CAMO CONST. CO., INC. v. Town of Vidalia

966 So. 2d 796, 2007 La. App. LEXIS 1835, 2007 La.App. 3 Cir. 354
Louisiana Court of Appeal·Decided October 3, 2007·No. 2007-354·Published

Opinion

966 So.2d 796 (2007)

CAMO CONSTRUCTION CO., INC.
v.
TOWN OF VIDALIA.

No. 2007-354.

Court of Appeal of Louisiana, Third Circuit.

October 3, 2007.

*797 Ronald J. Fiorenza, Provosty, Sadler, deLaunay, Fiorenza & Sobel, Alexandria, LA, for Defendant/Appellee-Town of Vidalia.

Richard Brooks Easterling, Baton Rouge, LA, for Plaintiff/Appellant-CAMO Construction Co., Inc.

Court composed of ULYSSES GENE THIBODEAUX, Chief Judge, MARC T. AMY, and MICHAEL G. SULLIVAN, Judges.

*798 THIBODEAUX, Chief Judge.

This case involves a contract dispute between the plaintiff-appellant, CAMO Construction Company, Inc. (CAMO) and the defendant-appellee, the Town of Vidalia (Town). In January of 2001, CAMO was awarded the contract for a street improvement and drainage project in Vidalia, Louisiana which called for completion in 270 days. The project was plagued with delays from the beginning and after two extensions of time was still not complete. The Certificate of Substantial Completion was issued 1007 days after the start date on the contract.

During construction, CAMO instituted a claim for extended overhead and delay damages of $221,634.04, later reduced to $141,681.59. At the end of the project, the Town rejected the claim and deducted $80,000.00 from CAMO's last payment as liquidated damages for 160 of the days that CAMO went beyond the last approved extension date on the contract.

CAMO filed suit for breach of contract in April 2004 seeking to recover the liquidated damages and the funds claimed for overhead and delay damages. After a bench trial, the trial court found in favor of the Town and dismissed all of CAMO's claims. CAMO filed this appeal. For the reasons set forth below, we affirm the judgment of the trial court.

I.

ISSUES

We must decide:

(1) whether the trial court erred in finding that CAMO Construction Company, Inc. was not entitled to additional payments for delays and extended overhead on the construction project for the Town of Vidalia; and
(2) whether the trial court erred in finding that the Town was entitled to deduct from CAMO's final payment liquidated damages for 160 days at $500.00 per day.

II.

FACTS AND PROCEDURAL HISTORY

In early January of 2001, the Town invited bids on a construction project entitled, "Town of Vidalia 1999 Street Improvement Program, Phase II-Subsurface Drainage." The Town estimated that the project would require funds of $2,445,016.00 and that the construction would take 270 days. CAMO Construction submitted the lowest overall bid, at $2,165,976.50 and was awarded the contract. In general, the project called for the installation of catch basins and various sizes of PVC pipe in open ditches, and then required covering the installations with dirt and sod, called "dressing up." The new installations were tied into, and sometimes replaced, existing subsurface drainage systems, at times requiring the breaking up and repair of private driveways.

The contract documents called for "unit price" bids, not cost plus bids, or price per hour bids. The bid forms were pre-printed with the description of each item, the estimated quantity of that item needed for the project, and the measurement unit for that item (linear foot, square yard, cubic yard, etc.). Blanks were provided at the end of each line item for the contractor to write in his "unit price" bid and his "total price" bid for that item. The contractors "unit price" bid was his price for each item installed, that is, after installation. Therefore the "unit price" bid for each item specifically included the cost of the material, the labor, the contractor's overhead, profit, taxes, insurance, bond premiums, equipment rentals, and any other *799 contractor costs associated with the installation.

For example, in one instance, 3,670 linear feet of fifteen-inch (15") inch pipe, was bid by CAMO at $17.88 per linear foot installed. Although not shown on the bid form, the purchase price (or unit rate) for this pipe was $5.60 per linear foot at one time during the project. The $17.88 per unit bid by CAMO is called the "unit price" and is then multiplied times the 3,670 linear feet indicated on the bid form, for a "total price" bid of $65,619.60 for that item (15" pipe). The original bid form contained eighteen (18) line items which included five sizes of corrugated PVC pipe, catch basins, inline drains, driveway repair, asphalt street repair, sand/clay/gravel, and other materials. Item 17 was a "utility relocation" lump sum cash allowance pre-set on the bid form at $2,000.00. Item 18 asked for a lump sum bid for "mobilization." The pre-printed quantities on the bid form were estimates only. CAMO would be paid for actual quantities installed based upon its "unit price" bid for each item.

Page two (2) of the bid packet signed by CAMO contained the following language:

The Bidder, in compliance with your Advertisement for Bids . . . having examined the plans and specifications with related documents and the site of the proposed work, and being familiar with all of the conditions surrounding the construction of the proposed project including the availability of materials and labor, hereby proposes to furnish all labor, materials, and supplies, and to construct the project in accordance with the contract documents within the time set forth therein and at the prices stated below. These prices are to cover all expenses incurred in performing the work required under the contract documents, of which this proposal is a part.
. . . .
BIDDER hereby agrees to commence WORK under this contract on or before a date to be specified in the written NOTICE TO PROCEED and to fully complete the PROJECT with[in] 270 consecutive calendar days thereafter. BIDDER further agrees to pay as liquidated damages, the sum of $500.00 for each consecutive calendar day thereafter as provided in Section 9 of the Information for Bidders.

Bryant Hammett and Associates, the engineering firm, was responsible for plan designs and drawings, materials lists, bid and contract documents and specifications, and supervision and administration of the project. The only two signatories on the two-page contract document setting forth the price, the completion time, and the amount for liquidated damages, were the CONTRACTOR (CAMO Construction) and the OWNER (Town of Vidalia through its Mayor, Hyram Copeland).

The notice to proceed was issued on January 31, 2001, and provided a construction start date of March 6, 2001. Since the construction contract required completion of the project in 270 days, the contract between the Town and CAMO had a completion date of December 1, 2001, which means that the project must be "substantially complete" by the designated date. Basically, the contractor notifies the owner that he is finished; the owner conducts a pre-final inspection, and issues a Certificate of Substantial Completion.

In addition to the provision in the bid packet, the contract document itself provided for liquidated damages in the form of a $500.00 per diem charge against the contractor for every day that the project ran over the completion date on the contract. However, the entire contract, which contained four parts — Contract and Bid Documents, General Conditions, Special *800 Conditions, and Technical Specifications — provided specific mechanisms for adjusting the contract price and the completion time,

Free access — add to your briefcase to read the full text and ask questions with AI

CAMO CONST. CO., INC. v. Town of Vidalia, 966 So. 2d 796, 2007 La. App. LEXIS 1835, 2007 La.App. 3 Cir. 354 (La. Ct. App. 2007).

966 So. 2d 796 (CAMO CONST. CO., INC. v. Town of Vidalia) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Stobart v. State Through DOTD
617 So. 2d 880 (Supreme Court of Louisiana, 1993)
Arceneaux v. Domingue
365 So. 2d 1330 (Supreme Court of Louisiana, 1978)
Rosell v. Esco
549 So. 2d 840 (Supreme Court of Louisiana, 1989)
Housley v. Cerise
579 So. 2d 973 (Supreme Court of Louisiana, 1991)
Mart v. Hill
505 So. 2d 1120 (Supreme Court of Louisiana, 1987)
Circle, Inc. v. Board of Supervisors, Sewerage District No. 2
387 So. 2d 606 (Louisiana Court of Appeal, 1980)