fabrication,
weather conditions, and conflicts with underground utilities.
Hammett had begun drawing new plan designs on August 30, 2002.
While the plan revisions were underway, CAMO could not install pipe but was able
to work on punch list items. CAMO reported the punch list complete on October 8
and requested the new drawings. Hammett sent the revised plan drawings and new
materials list on October 9, 2002. The revised plans called for the installation of
additional units of fifteen-inch (15") pipe and also added twelve-inch (12") pipe and
side drains to the project. Once the new materials were ordered, there were some
delays waiting for their delivery. The fifteen-inch (15") pipe had gone up in price by
$1.41 per linear foot since CAMO bid the job in January of 2001. The Town agreed
to pay CAMO the higher unit price on this bid item.
Change Order No. 4 was submitted on December 2, 2002, to increase
the contract price for four new line items, Items 19-22, for the installation of 6,895
linear feet of fifteen-inch (15") pipe, 870 linear feet of twelve-inch (12") pipe, 51 side
drains with pads and grates, and the 88 side drains on the punch list. Pursuant to this
change order, the contract price was increased by $280,164.65, which was CAMO’s
price for installing the new items, which were mostly the result of the plan revisions.
The change order also decreased the contract price due to deletions of certain items
for a net increase of $209,969.65. Originally, the deletions were incorrect, and the
change order was subsequently corrected to the price here stated. Change Order No.
7 4 brought the contract price up to $2,288,838.15. It did not add any days to the
contract, and the completion time remained at 790 days with the completion date of
May 5, 2003.
On December 13, 2002, CAMO wrote Hammett requesting the resolution
of five items revolving around CAMO’s extended overhead due to the delays and to
alleged costs associated with excessive field engineering. However, none of the
claims were quantified. CAMO considered the letter a claim and requested a meeting
the following week to discuss the specific items. The meeting took place, but it was
agreed that CAMO would keep working and the claims would be revisited.
On May 2, 2003, three days before the latest extension expired on May
5, 2003, Hammett wrote CAMO expressing the Town’s concern that the project
would not be completed that summer. Hammett noted the two previous time
extensions and asked CAMO to submit a completion schedule detailing the work
remaining and the time frame for completing the project. Hammett also asked CAMO
to submit a written explanatory request for more time.
CAMO responded in correspondence dated May 19, 2003, summarizing
the reasons for the previous extensions, but wanted to know whether streets
previously discussed as possible additions to the project were going to be added,
before providing a new extension time. CAMO never did provide a request in writing
to the engineer for an additional extension of time. In this letter of May 19, CAMO
also expressed concern about the outstanding issues in its December 13, 2002 letter.
In a separate letter dated the same day, CAMO asked for a new punch list. Hammett
mailed a four-and-one-half page punch list on June 20, 2003.
Several letters were exchanged between Hammett and CAMO between
July 17, 2003 and October 27, 2003. These communications prompted the Mayor to
8 instruct Hammett to attempt a compromise of the claim for extended overhead and
delay damages.
A meeting between Hammett and CAMO resulted in a reduction of these
claims from $221,634.04 to $141,681.59 and an additional claim for $20,926.44 for
removal of the leftover materials to the Town’s storage facility. This was confirmed
in writing on October 27, 2003. On October 30, 2007, CAMO requested from
Hammett a Certificate of Substantial Completion.
On November 19, 2003, the project engineer for Hammett, Keith
Capdepon, wrote CAMO referencing CAMO’s October 27, 2003 letter containing the
revised numbers and stating that the revised cost breakdown was approved. He
further indicated that a change order would be issued showing the cost breakdown
and adding it to the final estimate for payment.
On November 19, 2003, Change Order No. 5 was prepared and
subsequently signed by Bryant Hammett and CAMO, adding 217 days to the contract
period that had expired on May 5, 2003. This change order would result in a contract
period of 1007 calendar days and extend the contract completion date to December
8, 2003. Change Order No. 5 also contained a change in the contract price that
reflected the deletion of leftover, uninstalled materials, in the amount of $485,459.60,
and the addition of CAMO’s revised cost breakdown of $162,608.03. The new
contract price according to this change order was $1,985,986.58. However, Change
Order No. 5 was never signed by Mayor Copeland on behalf of the Town. While the
change order contains an issue date of November 19, Hammett was still trying to
confirm the figures with CAMO on December 13, 2003, and the change order was not
submitted to the Town by Hammett until December 17, 2003.
9 On November 26, 2003, the pre-final inspection that was attempted on
October 9, 2003, was rescheduled for December 9, 2003.
On December 8, 2003, Hammett generated a final punch list for CAMO,
and December 8, 2003 was determined to be the date of substantial completion of the
project. CAMO signed the Certificate of Completion on December 16, 2003.
On December 17, 2003, Hammett submitted correspondence to Mayor
Copeland attaching a twenty-third and final payment request and original Change
Order No. 5, both of which incorporated a $162,608.03 payment to CAMO for the
revised cost breakdown (extended overhead and delay costs of $141,681.59 plus
$20,926.44 for moving excess materials to storage). The December 17, 2003 letter
also attached Revised Change Order No. 4 as previously indicated.
On December 31, 2003, the Town’s comptroller, Kenneth J. Davis, wrote
CAMO, stating that the December 17, 2003 items had been reviewed for payment, but
more information was needed from the engineers before a final determination could
be made.
In January of 2004, the Town’s comptroller wrote CAMO indicating that
CAMO’s final payment would not include the $141,681.59 cost breakdown claimed
for extended overhead and delay damages, as the figures seemed arbitrary, and as the
contract was bid as a unit price contract. The letter stated that such a payment would
convert the contract to a cost plus contract and cause severe ramifications for the
Town. The Town further indicated that it would deduct the amount of $108,500.00
from CAMO’s final payment as liquidated damages for the 217 days that CAMO had
run over the contract period ($500.00 per day). The Town explained that its work
summaries indicated that CAMO had only worked 389 days on the project, and that,
10 even with an allowance for 107 rained out days, such a schedule did not justify the
217-day extension sought in Change Order No. 5.
On March 4, 2004, CAMO’s attorney wrote the City Attorney asserting
that CAMO’s records indicated 435 days on the job and that CAMO was entitled to
the extra cost because it based its bid on only 270 days of work. He indicated that
CAMO was not seeking additional costs for days not worked, or for delays caused by
waiting on materials and waiting on revised plans, but rather for extra days working
on the project due to delays beyond CAMO’s control.
On April 2, 2004, the Town comptroller, Mr. Davis, wrote CAMO’s
attorney presenting the Town’s adjustment to the Change Orders and the estimate for
payment number 23. The Town had deducted $80,000.00 for 160 days of liquidated
damages, instead of $108,500.00 for 217 days of damages for exceeding the contract
period, and had approved Revised Change Order No. 4. It had deleted the
$162,608.03 cost breakdown from Change Order No. 5 and from the estimate for
payment number 23, but indicated that it would pay the portion of that breakdown
that represented the cost of $20,926.44 for moving the leftover materials. It requested
that this amount be billed outside of the contract. Hence, CAMO’s claim for
extended overhead and delay damages was denied. The Town indicated that it had
issued a check to CAMO for a balance due of $207,168.65, which included a negative
balance of -$31,052.33 on the contract, due to the deduction of damages, and a
payment of plus $20,926.44 for moving the excess materials, and plus $217,568.10
for the installed price of the excess materials, which were paid outside the contract.
11 III.
LAW AND DISCUSSION
Standard of Review
An appellate court may not set aside a trial court’s findings of fact in
absence of manifest error or unless it is clearly wrong. Stobart v. State, Through
DOTD, 617 So.2d 880 (La.1993); Rosell v. ESCO, 549 So.2d 840 (La.1989). A two
tiered test must be applied in order to reverse the findings of the trial court:
a. the appellate court must find from the record that a reasonable factual basis does not exist for the finding of the trial court, and
b. the appellate court must further determine that the record establishes that the finding is clearly wrong (manifestly erroneous).
Mart v. Hill, 505 So.2d 1120 (La.1987).
Even where the appellate court believes its inferences are more
reasonable than the fact finders, reasonable determinations and inferences of fact
should not be disturbed on appeal. Arceneaux v. Domingue, 365 So.2d 1330
(La.1978). Additionally, a reviewing court must keep in mind that if a trial court’s
findings are reasonable based upon the entire record and evidence, an appellate court
may not reverse said findings even if it is convinced that had it been sitting as trier
of fact it would have weighed that evidence differently. Housely v. Cerise, 579 So.2d
973 (La.1991). The basis for this principle of review is grounded not only upon the
better capacity of the trial court to evaluate live witnesses, but also upon the proper
allocation of trial and appellate functions between the respective courts.
Claims for Extended Overhead and Delay Damages
CAMO contends that the trial court erred in finding that it was not
entitled to additional costs for extended overhead and delays beyond its control on
12 the construction project. The record reveals that the delays to which CAMO refers
began before the authorized start date on the contract of March 6, 2001. Yet, CAMO
did not provide a written request for compensation until December 13, 2002, after it
had received three change orders compensating CAMO in both time and price for the
costs and delays alleged.
More specifically, Mike Grantham, President of CAMO, testified that
around the time that the notice to proceed was issued on January 31, 2001, he began
ordering materials, and it was soon determined that the catch basins could not be
fabricated because the pipe to be installed was too big to go in the basin elevations.
Grantham had lengthy discussions with the engineers and the fabricator and wrote the
fabricator on March 15, 2001, regarding the various pipe sizes and the minimum
depth for the coordinating catch basins that were needed. Accordingly, he did not
begin construction until June 11, 2001. Once on the site it became apparent that the
eighteen-inch (18") pipe was too big and “riding out” of the ditches, and he began
running into underground utilities not accurately marked on the engineer’s drawings.
Grantham began making changes in the field, called “field engineering,”
from the very beginning. By September 3, 2002, Change Order No. 1 and Change
Order No. 3 had been issued giving him 200 and 320 additional days, respectively,
for a total of 520 additional days on the contract. The reasons for both change orders
were: (1) delays in material deliveries; (2) delays in material fabrication; (3) extreme
weather conditions; and, (4) conflicts with existing underground utilities. The
September 3, 2002 change order was accompanied by a cover letter from Bryant
Hammett specifically recommending the additional days. The drawings were being
revised at the time of the September 3, 2002 change order, and on December 2, 2002,
Change Order No. 4 was issued in order to compensate CAMO its quoted price of an
13 additional $280,164.65 for modifications and the installation of new materials due to
the changes in the plans not previously part of the original contract.
Eleven days later, on December 13, 2002, CAMO wrote Hammett the
letter, now being characterized as the claim. The letter requested resolution of: (1)
extended overhead for the delays listed in Hammett’s September 3, 2002 letter; (2)
delays due to conflicts with utilities and other obstructions; (3) delays due to work
stoppage for material revisions and deliveries; (4) costs due to excessive field
engineering for installation of pipe, catch basins, and inlets; (5) demobilization and
remobilization due to revision of drawings from August 30, 2002 to October 9, 2002.
The trial court agreed with the Town’s position that CAMO was granted
both time extensions and additional compensation for the items in the claim in three
previous change orders. Specifically, following two extensions of time in Change
Orders No. 1 and in Change Order No. 3, Change Order No. 4 increased the contract
by a net figure of $209,969.65 in order to pay CAMO $280,164.65 for the installation
of new material due to plan revisions and to pay CAMO its quoted price for
modifying some of the excess catch basins. Moreover, as the Town points out in its
brief, the Town paid CAMO for all of the excess catch basins that CAMO allegedly
ordered as a result of the duplication error on the plans. In fact, CAMO was paid the
installed price of the leftover materials.1 We also note that while the revisions during
construction led to the addition of certain installations to the original contract that
1 The evidence reveals that CAMO was paid the installed price of all of the leftover catch basins, pipe, and other materials that CAMO ordered and moved to the Town’s storage barn at the end of the project, even though CAMO did not actually install these materials. The cost of the leftover material was $173,967.50, and CAMO was paid $217,568.10 for the material, the difference being $15,222.16 (8.75%) for taxes, plus $28,378.45 (15%) for profit and overhead. Additionally, CAMO was paid its requested price of $20,652.88 for moving the material to storage. These payments to CAMO were not reflected in the change orders presumably because these materials were not installed as part of the project. CAMO was paid for these items outside of the contract. However, the unit price bid for these materials was included in the overall reductions in the contract price.
14 were not part of CAMO’s original bid, the revisions also caused the deletion of
certain installations that CAMO had bid in the original contract. That is the reason
for change orders – to document revisions in the work as it progresses, to adjust time
and prices as needed, and to pay the contractor his unit price for items actually
installed. In the end, in this case, there were more deletions than additions of work.
With regard to CAMO’s claim for cost of demobilization and
remobilization between August 30 and October 9 of 2002 while the engineers revised
the plan drawings, the Town’s comptroller gathered documentation from the project
engineer, Capdepon, stating that CAMO was working on a preliminary punch list
during that time in the Southern part of town where subsurface drainage had already
been installed and needed dressing up. Hammett testified at trial that his
understanding was that CAMO was working on a punch list except for about two
days during that time. This information is confirmed by CAMO’s letter from
Grantham to Capdepon, the project engineer, dated October 8, 2002, stating that “We
have completed the punch list . . . we are ready to proceed with the completion of the
project and are awaiting the revised drawings.” The following day, October 9, 2002,
a letter from Capdepon to Grantham encloses the requested drawings.
Moreover, Grantham testified at trial that during the plan revisions, they
could not install pipe so they dropped back and worked on punch list items. We note
that Change Order No. 4, issued on December 2, 2002 adds four Items to the contract,
Items 19-22. Items 19-21 are for the new installations pursuant to the revised plans
provided in October. The last item is described thusly: “Item 22 side drain (punch
list) were side drains installed by contractor after pipe had been laid.” Out of the total
of $280,164.65 paid to CAMO for the four additional items on Change Order No. 4,
Item 22 for the punch list items represents $88,484.00 of that amount.
15 We note that at the end of the project, the final contract price shown on
Revised Change Order No. 5 and on the final payment summary is $1,823,378.55,
which is less than CAMO’s bid of $2,165,976.50. This is because there were more
deletions of work due to revisions than additions to the work because of revisions.
We also note that, even though the final contract price was $1,823,378.55, the total
payments to CAMO were $1,981,599.53, due to the payment to CAMO for the
leftover materials. As is evident in the record, CAMO did not submit a price per hour
bid or a cost plus bid. The bid packet specifically invited only unit price bidding, and
the bid proposal is entitled “Bid for Unit Price Contracts.”
General Conditions to the Contract, Section 11.03, entitled “Unit Price
Work,” provides as follows:
A. Where the Contract Documents provide that all or part of the Work is to be Unit Price Work, initially the Contract Price will be deemed to include for all Unit Price Work an amount equal to the sum of the unit price for each separately identified item of Unit Price Work times the estimated quantity of each item as indicated in the Agreement. The estimated quantities of items of Unit Price Work are not guaranteed and are solely for the purpose of comparison of Bids and determining an initial Contract Price. Determinations of the actual quantities and classifications of Unit Price Work performed by CONTRACTOR will be made by ENGINEER subject to the provisions of paragraph 9.08.
B. Each unit price will be deemed to include an amount considered by CONTRACTOR to be adequate to cover CONTRACTOR’s overhead and profit for each separately identified item.
C. OWNER or CONTRACTOR may make a Claim for an adjustment in the Contract Price in accordance with paragraph 10.05 if:
1. the quantity of any item of Unit Price Work performed by CONTRACTOR differs materially and significantly from the estimated quantity of such item indicated in the Agreement; and
16 2. there is no corresponding adjustment with respect [to] any other item of Work; and
3. if CONTRACTOR believes that CONTRACTOR is entitled to an increase in Contract Price as a result of having incurred additional expense or OWNER believes that OWNER is entitled to a decrease in Contract Price and the parties are unable to agree as to the amount of any such increase or decrease.
(All emphasis ours.)
Based upon the foregoing, CAMO’s argument fails. Section 11.03(C)
provides that the contractor can make a claim for an adjustment in the contract price
in accordance to paragraph 10.05, which was not done in this case as explained more
fully below, if all three of conditions one (1) through three (3) are met. The second
condition, at Subsection (2), requires that there can be no other corresponding
adjustment with respect to any other item of work. As previously indicated, the
Town’s position is that previous change orders compensated CAMO for the changes
in the work. The trial court agreed. We also agree. The plans and drawings were
being revised by Hammett on August 30, 2002, and Change Order No. 3, granting
320 additional days to the contract, was dated September 3, 2002.
Testimony at trial indicated that the change orders requesting additional
time covered delays in the past and delays anticipated. Hence, in addition to Change
Order No. 1, granting 200 days for delays at the beginning of the contract in 2001,
Change Order No. 3, granting 320 days extension, compensates CAMO for delays
before, after, and at the time the plans were being revised in the fall of 2002.
Likewise, Change Order No. 4 compensates CAMO in the amount of $280,164.65 for
revisions and modifications in the work.
17 Pursuant to Section 12.05 of the General Conditions, delays beyond the
control of both owner and contractor are compensated by an extension of time equal
to the time lost, which “shall be the CONTRACTOR’s sole and exclusive remedy for
such delay.” Further, Section 12.06 provides that, “In no event shall OWNER or
ENGINEER be liable to CONTRACTOR . . . for damages arising out of . . . delays
. . . within the control of CONTRACTOR; or . . . delays beyond the control of both
OWNER and CONTRACTOR.” CAMO further argues that it should be compensated
in price for the delays caused by the conflicting underground utilities under Section
4.03(C) of the General Conditions. That section provides for contract changes in time
or price if subsurface conditions are unusual or materially different from conditions
ordinarily encountered or of such a nature as to establish material inaccuracies in the
technical data relied upon by the contractor. Again, since interference with
underground utilities started at the beginning of the work, Change Orders No. 1 and
No. 3 granted a total of 520 additional days for delays which specifically included
conflicts with underground utilities.
As to an increase in price due to those delays, paragraph 20 of page SC-6
of the Special Conditions in the contract, which override the General Conditions,
provides in pertinent part that, “The Contractor shall make his own investigations and
be fully responsible for locating and taking care not to damage any gas, water or
sewer lines. . . . In case that such physical properties conflict with the performances
of the contract, it shall be the Contractor’s responsibility to anticipate such conflicts
and to give advance notice thereof to the Owners.” (Emphasis added). In particular,
paragraph 21 of the Special Conditions at SC-7, entitled “Subsurface Conditions,”
provides: “Contractor shall make his own investigations of subsurface conditions.
No claims for extra compensation due to unusual conditions or development[s] that
18 are found to exist underground will be allowed.” (Emphasis added). Paragraph 9 at
SC-3, entitled “Site Investigation,” provides that the contractor is presumed to have
visited the site before bidding and to be thoroughly familiar with the nature and
location of the job, the equipment and quantities of materials needed, and that any
failure to acquaint himself with all available information “will not relieve him of
responsibility for estimating properly the difficulty or cost of successfully performing
this work.”
Section 2.05 of the General Conditions, entitled “Before Starting
Construction,” provides that “Before undertaking each part of the Work
CONTRACTOR shall carefully study and compare the Contract Documents and
check and verify pertinent figures therein and all applicable field measurements.”
Additionally, Section 4.04 of the General Conditions provides that
information shown or indicated in the contract documents with respect to existing
underground facilities is based on information and data furnished by the owners of
such underground facilities, and unless otherwise expressly provided in the
Supplementary Conditions, the OWNER and ENGINEER “shall not be responsible
for the accuracy or completeness of any such information or data.” It further provides
that the cost of reviewing and checking all such information, locating all underground
facilities, and coordinating the work during construction with the owners of the
utilities, “will be included in the Contract Price” and shall be the full responsibility
of the contractor.
Likewise, paragraph 11 on page 02221-4 of the Technical Specifications
of the contract provides that “it is solely the Contractor’s responsibility to verify the
exact location, number of utilities, number of lines, etc., prior to beginning
construction.”
19 Moreover, Section 11.03(C) and Section 4.03, and every other section
of the General Conditions dealing with the filing of a claim, whether for changes to
contract times or contract prices, requires that the claim be filed in accordance with
Section 10.05 of the General Conditions. Section 10.05 requires that written notice
of a claim “shall be delivered by the claimant to ENGINEER and the other party to
the Contract promptly (but in no event later than 30 days) after the start of the event
giving rise thereto.” CAMO did not comply with this requirement. CAMO waited
until December 13, 2002, eleven days after Change Order No. 4 was issued, to
provide written notice of events that started at the very beginning of the contract. The
final subsection - D - of Section 10.05, at page GC-27, provides that “No Claim for
an adjustment in Contract Price or Contract Times (or Milestones) will be valid if not
in accordance with this paragraph 10.05.”
CAMO has made much of the fact that on December 17, 2003, Hammett
sent a cover letter to the Mayor attaching the original proposed Change Order No. 5,
showing a 217-day extension to December 8, 2003, and showing an increase in the
contract price for the claim of extended overhead and delay damages. Therefore,
CAMO argues that Hammett’s signature on the change order constitutes a written
recommendation from the engineer that was binding upon the Town pursuant to
General Condition 9.08, which provides:
A. ENGINEER will determine the actual quantities and classifications of Unit Price Work performed by CONTRACTOR. ENGINEER will review with CONTRACTOR the ENGINEER’s preliminary determinations on such matters before rendering a written decision thereon (by recommendation of an Application for Payment or otherwise). ENGINEER’s written decision thereon will be final and binding (except as modified by ENGINEER to reflect changed factual conditions or more accurate data) upon OWNER and CONTRACTOR, subject to the provisions of paragraph 10.05.
20 As a threshold matter, the claim for extended overhead and delay
damages was not for quantities of unit price work performed, nor did CAMO submit
a proper claim under Section 10.05. Therefore, Section 9.08 is inapplicable. CAMO
was paid for every unit of pipe or other material that it installed. With regard to
having CAMO’s crew and equipment on the job longer than Grantham anticipated
when he bid the job, that is covered in the numerous sections requiring CAMO to
anticipate and include all such delays and underground obstructions in his bid price.
Hammett testified that during his 22 years as a project engineer, working on hundreds
of projects, he had never heard of a contractor being paid “extended overhead.”
Hammett further testified that he never made a final decision as to
whether CAMO had submitted a claim entitling it to additional money under the
contract, nor did he investigate or make any determinations regarding the validity of
CAMO’s claim. He testified that CAMO’s methodology for calculating equipment
rentals and some of the percentages seemed fair. However, the charge for one or two
man hours a day and increased cost of labor was completely arbitrary and not based
on anything. Hammett indicated that he had been instructed to try to work out
something with Grantham, and after meeting with him, Grantham reduced the
disputed portion of the claim, and Hammett presented the reduced amount in the
change order simply because he knew that it was the lowest that Grantham would go.
Hammett specifically stated that he told Grantham numerous times
throughout their discussions that he (Hammett) did not have the final say on the
claim. Moreover, Section 10.03 of the General Conditions provides that the Owner
and Contractor shall execute “appropriate” change orders recommended by the
engineer covering changes in the contract price or contract times “which are agreed
21 to by the parties” and “which embody the substance of any written decision rendered
by ENGINEER pursuant to paragraph 10.05.”
As stated, there was no written decision by Hammett pursuant to Section
10.05; indeed, there was no proper claim submitted pursuant to Section 10.05. There
was clearly no agreement by the parties since the Town refused to execute the original
proposed Change Order No. 5 and instructed Hammett to revise it, deleting the claim
for compensation and the 217-day extension of time.
In finding that CAMO had been compensated for its claims in time
extensions and price increases in previous change orders, the trial court concluded
it was well settled that after adjustments have been negotiated to a contract and
agreed upon by all parties, one party cannot subsequently seek additional relief. For
that proposition, the court cited Circle, Inc. v. Board of Supervisors, Sewerage
District No. 2, St. Bernard Parish, 387 So.2d 606 (La.App. 4 Cir.), writ denied, 394
So.2d 613 (La.1980). CAMO attempted to distinguish the case, but provided no
supporting precedent of its own. Contrary to CAMO’s assertion otherwise, the issues
and holding in Circle are quite analogous to this case. The 1967 contract in Circle
was a unit price contract. After construction on a public sewerage contract began, the
contractor encountered unexpected soil changes and obstructions to installation of the
line requiring changes to the proposed construction plan.
Accordingly, the parties in Circle negotiated a change order that
increased the contract time by 56 days and the contract price by $3,020.01 as
compensation for the relocation of some lines and the redesign of others.
Subsequently, the contractor sued for additional amounts for the extra work, delays,
and changes in the contract. The court determined that the change order involved the
entire contractual obligation and was a compromise between the parties after
22 negotiation, and therefore had the force of law. The court in Circle articulated that
the contractor may have made a bad bargain, but he had made a legally binding
bargain. The fact that the change order also provided that the cost for the work could
not exceed the contract amount plus a five percent contingency does not create an
“entirely different situation” as CAMO suggests.
Nor does CAMO’s assertion that the previous change order in Circle was
dissimilar to the previous change orders in the present case because it was reached
only after considerable negotiation and exploration. Change Orders No. 1, 3 and 4,
in the present case were certainly the result of much deliberation and extensive
calculations, and because they were signed by both of the parties to the contract,
CAMO and the Town, they were binding. Further, contrary to CAMO’s assertions,
the proposed Change Order No. 5 in the present case was not binding because it was
not signed by both parties to the contract in that the Mayor never endorsed it.
Accordingly, we find no manifest error in the trial court’s judgment dismissing
CAMO’s claim for additional compensation for extended overhead and delay
damages under the contract.
CAMO’s Claim for Additional Time
CAMO further contends that the trial court erred in finding that CAMO
was not entitled to the 217 additional days on the contract as indicated in Hammett’s
December 2003 letter to the Town. The record reveals that the Certificate of
Substantial Completion signed by CAMO was issued with a substantial completion
date of December 8, 2003. On December 17, 2003, nine days after the date on the
Certificate of Completion, Bryant Hammett submitted a proposed Change Order No.
5 to the Town that included the request for the 217 additional days that had already
been consumed, and the Town declined to grant the extension. The previous
23 extension of time approved by the Town had expired on May 5, 2003, pursuant to
Change Order No. 3. Hence, these final 217 days requested would cover the period
from May 5, 2003 to December 8, 2003 and prevent the assessment of the $500.00
per-day liquidated damages called for under the contract.
CAMO argues that it should have been granted the 217-day extension
because CAMO relied on a pattern established during construction wherein Hammett
would ask CAMO to submit a request for time, CAMO would comply, Hammett
would write up the change order, and the Town would approve it, and that Change
Order No. 5 should have been no different. More specifically, CAMO’s appellate
brief to this court provides: “Each time the current time period would be close to
expiring, the engineers would write CAMO and ask CAMO to request additional
time.” This is not an accurate statement. The pattern that had been established was
one wherein CAMO would fail to request an extension, as required under the
contract, and the Hammett firm would somewhat paternalistically carry CAMO
through the process, after the previous extension had already expired.
The record reveals that the initial completion date under the contract for
270 days was December 1, 2001. On December 13, 2001, the project engineer,
Capdepon, wrote to Mike Grantham as follows: “This correspondence is to advise
you that the contract time for the above captioned project expired on December 1,
2001. Please submit to us, in writing, a request for more contract time for the
completion of this project.” Grantham complied with this request by correspondence
dated December 20, 2001. The result was the Town’s approval of Change Order No.
1, dated December 20, 2001, granting 200 additional days from the December 1st
expiration date.
24 The new expiration date, pursuant to Change Order No. 1 was June 19,
2002. On July 8, 2002, Capdepon wrote Grantham an almost identical letter advising
him that the contract had expired on June 19, 2002, and asking for a written request
for more contract time, and an explanation for the extension. CAMO did not respond.
On July 30, 2002, Capdepon again wrote Grantham with the identical language as the
July 8th letter, asking for a written request for time. On August 1, 2002, Grantham
wrote Capdepon regarding the June 19th expiration date, indicating that he did not
know the extent of remaining changes due to obstructions, and he therefore did not
enter a request for time. There must have been verbal discussions, because on
September 3, 2002, Bryant Hammett wrote the Mayor recommending a 320-day
extension to the contract, and attaching Change Order No. 3.
Change Order No. 3, dated September 3, 2002, extended the contract
expiration date from June 19, 2002 to May 5, 2003. Revised plans were being drawn
up simultaneously with Change Order No. 3, indicating that the Town looked for
completion of the project on the date of May 5, 2003, as provided for therein. On
December 2, 2002, when Change Order No. 4 was issued for the $280,164.65
increase in contract price for CAMO’s quote on the additional Items 19-22, most of
which were due to the plan revisions, there was no request for additional time, and
the expiration date of Change Order No. 3 remained the same, May 5, 2003.
For the first time, on May 2, 2003, three days before the expiration date
of the May 5, 2003 deadline, Bryant Hammett wrote Grantham in advance that there
was “a growing anxiety among town officials and the Mayor that the work initially
begun will not be completed this summer.” The second paragraph reminded
Grantham of the specifics of the previous extensions and change orders and then
stated, “To date this project is not finished.” In the third paragraph, Hammett asked
25 Grantham to submit “a completion project schedule detailing the work remaining and
time frame for completing this project.” He then asked for a written request for more
time, with an explanation, and asked for Grantham’s help in completing the project
in a timely manner due to the inconvenience the project was causing the residents.
On May 19, 2003, two weeks after the expiration of the contract on May
5, 2003, Grantham responded to Hammett’s May 2nd correspondence, providing
reasons for the previous extensions and expressing his own anxiety over his
December 2002 letter asking for extended overhead and delay damages. Grantham
still did not request an extension time, stating that in order to do that he would need
to know whether the additional streets discussed the previous year were going to be
added. At trial, Grantham testified that, at that point in time, he did not know how
much time to ask for, so he did not put a time in the letter.
In another letter dated the same day, May 19, 2003, Grantham wrote
Capdepon, asking for a punch list of items to be addressed, and asked that any
additional streets should be made part of the punch list. On June 20, 2003, Capdepon
sent Grantham the punch list comprised of four-and-a-half pages of items to be
completed, but the additional streets were not added. Grantham was still laying pipe
when he received the punch list. The record contains no evidence that Grantham ever
provided the engineers with a written request for an extension of time, though there
is correspondence regarding his claim for extended overhead and delay damages in
October 2003.
Section 12.02(A) of the General Conditions provides that the contract
times may only be changed by a change order or written amendment, and, any claim
for an adjustment in contract times “shall be based on written notice submitted by the
party making the claim to the ENGINEER and the other party to the Contract in
26 accordance with the provisions of paragraph 10.05.” CAMO did not comply with
Section 12.02(A) under its own volition for the first two extensions of time. Rather,
it had to be asked to comply after the expiration of the contract. That was the actual
pattern that had been established. For what might have been the third extension of
time, even though he was pleaded with prior to the final expiration on May 5, 2003,
CAMO never provided the written request to the engineers as required.
Section 12.02(B) provides that any adjustment to the contract times will
be in accordance with the provisions of Article 12. Section 12.04 provides that the
contract times will not be extended due to delays within the control of the contractor.
Even though the engineers, Hammett and Capdepon, took full responsibility for their
drawings, the Town’s position is that CAMO was granted 520 additional days on the
contract for delays beyond its control, and that some of the delays were the fault of
CAMO, including its failure to verify information in advance and to allow for
interference with utilities in its bid as required by the contract. Moreover, the Town’s
information demonstrated that out of the 1007 days between the contract start date
and the Certification of Completion date, CAMO was on the site for only 392 days,
and that only around 100 days were attributable to rain-out days. CAMO argued that
its records indicated 435 days on the job, asserting that the Town failed to include wet
days following the rain-out days and failed to include the work done prior to the
beginning of construction. The trial court agreed with the Town’s position, and the
record supports the trial court’s findings.
With regard to the proposed Change Order No. 5 that Hammett and
CAMO signed requesting a 217-day extension of time and the price increase for
extended overhead and delay damages, the Town apparently did not receive the
request until December 17, 2003, when Hammett attached it to his cover letter of the
27 same date. By that time, the 217 days had already expired, and the completion
certificate had been executed. Once the Town received the request, it began to
investigate, and found that the reports did not support either the time extension or the
price increase requested pursuant to CAMO’s claim for extended overhead and delay
damages. Therefore, the Town never signed or approved the original proposed
Change Order No. 5. For all of the reasons discussed above, proposed Change Order
No. 5 was not binding. Therefore, the Town was authorized under the contract to
deduct liquidated damages for the unapproved 217 days between the contract
expiration date on Change Order No. 3, which was May 5, 2003, and the date on the
Certificate of Substantial Completion, which was December 8, 2003.
CAMO argues that if it is found liable for liquidated damages, that such
damages should not be imposed beyond September 8, 2003, at which time it sent
correspondence to Capdepon that the pipe was installed pursuant to the drawings and
that CAMO was currently working on punch list items and dressing up recently
installed piping. However, the record also reveals that CAMO did not request the
Certificate of Substantial Completion until October 30, 2003. The Town chose to
impose liquidated damages only to October 12, 2003, which was a date nearer to the
first date scheduled for the pre-final inspection, which was October 9, 2003, pursuant
to Capdepon’s letter to the Mayor. The record indicates that the pre-final inspection
had to be rescheduled to December 8, 2003. Notwithstanding, the Town still chose
to deduct only 160 days of liquidated damages through October 12, 2003, for a total
of $80,000.00. The trial court determined that this was more than fair. We find no
manifest error in its judgment.
28 IV.
CONCLUSION
Based upon the foregoing, we affirm the trial court’s judgment
dismissing CAMO’s claims for additional compensation for extended overhead and
delay damages and for additional time on the subject contract with the Town of
Vidalia. All costs of this appeal are assessed against plaintiff-appellant, CAMO
Construction Co., Inc.
Camo Construction Co., Inc. v. Town of Vidalia (Camo Construction Co., Inc. v. Town of Vidalia) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.