Camino Real Developers, LLC; Jack Dyer; And Dan Addante v. Tim Adkins and RivenRock, LLC

CourtCourt of Appeals of Texas
DecidedApril 30, 2025
Docket03-23-00233-CV
StatusPublished

This text of Camino Real Developers, LLC; Jack Dyer; And Dan Addante v. Tim Adkins and RivenRock, LLC (Camino Real Developers, LLC; Jack Dyer; And Dan Addante v. Tim Adkins and RivenRock, LLC) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Camino Real Developers, LLC; Jack Dyer; And Dan Addante v. Tim Adkins and RivenRock, LLC, (Tex. Ct. App. 2025).

Opinion

TEXAS COURT OF APPEALS, THIRD DISTRICT, AT AUSTIN

NO. 03-23-00233-CV

Camino Real Developers, LLC; Jack Dyer; and Dan Addante, Appellants

v.

Tim Adkins and RivenRock, LLC, Appellees

FROM THE 421ST DISTRICT COURT OF CALDWELL COUNTY NO. 21-0-359, THE HONORABLE CHRIS SCHNEIDER, JUDGE PRESIDING

MEMORANDUM OPINION

Dan Addante and Jack Dyer, who were defendants in the suit below, and Camino

Real Developers, LLC, an intervenor in the suit below, all appeal the trial court’s judgment,

rendered after a bench trial. The court rendered judgment for Tim Adkins and RivenRock, LLC

on their claim for breach of contract, by which they sought specific performance, and on their

claims for declaratory relief, but the trial court denied all their other claims—fraudulent

inducement, breach of fiduciary duty, tortious interference with prospective contractual relations,

involuntary winding up and termination, quantum meruit, unjust enrichment, promissory estoppel,

and claims for other injunctive relief. In six appellate issues, Addante and Dyer seek reversal

of the judgment on the contract and declaratory-relief claims, including reversal of the

specific-performance relief awarded, offering several reasons for why Adkins and RivenRock

cannot recover in contract. We agree with Addante and Dyer that Adkins and RivenRock cannot recover in contract because the parties agreed to a condition precedent to contract formation and

that condition was unmet. Thus, we reverse all challenged portions of the trial court’s judgment

and render judgment that Adkins and RivenRock take nothing on their contract claims and on most

of their declaratory-relief claims.1

BACKGROUND

Addante and Dyer developed a business idea for building and operating a luxury

RV park along a road in Caldwell County called Camino Real. They formed Camino Real

Developers, LLC for the project, with Camino Real’s Company Agreement going into effect in

late 2017. In accordance with the Company Agreement, one of Camino Real’s members—

JLR Mansions, LLC—would be responsible for much of the LLC’s capital funding.

JLR Mansions owned a 50% membership interest in the LLC. Addante and Dyer were the other

two members, each owning a 25% membership interest. JLR Mansions was run by Josh Dikoff.

Dikoff came to doubt JLR Mansions’ ability to keep meeting Camino Real’s

funding needs, including the monthly payments on its land note, so Addante and Dyer began

looking for someone to take JLR Mansions’ place in the project. Addante approached Jeff Ballard

1 There is one item of declaratory relief awarded by the trial court’s judgment that is not challenged by the appellants’ issues—a declaration “that RivenRock LLC owns a 50% membership interest in Camino Real Developers, LLC.” Also, no one challenges the portions of the judgment that deny all other claims in the suit, that is, Adkins and RivenRock’s other claims and Addante and Dyer’s and Camino Real’s counterclaims, and that order each side to bear their own fees and costs. We affirm these unchallenged portions of the judgment. See Bass v. Bogle, No. 03-23-00319-CV, 2024 WL 3446921, at *7 (Tex. App.—Austin July 18, 2024, no pet.) (mem. op.) (“As a preliminary matter, we address the portions of the final judgment that are not challenged on appeal. Specifically, no party has challenged [two portions of the judgment]. Because they are unchallenged on appeal, we affirm those portions of the final judgment.”); Elliott v. Rockwood Vill. Partners, Ltd., No. 03-12-00298-CV, 2012 WL 6554826, at *8 (Tex. App.— Austin Dec. 12, 2012, no pet.) (mem. op.) (“The remaining portions of the district court’s judgment were not challenged on appeal and are therefore affirmed.”).

2 about taking over the funding role in the project. In the midst of their discussions, Addante in

early August 2018 emailed Ballard, copying Dyer, a document titled “Financial Scope Recap.”

The Recap is addressed as a letter to Ballard from Addante, with Camino Real’s

name appearing just below Addante’s in the signature block. The Recap, according to its

beginning, “summarizes the financial scope of the project” and gives “a snapshot of our anticipated

costs, returns, phased build out and financial costs/stakes/responsibilities to move forward.” The

Recap then discusses a sale of JLR Mansions’ 50% membership interest in Camino Real and the

buyer of that interest’s assuming “all current liabilities of the Business of the Company . . . .” The

Recap gives details under headings titled “Current LLC expenses,” “Project Costs and Buildout

Schedule,” “Project Design / Preconstruction,” and “Investor Responsibilities.” And under that

last heading, the Recap says: “Complete financial funding and liability throughout construction

and park operation. The financial partner will have 50% revenue stake as well as 2/3 dictating

vote of financial and larger operation matters. All other management and operation duties will be

the sole responsibility of 2 other members.”

Discussions continued among Addante, Dyer, and Ballard, and Adkins was soon

brought in. Adkins and Ballard were the co-owners of RivenRock. A week after Addante emailed

the Recap to Ballard, Dyer emailed it to Adkins. The Recap, Adkins testified at trial, was the first

written communication about Camino Real that he ever saw. Discussions continued.

The day after the Dyer–Adkins email, Addante emailed Adkins, copying Dyer

and Ballard, to send two items—(1) the Recap and (2) a letter of intent with the filename

“LOI - Ballard.” Addante described in his email the “attachments below: our current LLC, original

LOI and the financial/timeline project overview.”

3 Eleven days later, in late August 2018, Adkins emailed Addante, copying Ballard,

to return a signed copy of a slightly edited version of the letter of intent, substantially the same in

terms as the document named “LOI – Ballard.” The edited document bore a new date and included

Adkins as an addressee alongside Ballard, among other changes not relevant here. Adkins had

signed this revised letter of intent. (We refer to this document signed by Adkins as the “LOI.”)

Adkins admitted in his trial testimony that “there’s some overlap” between the LOI’s terms and

the Recap’s. Also in the LOI was language calling for a “definitive agreement” among the parties:

2. Definitive Agreement

The closing will be subject to the negotiation and execution of definitive transaction documents that will include, among other things, customary representations, warranties, covenants, and indemnities by [Camino Real] and their principals regarding the business, operations, and financial condition of the Business.

....

4. Conditions to Closing

The consummation of the Transaction will be subject to the satisfaction of customary conditions, including, without limitation . . . [t]he negotiation, execution, and delivery of definitive agreements satisfactory to each of the parties . . . .

5. Binding Agreement

Other than this paragraph 5, which is intended to be and is legally binding, this letter is nonbinding and constitutes an indication of intent only and creates no liability or obligation of any nature whatsoever among the parties hereto with respect to any contemplated transaction or any other matter or action described or referred to herein.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

In Re Kellogg Brown & Root, Inc.
166 S.W.3d 732 (Texas Supreme Court, 2005)
In Re Laibe Corp.
307 S.W.3d 314 (Texas Supreme Court, 2010)
Lopez v. Muñoz, Hockema & Reed, L.L.P.
22 S.W.3d 857 (Texas Supreme Court, 2000)
Fort Worth Independent School District v. City of Fort Worth
22 S.W.3d 831 (Texas Supreme Court, 2000)
Texas Disposal Systems Landfill, Inc. v. Waste Management Holdings, Inc.
219 S.W.3d 563 (Court of Appeals of Texas, 2007)
Clear Lake City Water Authority v. Kirby Lake Development, Ltd.
123 S.W.3d 735 (Court of Appeals of Texas, 2003)
Republic Insurance Co. v. Davis
856 S.W.2d 158 (Texas Supreme Court, 1993)
Skelton v. Washington Mutual Bank, F.A.
61 S.W.3d 56 (Court of Appeals of Texas, 2001)
Central Power & Light Co. v. Del Mar Conservation District
594 S.W.2d 782 (Court of Appeals of Texas, 1980)
Stable Energy, L.P. v. Newberry
999 S.W.2d 538 (Court of Appeals of Texas, 1999)
Oppenheimer & Co. v. Oppenheim, Appel, Dixon & Co.
660 N.E.2d 415 (New York Court of Appeals, 1995)
WTG Gas Processing, L.P. v. ConocoPhillips Co.
309 S.W.3d 635 (Court of Appeals of Texas, 2010)
Emmons v. Ingebretson
279 F. Supp. 558 (N.D. Iowa, 1968)
Sun Exploration and Production Co. v. Benton
728 S.W.2d 35 (Texas Supreme Court, 1987)
Veal v. Thomason
159 S.W.2d 472 (Texas Supreme Court, 1942)
Freeman v. Magnolia Petroleum Co.
171 S.W.2d 339 (Texas Supreme Court, 1943)
Craig v. Tejas Promotions, LLC
550 S.W.3d 287 (Court of Appeals of Texas, 2018)

Cite This Page — Counsel Stack

Bluebook (online)
Camino Real Developers, LLC; Jack Dyer; And Dan Addante v. Tim Adkins and RivenRock, LLC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/camino-real-developers-llc-jack-dyer-and-dan-addante-v-tim-adkins-and-texapp-2025.